Surety's
Interest Page3

Extended
consideration and analysis has been given to cases similar to the one
here in several of the cited cases and little purpose would be served by
extensively reviewing said authorities. For a compilation of applicable
authorities and legal theories see Wolverine Ins. Co. v. Phillips,
supra.
The
United States
relies on the cases of Phoenix Indemnity Co. v. Earle, 9 Cir.,
218 Fed. (2d) 645 [55-1USTC ¶9179]; and U. S. v. R. F. Ball Const.
Co., 355
U. S.
587, 78 S. Ct. 442 [58-1 USTC ¶9327]. It appears that the result in the
first cited case was controlled by the sovereign character of the United
States and the provisions of the Bankruptcy Act, neither of which
factors are material in this case. In the Ball case the fund in
question was admittedly property of the delinquent taxpayer and the only
question was whether the interest of the claimant was perfected as
against the tax lien of the
United States
.
A number of
cases involving the same questions as is presently before the Court have
been decided since the decision in the Ball case and it did not
control the results,Aetna Cas. & Sur. Co. v. U. S. A., supra;
Wolverine Ins. Co. v. Phillips, supra; Central Sur. & Ins. Co. v.
Martin Infante Co., supra.
In accordance
herewith, the plaintiff, General Insurance Company of
America
, is entitled to the said sum heretofore deposited with the Clerk of the
Court in the sum of $11,834.08.
Counsel for
the plaintiff shall prepare Findings of Fact, Conclusions of Law, and a
Proposed Judgment, serve copies of the same on counsel for the defendant
and submit the originals to the Court.
[58-2 USTC
¶9778]Charles W. Berry Houses, Aetna Casualty & Surety Company,
Respondent v. United States of America, Appellant, and Horticultural
Service, Inc., et al., Defendants, and another action (Lester W.
Patterson Houses)
State
of New York Court of Appeals, No. 75, 4 NY2d 639, 4/30/58
[1939 Code Sec. 3670--similar to 1954 Code Sec. 6321]
Tax lien: Fund withheld from contractor: Effect of state law.--Tax
liens were asserted against funds withheld from a contractor who had not
paid for labor and materials. Under
New York
law, a contractor who defaults in payment of laborers and materialmen
has no right to and no property interest in the withheld funds. Since
the contracts involved required payment of claims for labor and material
as a condition precedent to the contractor's right to payment, there was
not a substantial performance which would entitle the contractor to the
funds. Consequently, the Federal tax liens did not attach to any of the
withheld funds and the surety which performed under its bonds and
completed the contracts was entitled to the funds. The Appellate
Division erroneously awarded the Government $331 on the grounds that one
tax assessment list had been received before the execution of one bond.
Paul W.
Williams, United States Attorney, Foley Square, New York, N. Y., John S.
Clark, for United States of America. M. Carl Levine, Morgulas &
Foreman, 521 Fifth Avenue, New York, N. Y., Albert Foreman, for Aetna
Casualty & Surety Co. Irving Wise, 299 Broadway, New York, N. Y.,
for New York City Housing Authority.
Opinion
CONWAY, Chief
Judge:
In these two
actions both the plaintiff Aetna Casualty & Surety Company and the
defendant United States assert liens against two funds which the N. Y.
City Housing Authority holds as the balance due under two contracts for
the landscaping of two public housing projects. This case was tried on
stipulated facts. Horticultural Service Inc. entered into two contracts
with the Authority, one on
October 28, 1949
to landscape the Charles W. Berry project, and the other on
January 24, 1950
to landscape the Lester W. Patterson project. Under these contracts
Horticultural was required to procure bonds to secure the performance of
the contracts and the payment of laborers, materialmen etc. Aetna, as
surety, issued these Performance and Payment Bonds, those for the
Berry
project being issued on
November 29, 1949
, and those for the Patterson project on
February 6, 1950
. Applications for Contract Bond and Agreement of Indemnity, executed on
the same respective dates, made Aetna the subrogee and assignee of all
of Horticultural's rights to any monies due or to become due from the
Authority under the contracts, should Horticultural default in its
performance of the contracts thereby requiring
Aetna
to perform under its bond. Horticultural entered into performance of the
work but was unable to complete it because it lacked sufficient funds.
Consequently,
Aetna
performed under its bonds and made large expenditures in payment of
materialmen, subcontractors, and the wages of Horticultural's laborers.
Aetna
's expenditures on the Patterson project, commencing on March 19, 1951,
totalled $38,288.98. However, it received payments of $5,990, leaving a
present loss to
Aetna
on the Patterson project of $32,298.98. Aetna's expenditures on the
Berry
project, commencing on April 12, 1951, totalled $28,469.18 which
represents the present loss since no payments were received. It will
immediately be seen that Aetna's losses exceed the total unpaid contract
balance presently held by the Authority which amounts to $9,444.02 on
the
Berry
project, and $1,860.75 on the Patterson project.
[Tax
Liens]
Opposed to
Aetna
's claims on these funds are the tax liens presently asserted by the
federal government which arose out of Horticultural's failure to turn
over to the government the Withholding and Employment taxes which it
collected from its workers. All except one of the tax assessment lists
were received by the Collector of Internal Revenue subsequent to
Aetna
's issuance of its bonds. One, in the sum of $331.30, was received on
December 12, 1949, subsequent to the execution of the
Berry
bonds, but prior to the Patterson bonds. It may be noted that it was
this asserted tax lien only for which the Appellate Division rendered
judgment for the
United States
. While all but one of the tax assessment lists were received by the
Collector subsequent to Aetna's execution of its bonds, the
amount of the assessment lists received prior to Aetna's performance
under its bonds exceeded the sums presently held by the Authority. Tax
liens, of course, arise upon the receipt by the Collector of the
assessment list (26
U. S.
C. §3671), but they attach only to "property and rights to
property" belonging to the taxpayer (26
U. S.
C. §3670).
[Issue]
The crucial
issue in this case is whether Horticultural had any interest in the
funds presently held by the Authority to which a tax lien could attach.
As far as Horticultural's contractual rights to these funds are
concerned, each contract provided that "[a]s a condition precedent
to his right to any partial payment the Contractor must, as requested,
submit to the Authority proof satisfactory to the Authority that the
Contractor is meeting his obligations to the Subcontractors,
Materialmen, and workmen promptly." [section 5(c)]. The Authority
was authorized to retain 10% of each estimated partial payment, as
"retained percentages", until final completion of the work.
[section 5(e)]. Partial payments could be withheld or reduced at the
Authority's option if it felt the work was not progressing
satisfactorily [section 5(g)]. As a "condition precedent" to
final payment, Horticultural was obligated to furnish proof of payment
to all subcontractors, materialmen, laborers, etc., until which time it
was provided "[t]he Final Payment payable to the contractor shall
not become due." [section 6(a)]. It was provided also that
"[b]efore Final Payment or any retained percentages shall become
due and payable, the Contractor must also, if required, obtain and
furnish written consent of his sureties to such payment." (Ibid.)
If the work were not performed in accordance with the contract, or if
Horticultural failed to pay its subcontractors, materialmen, laborers
etc., the Authority was entitled under the contract to withhold out any
payment, final or otherwise, such sums as it deemed ample to satisfy
such claims [Section 7(a)]. The net effect of these provisions was to
condition Horticultural's right to any payment, partial or final, upon
the full and faithful performance of its contract obligations to do the
work and pay its laborers, materialmen, subcontractors etc.
The federal
tax lien is assertable only to the extent of Horticultural's interest,
if any, in the funds retained by the Authority. The parties agree that
the basic question presented here is whether Horticultural had any
interest in the funds, presently held by the Authority, to which the
federal tax liens could attach. The
United States
contends that this issue presents a question of federal law, and that
under that law Horticultural did have an interest. Aetna, on the other
hand, argues that this is a matter of state law, and that under the law
of the State of
New York Horticultural
had no such interest.
In Fidelity
& Deposit Co. v.
N.
Y.
City
Housing Authority, 241 Fed. (2d) 142 (1957) [57-1 USTC ¶9410], the
Second Circuit Court of Appeals said: "Section 3670 imposes a tax
lien on 'all property and rights to property' of a defaulting taxpayer.
In adopting this legislation, the Congress did not create property
interests on which a lien might be imposed; there is no suggestion that
it authorized the federal courts to do so." (
Id.
at 144). Accordingly, that court held that the existence of a property
interest "is solely a question of state law." (Ibid.)
Citing this case, the United States Supreme Court held, on June 9th,
1958, in United States v. Bess, 26 U. S. Law Week 4381: "Third.
We must now decide whether Mr. Bess possessed in his lifetime, within
the meaning of §3670, any 'property' or 'rights to property' in the
insurance policies to which the perfected lien for the 1946 taxes might
attach. Since §3670 creates no property rights but merely attaches
consequences, federally defined, to rights created under state law, Fidelity
& Deposit Co. v.
New York City
Housing Authority, 241 Fed. (2d) 142, 144 [57-1 USTC ¶9410], we
must look first to Mr. Bess' right in the policies as defined (
Id.
at 4382).
[State
Law]
Thus, whether
Horticultural had any interest in the funds held by the Authority is to
be determined by
New York
law. The case of U. S. Fidelity & Guaranty Co. v. Triborough
Bridge Authority, 297 N. Y. 31 [47-2 USTC ¶9327], is dispositive of
this question. In that case we held that a surety who performs under its
bond upon the contractor's default has an equitable lien upon the funds
held by the owner, and that this lien arises upon execution of the bond
although it does not become enforceable until the surety suffers a loss
by making payments pursuant to its obligation under the bond. In so
holding we went on to say: "In addition, it is, of course, settled
that intervenor's rights to the moneys held by defendant Authority can
be no greater than those which its taxpayer--the contractor--had. (Karno-Smith
Co. v. Maloney, 112 Fed. (2d) 690, 692 [40-2 USTC ¶9533]; Internal
Revenue Code, §3670; U. S. Code, tit. 26, §3670). Here the
contractor's rights to the fund were clearly subordinate to the right of
defendant Authority--and, by subrogation, of plaintiff--to withhold and
apply those moneys to the payment of unsatisfied claims for labor and
materials. So long as such claims were outstanding and unpaid and so
long as defendant Authority had the right to withhold and apply, the
contractor had no rights to the fund, and consequently, had no
property interest therein upon which intervenor could place a
lien." (
Id.
at 37). (Italics added). The law of the Triborough case, followed
in other cases, is well-settled law. (See Scarsdale Nat. Bank &
Trust Co. v. United States Fidelity & Guaranty Co., 264 N. Y.
159, 163-164; U. S. Casualty Co. v. Met Contracting Corp., 158 N.
Y. S. 2d 117; Lumbermans Mut. Cas. Co. of Ill. v. Great Atl. Constr.
Corp., 158 N. Y. S. 2d 115; Fidelity & Deposit Co. of Md. v.
N. Y. City Hous. Auth., supra at 144, 146; Vincent v. P. R.
Matthews, 126 Fed. Supp. 102 [54-2 USTC ¶9658]; Alabama-Tennessee
Nat. Gas Co. v. Lehman-Hoge & Scott, 122 Fed. Supp. 314 [54-2
USTC ¶9519]; Royal Indemnity Co. v. United States, 93 Fed. Supp.
891, 899; In Re Cummins Constr. Corp., 81 Fed. Supp. 193,
196-197). The net effect of these cases is that Horticultural had no
interest in the funds presently held by the Authority to which the tax
lien could attach. Consequently, inasmuch as Aetna's losses far exceed
the funds held by the Authority, it was entitled to recover the full
unpaid balance of the contract price--(1) $9,444.02 on the
Berry
project, and (2) $1,860.75 on the Patterson project. The
United States
is entitled to nothing out of these funds.
[Conclusion]
The award by
the Appellate Division of $331.30 to the United States suggests the
conclusion that that court felt Horticultural did have an interest in
these funds, and therefore the tax assessment list received prior to the
execution of the Patterson bond created a lien in favor of the United
States for $331.30 upon the unpaid balance of the Patterson contract
price. This, as explained above, was error. Consequently, the judgment
in Action No. 1 should be affirmed, and the judgment in Action No. 2
should be modified so as to increase the judgment in favor of plaintiff
Aetna Casualty & Surety Company by $331.30 and, as so modified,
affirmed.
In Action No.
1:
Judgment
affirmed, without costs. All concur.
In Action No.
2:
Judgment
modified in accordance with the opinion herein and, as so modified,
affirmed, with costs to the plaintiff
Aetna
. All concur.
[58-1 USTC
¶9350]Fidelity and Deposit Company of
Maryland
, Plaintiff v. New York City Housing Authority, Caruso-Sturcey
Corporation, Arnold Lewis, as Assignee of Caruso-Sturcey Corporation,
People of the State of New York and United States of America, Defendants
U.
S. District Court, So. Dist. N. Y., Civ. 93-145, 157 FSupp 87, 12/4/57
[1939 Code Sec. 3670--substantially unchanged in 1954 Code Sec. 6321]
Tax liens: Fund withheld from contractor: Surety's lien: Effect of
New York law.--State and Federal tax liens were asserted against a
fund withheld from a contractor who had not paid for labor and
materials. Reversing the District Court, the Appellate Court held in an
earlier opinion that state law governed the nature of the contractor's
interest. Under
New York
law, a contractor who defaults in payment of laborers and materialmen
has no right to and no property interest in the withheld funds. On
remand, the District Court held that the tax liens against the
contractor did not attach to the withheld funds. It held that the surety
which had paid the laborers and materialmen had an equitable lien upon
the withheld funds.
Maurice,
McNamee & Dart, 149 Broadway,
New York
6, N. Y. (Stewart Maurice, of counsel), for plaintiff. Louis J.
Lefkowitz, Attorney General, State of New York, 80 Centre Street, New
York 13, N. Y. (Samuel Backlar, Assistant Attorney General, of counsel),
for People of the State of New York. Paul W. Williams, United States
Attorney, Southern District of New York, United States Court House,
Foley Square, New York 7, N. Y. (John S. Clark, Assistant United States
Attorney, of counsel), for United States of America.
Opinion
DIMOCK,
District Judge:
Plaintiff
moves for summary judgment.
[Facts]
The suit is
one by Fidelity and Deposit Company of
Maryland
, surety on the bond of Caruso-Sturcey Corporation, a building
contractor, to recover the sum of $46,392.51 from defendant New York
City Housing Authority, hereinafter referred to as the owner. That sum
is the amount equal to the unpaid balance of the contract price for
heating and ventilating work that the contractor agreed to do for the
owner. Plaintiff, as surety on the contract, paid laborers and
materialmen whom the contractor in breach of its contract had failed to
pay. The amount paid by the surety was in excess of the amount unpaid
under the contract and plaintiff seeks to apply the unpaid amount in
reduction of its claim. Taxes are due from the contractor both to the
United States of America
and the State of
New York
and both asserted liens upon the contractor's claim against the owner.
The case was
tried before me and I held, 140 Fed. Supp. 298 [56-2 USTC ¶9761], that
federal law applied, citing United States v. Kings County Iron Works,
Inc., 2 Cir., 224 Fed. (2d) 232, 235 [55-2 USTC ¶9536]. Accordingly
I applied United States v. Munsey Trust Co., 332
U. S.
234, as I interpreted it, and held that the Government had a paramount
lien upon the contractor's claim. Judgment for the Government was
entered.
On appeal the
Court of Appeals reversed the judgment, 241 Fed. (2d) 142 [57-1 USTC ¶9410],
holding that the nature of the interest of the contractor, as
distinguished from the priority of the Government, was to be determined
by the law of the State of
New York
. The Court, p. 145, said that the Kings County Iron Works case
did no more than hold that state-law classification of a right as a
trust did not preclude its classification as a lien upon federal inquiry
into its nature. The court therefore applied New York law as expressed
in U. S. Fidelity & Guaranty Co. v. Triborough Bridge Authority,
297 N. Y. 31 [47-2 USTC ¶9327], and held that the owner had no property
right in the unpaid portion of the purchase price to which any lien of
the Government could attach. The case was therefore remanded.
Plaintiff,
instead of seeking a new trial, has moved for summary judgment. This
procedure is quite proper since there is no dispute as to the facts.
The
Government, though held by the Court of Appeals to be without right as
lienor upon any property right of the contractor, is still in the field
asserting a priority over the surety. I must therefore determine the
respective rights of the parties and, to do that, I must determine what
law governs.
The Court of
Appeals in its opinion in this case said, p. 145:
"These
cases make it perfectly clear that : (1) the classification of state
created rights and (2) the weighing of relative priorities under Section
3670, are both matters of federal law. But here we are concerned with
the question of whether or not a contractual right exists and that we
hold is a matter of state law only."
From this I
conclude that in determining whether a right exists I must look to state
law if its creation would be within state competence and federal law if
its creation would be within federal competence. Then, in classifying a
state created right according to its true nature, for purposes of
resolution of competing state and federal claims, I am not bound by the
name that the state law applies to it but must apply federal law.
Finally, I must apply federal law in determining the relative priority
of a federally created right, on the one hand, and state created rights
on the other.
[Surety's
Lien]
Any right
which the surety in this case may have to the withheld funds is state
created. The New York State case of U. S. Fidelity & Guaranty Co.
v. Triborough Bridge Authority, 297 N. Y. 31, supra, as an
alternative ground undiscussed by our Court of Appeals in reversing,
held that the surety, in a case such as this, obtains an equitable lien
upon the withheld funds. I believe that United States v. Munsey Trust
Co., 332
U. S.
234, supra, holds to the contrary, but, even so, it does not
purport to declare the law of the State of
New York
. *
It is thus
established that the surety has an equitable lien on the withheld funds.
It is also established that the Government has no lien on any right of
its debtor, the contractor, and no one has suggested any other avenue
through which the Government could reach the withheld funds. Since the
Government has no interest in the withheld funds, no question arises
either as to the true nature of the surety's equitable lien thereon or
as to the relative priority of interests of the surety and the
Government therein.
The Government
suggests that an appeal to the Court of Appeals of the State of New York
is now pending from the judgment of the Appellate Division in Aetna
Casualty & Surety Co. v. Horticultural Service, Inc., 2 A. D. 2d
963, a case which followed the ruling in the Triborough case, and
that I ought to withhold decision until a final determination of that
appeal. As a general proposition I am loath to dealy the enforcement of
the rights of litigants in anticipation of a possible change in
controlling law. In this case, moreover, it would serve no purpose,
since substantially the same result can be obtained by the taking of an
appeal from my present determination and keeping it pending until the
determination of the Horticultural Service appeal by the State
Court of Appeals.
[Judgment]
Judgment is
awarded plaintiff against the New York City Housing Authority for
$46,392.51, and the claims of all other parties are dismissed.
With respect
to the time for appeal counsel will please note the provisions of Rule
58 F. R. Civ. P.
*
Evidently its effect must be limited to cases like it where government
contracts are concerned and where consequently a general federal common
law rather than the law of a specific state is applied. Priebe &
Sons v.
United States
, 332
U. S.
407, 411.
[57-1 USTC
¶9410]Fidelity and Deposit Company of
Maryland
, Plaintiff-Appellant v. New York City Housing Authority, Caruso-Sturcey
Corporation, Arnold Lewis, as assignee of Caruso-Sturcey Corporation,
People of the State of New York, Defendants, and United States of
America, Defendant-Appellee
(CA-2),
U. S. Court of Appeals, 2nd Circuit, Docket No. 24196, 241 F2d 142,
2/8/57, Reversing and remanding the decision of the District Court, 56-2
USTC ¶9761, 140 F. Supp. 298
[1939 Code Sec. 3670--substantially unchanged in 1954 Code Sec. 6321]
Tax lien on fund withheld from contractor: Effect of state law.--A
tax lien was asserted against a fund withheld from a contractor who had
not paid for labor and materials. Under the applicable
New York
law, a contractor who defaults in payment of laborers and materialmen
has no right to the withheld funds and no property interest. Such local
law must be recognized for federal tax purposes. Under 1939 Code Sec.
3670, the courts have authority to determine whether state-created
interests are choate or inchoate; the existence of the interests to be
federally classified, however, is solely a question of state law. Since
the contract required payment of claims for labor and material as a
condition precedent to the contractor's right to payment, there was not
a substantial performance which would entitle the contractor to the
withheld fund. Payment of the claims by surety did not satisfy this
condition.
Maurice,
McNamee
&
Dart
,
New York
City (Stewart Maurice,
Rob
ert F. Dart,
New York City
, of counsel), for plaintiff-appellant. Paul W. Williams, United States
Attorney, New York City (Arthur B. Kramer, Miriam R. Goldman, Assistant
United States Attorneys, New York City, of counsel), for
defendant-appellee.
Before SWAN,
MEDINA
and WATERMAN, Circuit Judges.
MEDINA
, Circuit Judge:
This case was
tried below [56-2 USTC ¶9761, 140 Fed. Supp. 298] on an agreed
statement of facts. Caruso-Sturcey Corporation contracted on
June 21, 1949
with the New York City Housing Authority to install heating and
ventilating facilities on a housing project. The contract required
Caruso to give a performance bond, not involved in this litigation, and
a payment bond for laborers and materialmen. This the contractor did
when it executed the bonds on
July 11, 1949
with Fidelity and Deposit Company of
Maryland
.
When the
heating and ventilating facilities had been installed and accepted by
the owner on
March 1, 1952
, there was an unpaid balance on the contract, amounting to $46,392.31.
The principal claimants to this fund are Fidelity, which had made
payments for labor and materials aggregating $75,650.09, from December
11, 1950 through November 13, 1951, as required by its bond, on Caruso's
failure to make such payments when due, and the United States by reason
of tax liens, for withholding taxes retained by Caruso from the wages of
its employees, but not remitted. The tax assessments run from April 11,
1950 through September 12, 1951; and the total of these is $47,639.68.
On September
14, 1951, Caruso made an assignment for the benefit of creditors,
pursuant to the provisions of the New York Debtor and Creditor law, to
defendant Arnold Lewis; and there is a subsidiary claim of the
defendant
State
of
New York
arising out of certain corporation and franchise taxes owing by Caruso.
In form the
suit is one by Fidelity in equity against the Housing Authority to
recover the fund. Caruso's assignee filed an answer containing a
counterclaim but failed to appear at the trial. The State of
New York
asserted its claim against the fund for taxes. The
United States
pleaded a claim to the fund under Section 3670 of the Internal Revenue
Code of 1939, 26
U. S.
C., Section 3670. 1
The fund was
awarded by the court below to the
United States
on the theory that the defaulting taxpayer Caruso, under its contract,
had a conditional right to the fund, that this right was a "right
to property" within the meaning of Section 3670, and that the
United States
thus had a valid tax lien on the entire fund. As the tax lien thus found
to exist would take superiority over any claim by Fidelity, it became
unnecessary for the court otherwise to pass upon the nature and
sufficiency of Fidelity's claim. Nor was consideration given to the
claim of the State of
New York
, for the same reason. As we have concluded that there were no rights of
Caruso upon which the government tax lien could attach, there must be a
new trial in which all the issues raised by the pleadings and not yet
disposed of may be adjudicated, including the rights of the State of New
York, although the appeal to this court is by Fidelity alone.
[Contractor's
Right to Withheld Fund]
The first
issue to be considered is whether the defaulting taxpayer under its
contract had a conditional right to the withheld fund. The contract was
made and performed in
New York
. The New York Court of Appeals has had occasion to consider a similar
contract that also required as a condition precedent to payment proof
that the contractor had satisfied claims of materialmen and laborers.
"So long as such claims were outstanding and so long as [the owner]
had the right to withhold and apply," it held, "the contractor
had no rights to the fund and, consequently, no property interest
therein upon which [the United States] could place a lien.' United
States Fidelity & Guarantee Co. v. Triborough Bridge Authority,
297 N. Y. 31, 37 [47-2 USTC ¶9327]. And again: "A failure by the
contractor to pay for labor and material was just as much a failure to
perform and carry out the terms of the contract as an abandonment of the
work would have been." Ibid. p. 36.
For the
highest court of the State of
New York
, in short, a failure to pay laborers and materialmen is a breach of
contract and a contractor who fails to make such payments has no right
under the contract. This decision, if binding here, disposes of the
holding below: without a finding that the defaulting taxpayer has some
right that may be classified as a "right to property," there
can be no federal tax lien. But is it binding here?
[Effect
of State Law]
Section 3670
imposes a tax lien on "all property and rights to property" of
a defaulting taxpayer. In adopting this legislation, the Congress did
not create property interests on which a lien might be imposed; there is
no suggestion that it authorized the federal courts to do so. On the
contrary, it took for granted here, as it normally does in the tax law,
the vital existence of state laws creating and maintaining various
interests. The statute was fashioned to require the courts to determine
for federal purposes whether those state-created interests are
"property" or "rights to property." That
classification of interests is a federal question; the existence of the
interests to be federally classified, however, is solely a question of
state law.
This
distinction was formulated by the Supreme Court in Morgan v.
Commissioner, 309
U. S.
78, 80 [40-1 USTC ¶9210], which also involved the tax law. "State
law," the court explained, "creates legal interests and
rights. The federal revenue acts designate what interests or rights, so
created, shall be taxed. Our duty is to ascertain the meaning of the
words used to specify the thing taxed. If it is found in a given case
that an interest or right created by local law was the object to be
taxed, the federal law must prevail no matter what name is given to the
interest or right by state law."
This
distinction has not been discarded in the Supreme Court decisions under
Sections 3670 and 3671. In none of those cases was there any doubt that
a federal tax lien had attached to "property or rights to
property"; nor for that matter was there any question under state
law as to whether the party against whom the federal government asserted
a tax lien had some interest in the disputed property. The question was
solely one of priorities between two existing claims.
Thus, in United
States v. Security Trust and Savings Bank, 340 U. S. 47 [50-2 USTC
¶9492], the court held "inchoate" an attachment lien that had
been thought by the state courts, applying the state doctrine of
relating a judgment lien back to the time of the attachment lien, to
have been perfected. In United States v. Acri, 348
U. S.
211 [55-1 USTC ¶9138], the court exercised a similarly independent
judgment in disregarding for federal purposes a state holding that an
attachment is "execution in advance." In these and in other
cases cited in the footnote, 2
the issue was one of priorities under a federal statute; in disposing of
this issue, the Supreme Court held itself free to disregard for federal
purposes the state determination as to whether the right the state had
created was "choate."
Nor was this
distinction discarded in our decision in United States v. Kings
County Iron Works, 224 Fed. (2d) 232 [55-2 USTC ¶9536]. The facts
in that case, as in the one before us, were not disputed. It was
admitted that the taxpayer-contractor owed money to the
United States
for unpaid taxes, that he also owed money to his subcontractor for
services performed, and that he was owed money (having performed his
promises under a contract) by the owner. The issue was whether the New
York Lien Law that classified a reserve fund for workers and materialmen
as a "trust," precluded a federal inquiry into the nature of
the right thus created. The court held for federal purposes that it did
not, that the right admittedly created by state law was for the purposes
of Section 3670 a "lien" rather than a "trust," that
peculiar local conditions were responsible for the differences in
vocabulary. The court did not inquire whether the state had created a
right. It assumed that it did and was concerned with the "relative
priority of a federal tax lien and a mechanic's lien under state
law." United States v. Kings County Iron Works, supra, at
234.
These cases
make it perfectly clear that: (1) the classification of state-created
rights and (2) the weighing of relative priorities under Section 3670,
are both matters of federal law. But here we are concerned with the
question of whether or not a contractual right exists and that we hold
is a matter of state law only. F. H. McGraw & Co. v. Sherman
Plastering Co., 60 Fed. Supp. 504, 511-512 (per Hincks, D. J.).
Under the authority of
Triborough
Bridge
Authority, supra, we are constrained to rule that Caruso was
left with no contractual right; and, accordingly, we have nothing to
"classify."
[Government's
Arguments]
The
government, citing no
New York
cases, tries to spell out a right to the withheld fund in two ways.
First, it claims that the contractor could have sued for the fund after
satisfactorily installing the heating facilities on a theory of
substantial performance, even though the contractor failed to satisfy
the claims for labor and material. This argument is not persuasive. The
contract carefully requires satisfaction of those claims as a condition
precedent to partial payment no less than to final payment. Thus,
Section 5(c) provides:
"As
a condition precedent to his right to any partial payment, the
Contractor must, as requested, submit to the Authority proof
satisfactory to the Authority that the Contractor is meeting his
obligations to the Subcontractors, Materialmen, and workmen promptly.
The Contractor's monthly requisitions must be accompanied by his
affidavit showing the amounts previously paid for Work executed by such
Subcontractors or materials furnished by such Materialmen, and the
amounts remaining unpaid and owing to any such persons, setting forth
therein the names of the persons whose claims are unpaid and the amount
due to each and, if required, must also be accompanied by affidavits
from all Subcontractors and Materialmen, containing this
information."
And
Section 6 provides:
"The
Contractor shall, as a condition precedent to final payment, furnish to
the Authority a detailed sworn statement of all liens, claims and
demands, just and unjust, of Subcontractors, Materialmen, laborers,
other employees, and third persons, then outstanding or which he has
reason to believe may thereafter be made on account of the Work or
performance thereof. The Final Payment payable to the Contractor shall
not become due, however, until the Contractor shall deliver to the
Authority all releases required by the Authority from all such claims
and demands arising out of any Work done pursuant to the Contract * *
*."
We
do not understand how the
New York
courts, or any courts for that matter, could find justification for
holding, in the face of so carefully drawn a contract, that a failure to
satisfy these condition is "insubstantial." Jacob &
Youngs v. Kent, 230 N. Y. 239; Dauchey v. Drake, 85 N. Y.
407; Spence v. Ham, 163 N. Y. 220; Cassino v. Yacevich,
261 App. Div. 685; Gompert v. Healey, 149 App. Div. 198.
The second
theory assumes, as it were, that the contractor might not be able to
recover on a claim of substantial performance. "Caruso might agree
to waive its claim to the fund unless it paid all laborers and
materialmen," the argument goes, "but it could not waive the
Government's interest; for purposes of federal taxation, Caruso
continued to have an interest in the fund despite any agreement to give
laborers and materialmen a preferred and divesting interest."
This statement
begs the very question it is designed to answer. Of course, if the
government has an interest in the funds, Caruso by agreement could not
waive it. The problem, however, is whether Caruso has, without prior
payment of laborers and materialmen, the enforceable interest in the
fund to which a tax lien might attach. By the terms of the contract, he
does not.
The government
advances one other reason for holding that Caruso has a right to the
withheld fund under the contract. The terms of the contract, it urges,
do not specifically require that the contractor pay the laborers and
materialmen; it requires only that they somehow be paid. Here, they were
paid (by the surety) and the condition precedent to payment was thus
satisfied.
While perhaps
superficially plausible, this construction of the contract is not
convincing. Section 3 of the contract requires the contractor to
"furnish all labor and materials" needed to comply with the
contract. Section 5(c) declares that "As a condition precedent to
partial payment, the Contractor must, as requested, submit to the
Authority proof * * * that the Contractor is meeting his obligations to
the Subcontractors, Materialmen and workmen promptly." Section 20
declares that "The Contractor * * * shall promptly pay all amounts
due for services rendered, work performed and materials and equipment
supplied * * *." This terminology indicates that while the ultimate
aim of the Authority may have been to secure prompt payment for laborers
and materialmen, it required contractually as a condition precedent to
payment that the contractor do so.
We are
satisfied, then that under Triborough Bridge Authority, supra,
recently cited as controlling authority by the New York Appellate
Division in Aetna Casualty & Surety Co. v. Horticultural Service,
Inc., -- N. Y. Supp. --, reported in N. Y. L. J., Dec. 12, 1956
(Nos. 10544-10545) [56-1 USTC ¶9548], the taxpayer-contractor had no
right to the withheld fund. Of necessity, it follows that it had no
"right to property" to which a federal tax lien might attach
and the government's claim must fail.
Reversed and
remanded.
1
Section 3670. Property subject to lien.
If any person
liable to pay any tax neglects or refuses to pay the same after demand,
the amount * * * shall be a lien in favor of the
United States
upon all property and rights to property, whether real or personal,
belonging to such person.
2
On the "inchoate" character of the lien: United States v.
White Bear Brewing Co., 350 U. S. 1010 (1956) [56-1 USTC ¶9440],
petition for rehearing den., 351 U. S. 958 (Mechanic's Lien); United
States v. Colotta, 350 U. S. 808 (1955) (Mechanic's Lien) [55-2 USTC
¶9680]; United States v. Scovil, 348 U. S. 208[218] (1955)
(landlord's distress lien) [55-1 USTC ¶9137]; United States v.
Liverpool & London Ins. Co., 348 U. S. 215 (1955) (garnishment)
[55-1 USTC ¶9136]; United States v. City of New Britain, 347 U.
S. 81 (1954) (city tax lien) [54-1 USTC ¶9191]. See also, United
States v. Gilbert Associates, 345
U. S.
361 (1953) (ad valorem tax held "judgment" under state law,
but not for federal purposes) [53-1 USTC ¶9291].
[60-1 USTC
¶9413]The Atlantic Refining Company v. Continental Casualty Company,
Joseph M. Smith, and Greensburg Concrete Block Company, Defendants, and
United States of America, Intervenor
U.
S. District Court, West. Dist. Pa., Civil Action No. 15185, 183 FSupp
478, 4/8/60
[1954 Code Secs. 6321-6323]
Tax liens: Funds withheld under construction contract: Surety's
rights.--A lien for taxes did not attach to funds withheld from the
tax-delinquent contractor under a construction contract which provided
that final payment would be made only after the contractor showed that
there were no liens for unpaid claims for labor and material, which the
contractor was unable to do. The surety on the contractor's bond was
subrogated to the rights of the person for whom the work was being done,
not to the rights of the contractor (which would be subject to the tax
lien), and, under the terms of the contract and bond, was not liable to
the United States for withholding and social security taxes attributable
to the construction performed under the contract.
Rob
ert A. Rundle, of Wright & Rundle,
Frick
Building
,
Pittsburgh
19,
Pa.
, for plaintiff. J. M. McCandless,
304 Ross Street
,
Pittsburgh
19,
Pa.
, for defendant.
Opinion
and Order
Opinion
MARSH,
District Judge:
The facts as
disclosed by the pleadings and stipulated by the parties, except as
hereinafter specified, are adopted by the court as if found pursuant to
Rule 52, Fed. R. Civ. P.
Atlantic
Refining Company, hereinafter called the Owner, on
November 8, 1954
, and
May 16, 1955
entered into two no-lien construction contracts with Joseph M. Smith,
hereinafter referred to as Contractor, to furnish labor and materials
for the construction of two service stations located, respectively, in
Mt.
Pleasant
,
Westmoreland County
,
Pennsylvania
, and Connellsville,
Fayette County
,
Pennsylvania
. The contracts were filed of record in the respective counties before
visible commencement of work was begun on the ground. A construction and
payment bond furnished by Continental Casualty Company, hereinafter
referred to as Surety, accompanied each contract.
The Contractor
completed the construction of the service stations but failed to pay
certain materialmen on each job. As of November, 1956, the balance
withheld by the Owner on the contract price was $6,027.68 for the
Mt.
Pleasant
station and $6,626.26 for the Connellsville station, or a total of
$12,653.94.
[Claims
to Withheld Funds]
Previously,
the United States Internal Revenue Service served on Owner notice of
levy and demand for certain taxes owned by the Contractor, assessed in
July and December of 1955 and noticed and filed of record on
October 28, 1955
and
December 30, 1955
. The total amount of the assessments was $11,632.06, plus interest, of
which sum $1,114.81 was incurred by the Contractor in erecting the two
service stations aforementioned.
Greensburg
Concrete Block Company, a judgment creditor of the Contractor, served a
writ of attachment execution on the Owner, as garnishee, attaching the
fund allegedly due to the Contractor to satisfy its judgment of $737.65,
with interest and costs.
The Surety
claimed the balances withheld on the contract prices by reason of its
liability on the bonds to unpaid materialmen.
Faced with
these conflicting claims, the Owner on
November 15, 1956
filed a "Complaint for Interpleader and Declaratory Relief"
against the
United States
, the Surety Company, Greensburg Concrete Block Company, and the
Contractor, and thereupon paid $12,653.94 into the registry of this
court.
A default
judgment was entered against Contractor Smith and Greensburg Concrete
Block Company for failure to appear, answer or plead, and the Owner was
discharged from any claim that they might assert against the funds paid
into court.
[Tax
Liens]
The complaint
was dismissed as to the
United States
, and the
United States
was permited to intervene as a party plaintiff. The government's
complaint in intervention alleges that the Contractor is indebted to it
for certain withholding and F. I. C. A. taxes in the sum of $11,632.06,
plus interest, and claims by virtue of the 1955 assessments that it has
a prior lien on the fund allegedly due to the Contractor from the Owner.
Hence, it demands the funds paid into court by Owner.
By amendment
to its complaint, the government also sues the Surety directly on the
bonds for all withholding and F. I. C. A. taxes due it from the
Contractor in the sum of $11,632.06, plus interest. This suit, however,
is pressed only for the sum of $1,114.81, plus interest, that amount
being the withholding and F. I. C. A. taxes incurred by the Contractor
in the construction of the service stations at
Mt.
Pleasant
and Connellsville (see government's brief, pp. 32-34).
[Surety's
Claim]
After the fund
was paid into court, the Surety paid claims of materialmen on the
Mt.
Pleasant
station in the sum of $6,004.51, leaving a balance of $23.17 unclaimed
except by the
United States
. The Surety paid claims of materialmen on the Connellsville station in
the sum of $12,285.53. The Surety took assignments from the materialmen
which it paid.
The Surety
presses its claim on the following grounds:
(1)
The Contractor had no property or property interest in the fund upon
which the government liens might attach.
(2)
The Surety is subrogated to the rights of the Owner and materialmen in
the fund created by the contract between the Owner and the Contractor.
(3)
The Surety is entitled to the fund under equitable assignments given by
the Contratcor to the Surety at the time of the execution of the bonds. 1
In my opinion
the Surety is entitled to the fund on the first ground, and on the
second ground, i.e., because it is subrogated to the rights of the
Owner. It is, therefore, unnecessary to discuss the third ground,
although I am of the opinion that the Surety's contentions with respect
to the effect of its equitable assignments would not succeed against the
federal liens. 2
The provisions
of the contracts between the Owner and the Contractor are identical
except for description of work and prices.
The pertinent
provisions thereof are as follows:
(1)
"Contractor shall, during the progress of the work, pay all valid
charges of all his sub-contractors and other persons furnishing labor
and/or materials in the performance or prosecution of the work . . .
when and as such charges become payable and in their full amount."
(2)
"When the contract has been completed, the Contractor shall deliver
to the Owner a full Release of Liens signed by himself and all
sub-contractors and other persons who have furnished any materials,
labor, or both, in the performance of the contract or prosecution of the
work. . . . Such release, with accompanying affidavits, shall be in such
form as the Owner may require and its presentation to Owner shall
constitute a representation by Contractor that all sub-contractors . . .
have joined in the proper execution thereof as having been paid. . . .
Until such releases and affidavits are delivered properly executed, the
final schedule of payments may be withheld."
(3)
"WAIVER OF LIENS AND CLAIMS: . . . In the event that notice
is given of any claim . . . which is chargeable to the Contractor . . .
the Owner shall have the right to retain out of any payment then due, or
to become due, an amount sufficient to completely indemnify the Owner
against such claim. . . . In the event of . . . [the Contractor's]
failure to have such claims . . . paid . . . the Owner shall have the
right to take such action as is necessary to have the same done,
charging the cost thereof . . . to the Contractor."
(4)
"The Owner shall retain ten percent (10%) pending completion of the
job and full compliance with the contract. . . . The final payment shall
be made within thirty (30) days after final test and acceptance of the
work, provided the Contractor shall have submitted to the Owner a
satisfactory Release of Liens showing that all claims and bills for
labor and material have been met and paid as hereinbefore
provided."
The surety
bonds are identical in their material provisions. Each contract was
incorporated by reference in the accompanying bond.
Each bond was
conditioned upon faithful performance of the contract and upon prompt
payment of all just charges for labor and material furnished by
Contractor.
No release of
liens was furnished the Owner by the Contractor with respect to either
job as required by both contracts. The Owner withheld the balances due
on the contract prices and interpleaded the claimants thereto.
The
Contractor Does Not Have Any Property or Rights to Property in the
Withheld Balances of the Contract Prices Upon Which the Liens for
Federal Taxes Might Attach
The
United States
bases its claim to the fund on §§ 6321 and 6322 of the Internal
Revenue Code of 1954. 3
As therein provided "if any person liable to pay any tax neglects
or refuses to pay same after demand, the amount . . . shall be a lien in
favor of the
United States
upon all property and rights to property . . . belonging to such
person."
It was held in
United States v. Bess, 357 U. S. 51, 55 (1958) [58-2 USTC ¶9595]
that ". . . §3670 [now 26 U. S. C. §6321] creates no property
rights but merely attaches consequences, federally defined, to rights
created under state law", citing Fidelity & Deposit Co. v.
New York City Housing Authority, 241 F. 2d 142, 144 (2nd Cir. 1957)
[57-1 USTC ¶9410]. As stated in Morgan v. Commissioner, 309
U. S.
78, 80 (1940) [40-1 USTC ¶9210]: "State law creates legal
interests and rights."
As of the
dates the federal liens were assessed (1955), the Contractor was not
entitled to received any money under the terms of the contract, for the
Contractor owed materialmen on both jobs. On the
Mt.
Pleasant
job the unpaid amount was practically equivalent to the amount withheld
by the Owner, and on the Connellsville job the amount was substantially
in excess of the amount withheld.
[Contractor's
Rights Under State Law]
It must now be
determined under the
Pennsylvania
law whether the Contractor had any "property" or "rights
to property" in the balances withheld from the Owner and paid by it
into court. Cf. Central Surety and Insurance Corp. v. Martin Infante
Co., 272 F. 2d 231 (3rd Cir. 1959) [59-2 USTC ¶9736].
It is a
general principle that a material failure of performance by one party to
a contract not justified by the conduct of the other discharges the
latter's duty to give the agreed exchange. Sections 274 and 275,
Restatement, Contracts, with which Pennsylvania law is in accord; Wright
v. Barber, 270 Pa. 186, 113 Atl. 200 (1921); City of Farrell v.
H. Platt Co., 142 Pa. Super. 242, 15 A. 2d 718; vol. 8 P. L. E. §301;
Sum.
Pa.
Jur. Contracts, §498; cf. vol. 4, Corbin on Contracts, §901. Also in
accord are cases in other jurisdictions involving contracts providing
for the payment of labor and materialmen as a prerequisite for payment
of the contract price. Central Surety & Insurance Corp. v. Martin
Infante Co., supra; Fidelity & Deposit Co. v. New York City Housing
Auth., supra; United States Fidelity & Guaranty Co. v. United
States, 201 F. 2d 118 (10th Cir. 1952) [53-1 USTC ¶9249]; Wolverine
Insurance Co. v. Phillips, 165 F. Supp. 335 (N. D. Iowa W. D. 1958)
[58-2 USTC ¶9765]; United States Fidelity and Guaranty Co. v.
Miller, 143 F. Supp. 941 (W. D. N. C. 1956) [56-2 USTC ¶9930]; Scott
v. Zion Evangelical Lutheran Church, 75 S. D. 559, 70 N. W. 2d 326
(1955) [55-2 USTC ¶9669]; United States Fidelity & Guaranty Co.
v. Triborough Bridge Authority, 297 N. Y. 31, 36-37, 74 N. E. 2d
226, 228 (1947) [47-2 USTC ¶9327].
In the cited
cases it was held that the tax liens of the
United States
did not attach to the withheld funds; and the sureties and, in one case,
the materialmen, won the money. In at least four of the cases, it seems
that the contractors had completed or substantially completed the work
for the owners, 4
the contractual breach being their failure to pay materialmen.
Therefore, I
am of the opinion that a failure by the Contractor here to pay for labor
and materials is just as much a failure to perform and carry out the
terms of the contract as an abandonment of the work would have been.
Since the
Contractor failed to pay the materialmen in amounts almost equal to or
in excess of the balances withheld on the contract prices, express
promises of the Contractor to the Owner to pay materialmen were
materially breached by these substantial failures. Consequently, except
for $23.17, the Contractor had no right of property in the balances
withheld by the Owner; he could "not get" the withheld
balances, Lancaster County Nat. Bank's Appeal, 304 Pa. 437, 155
Atl. 859; he had "no rights whatever" to the said balances, Prairie
State Bank v. United States, 164 U. S. 227 (1896).
In Lancaster
County Nat. Bank's Appeal, supra, the construction contract, as
here, required the contractor to pay the materialmen. Being a contract
for public work, it was, as here, in effect, a no-lien contract. On page
861 (155 Atl.), it was stated:
"[A]s
it [the assignee of the contractor] was claiming the right to receive a
sum payable to the contractor under the terms of the contract, it was
bound to take notice also of the fact that the contractor could not
get the semifinal estimate, which is the one in controversy here,
until and unless all 'claims for labor and materials [incurred in the
performance of the contract] have been satisfactorily settled,' . .
.." (Italics supplied.)
Likewise, in Prairie
State Bank v. United States, supra, with which it has been declared
the Pennsylvania law is "in harmoney", Sundheim v. School
District, 311 Pa. 90, 166 Atl. 365 (1933), it was stated at page
232:
"A
great deal of confusion has arisen in the case by treating . . . [the
surety] as subrogated merely 'in the rights of . . . [the contractor]'
in the fund, which, in effect, was saying that he was subrogated to
no rights whatever." (Italics supplied.)
Thus when
perfected in 1955, the lien of the government's taxes bound a contingent
right of the Contractor to receive the balance of the contract prices
if, but only if, he substantially performed his direct contractual
obligations to the Owner to pay the materialmen. After his material
breaches, the Contractor's contingent right never ripened into a
"right to property" which he could enforce or on which the
federal tax liens could attach.
It is ".
. . well settled that the lien of federal taxes extends only to property
in which the taxpayer has an interest." United States v. Burgo,
175 F. 2d 196, 198 (3rd Cir. 1949) [49-1 USTC ¶9307]. "Since the
government's rights under Sections 6321 and 6322 can rise no higher than
the rights of the taxpayer, there was nothing of Infante's [the
contractor's] to be levied upon." Central Surety and Insurance
Corp. v. Martin Infante Co., supra, at pages 234-235.
Adapting Mr.
Justice Brennan's statement in
United States
v. Bess, supra, at pp. 55, 56, it would be anomalous to view as
"property" subject to lien, money never within the
Contractor's reach to enjoy.
In the instant
case, I conclude that the Contractor had no "property" or
"right to property" in the withheld balances which the Owner
paid into court, and, therefore, there was nothing to which the
government's lien could attach.
The
Surety Is Subrogated to the Rights of the Owner in the Withheld Balances
Having
determined that the
United States
does not have a lien on the withheld balances, it seems certain that the
Surety is entitled to recover the fund paid into court.
However, the
government strenuously argues that in no-lien contracts where the work
is completed by the Contractor, the Surety cannot be subrogated to the
rights of the materialmen or the Owner, but only to the rights of the
Contractor, which rights, of course, are subject to the government's tax
liens. I am of the opinion that under
Pennsylvania
law the Surety can be, and is, subrogated to the rights of the Owner,
and is thus entitled to the fund in which the Contractor, as shown, has
no property rights.
It is
established in Pennsylvania that upon elementary principles a surety is
entitled to assert the equitable doctrine of subrogation to funds in the
hands of the owner where there is a direct contractual obligation to
the owner, as a party to the contract, binding upon the contractor
and the surety to pay materialmen when the contractor breaches the
contract by failing to pay the materialmen. In such circumstances, the
surety is entitled to be subrogated to the rights of the owner in
the retained balances. Subrogation arises from the owner's right to have
the original contract performed according to its terms. When the surety
pays the materialmen, it stands in the position of a surety who not only
has completed the contractual obligations of the defaulting contractor,
but also has carried out the equitable obligations of the owner to see
that the materialmen are paid. Sundheim v. School District, supra.
(Compare with similar cases in other jurisdictions, see footnote 4.)
In Henningsen
v. United States Fidelity & Guaranty Co., 208 U. S. 404, 411
(1907), where the contractor promised the owner to pay materialmen, it
was held that the surety was "entitled to assert the equitable
doctrine of subrogation", citing Prairie State Bank v. United
States, supra. And in
Lancaster
County
No. Bank's Appeal, supra, at page 861 (Atl.), "under
precisely similar circumstances" to those in Hinningsen, the
Pennsylvania Supreme Court said: "With this statement of the law we
are in complete accord. . . ." (page 862 Atl.).
In Sundheim
v.
School District
, supra, at pp. 367-368 (Atl.), the Supreme Court of Pennsylvania
stated:
"Consequently,
when the contractor fails to pay labor and materialmen, it is tantamount
to a breach of its contract with the
United States
[the owner]. . . . When this occurs and the surety pays the labor and
materialmen, it stands in the position of a surety completing a
contractual obligation of a defaulting contractor and performing an
equitable duty to the
United States
. It [the surety] is therefore entitled to subrogation to the rights of
the
United States
in the fund. Subrogation does not arise through the contractor, but
from the government's [the owner's] rights. Prairie State Nat. Bank v.
U. S.
, 164
U. S.
227, 17 S. Ct. 142, 41 L. Ed. 412; Henningsen v.
U. S.
Fid. & Guar. Co. of Baltimore, 208
U. S.
404, 28
S. Ct.
389, 52 L. Ed. 547; In re Scofield Co. (C. C. A.) 215 F. 45. In
Pennsylvania, where our statutes and the facts coincide with the cases
decided by the federal courts, we are in harmony with those
decisions as illustrated by Lancaster County National Bank's Appeal,
304 Pa. 437, 155 A. 859, 861." (Italics supplied.)
In Prairie
State Bank v.
United States
, supra, at pages 232-233, it was stated:
"Hitchcock's
[the surety's] right of subrogation, when it became capable of
enforcement, was a right to resort to the securities and remedies which
the creditor (the United States) [the owner] was capable of asserting
against its debtor Sundberg & Company [the contractors], had the
security not satisfied the obligation of the contractors, and one of
such remedies was the right based upon the original contract to
appropriate the ten percent retained in its hands. . . . The right of
Hitchcock to subrogation, therefore, would clearly entitle him when, as
surety, he fulfilled the obligation of Sundberg & Company [the
contractors], to the government [owner], to be substituted to the
rights which the
United States
[owner], might have asserted against this fund." (Italics
supplied.)
In Henningsen
v. United States Fidelity & Guaranty Co., supra, at page 410, it
was stated:
"It
[the surety] paid the laborers and materialmen and thus released the
contractor from his obligations to them, and to the same extent released
the Government from all equitable obligations to see that the laborers
and supply men were paid." (Italics supplied.)
That the
owner-promissee has equitable obligations and rights in a donee
beneficiary contract, as a promise to pay materialmen seems to be, 5
is pretty well established. Restatement, Contracts, §138; Burnet v.
Wells, 289
U. S.
670, 679-680 [3 USTC ¶1108]; Cove IRR. Dist. v. American Surety Co.
of
New York
, 42 F. 2d 957 (9th Cir. 1930); Williston on Contracts, rev. ed.,
§§ 358, 359; Corbin, Contracts, vol. 4, §812.
Thus, Henningsen
v. United States, supra, and Prairie State Bank v. United States,
supra, pointed to in the Pennsylvania cases (Lancaster and Sundheim)
as exemplifying the federal law with which Pennsylvania is in accord,
clearly hold that in no-lien construction contracts, 6
the owner has an equitable obligation to see that the materialmen are
paid, and when the surety has paid them, the surety is subrogated to the
rights of the owner in the withheld balances as of the date of the
original contract.
The rationale
of the foregoing principles is well expressed in Corbin on Contracts,
vol. 4, §901, pp. 609, 610, from which the following extracts are
taken:
"If
the surety claims by subrogation, his claim is not a 'latent equity' for
the reason that he is being put into the position of the obligated
owner, none of whose defenses and counterclaims can be described as
'latent'.
"The
owner, in such a case as the above, is both an obligor and an obligee.
His duty to pay is accompanied by a right to the performance promised in
exchange for his money; his duty to pay is conditional upon performance
by the builder. . . . In so far as the building contractor has not
performed his part of the agreed exchange, he has no right to payment by
the owner; and his assignee [lien creditor] has none. In so far as the
agreed exchange has been performed at the surety's expense, under the
compulsion of the surety bond, it has seemed fair and just to give to
him that part of the payment that is dedicated to the agreed exchange;
and it has seemed unjust to let either the contractor or his assignee
[lien creditor] profit by the performance rendered under compulsion by
the surety. This is the doctrine of subrogation of the surety to the
position of the creditor. For, again be it noted, although the owner is
a debtor (obligor) as to the promised payment, he is a creditor
(obligee) as to full performance by the building contractor, and
deferred payments are retained by him as security for such performance.
. . .
"So,
when the surety performs any of the contractor's duties to the owner, he
is subrogated to the owner's right and securities against the principal
contractor; and among these are included the deferred payments and
retained percentages in the owner's hands."
The contracts,
sub judice, are explicit in providing that the final schedule of
payments may be withheld from the Contractor (promisor) until proof
satisfactory to the Owner (promisee) is delivered, in order to show the
Owner that all claims of laborers and materialmen (beneficiaries) have
been paid by the Contractor as promised. 7
Because no such proof was ever submitted and substantial amounts were
due to materialmen, the Owner did withheld final payments. Thereupon the
withheld balances became collateral security for the Owner and
ultimately for the Surety when it performed its obligations under the
bonds and paid the materialmen. Prairie State Bank v.
United States
, supra. I hold that the Surety is entitled to the fund.
Payment
by the Owner of the Withheld Balances Into Court Does Not Constitute a
Waiver of the Surety's Right of Subrogation
The government
argues that when the Owner paid the withheld balances into court, it
waived its right to withhold them and the Contractor's property rights
to same were reinstated and hence the federal liens attach. I do not
agree.
In Lancaster
County Nat. Bank's Appeal, supra, at page 861 (Atl.), it is stated:
".
. . [T]he surety had an equity to insist that the secretary of the
department 'withhold the payment of any semifinal or final estimate'
until these claims were paid, as by the contract itself he said he would
do, and on the faith of which provision, inter alia, the surety executed
the bond.
Derby
v. United States Fidelity & Guaranty Co., 87 Or. 34, 169 P.
500; Canton Exchange Bank v.
Yazoo
County
, 144
Miss.
579, 109 So. 1."
Cf.
Sum.
Pa.
Jur., Surety & Guarantor, §139.
The Owner,
when it actually withheld the balances and paid them into court, waived
any defenses it had aaginst the claimants, 8
but it could not waive any right that the Surety might have to the
withheld balances which are the security for the Contractor's
performance. Interpleader does not affect the rights of the claimants or
the merits of their respective claims inter se.
Moore
's Federal Practice, 2d ed., vol. 3, ¶22.07, pp. 3021-3022.
The Surety
upon payment of the materialmen was entitled to insist that the withheld
balances remain as its security, 9
and their payment into court by the Owner, the plaintiff in
interpleader, did not divest the funds of their character as security.
They did not ipso facto become the property of the Contractor.
The
United States
Cannot Recover From Surety Unpaid Taxes of the Contractor Incurred in
the Performance of Work Under the Contracts at Bar
It remains to
be determined whether or not the government is entitled to a judgment
against Surety in the sum of $1,114.81, plus interest, being the
withholding and social security taxes attributable to the construction
of the
Mt.
Pleasant
and Connellsville service stations which the Contractor failed to pay.
In may opinion
the claim should be denied.
It seems to be
established that withholding and social security taxes due to the
government from the Contractor are owing as taxes and not as wages. United
States v. Crosland Const. Co., 217 F. 2d 275 (4th Cir. 1954) [58-1
USTC ¶9112]; Westover v. William Simpson Const. Co., 209 F. 2d
908 (9th Cir. 1954) [54-1 USTC ¶49,022]; United States v. Zschach
Const. Co., 209 F. 2d 347 (10th Cir. 1954) [54-2 USTC ¶9164].
The pertinent
portion of both contracts is as follows:
"With
respect to all persons at any time employed by or