Surety's
Interest Page4

The facts in
the instant case present a different situation. Steelcraft was the
principal on the payment bond executed to the Commodity Credit
Corporation with Fireman's Fund Indemnity Company as surety, and is
therefore liable for the unpaid material bills as principal upon this
bond under the Miller Act. In
United States
Fidelity and Guaranty Co. v.
United States
, 10 Cir., 201 Fed. (2d) 118, 121 [53-1 USTC ¶9249], the court
said:
"On the
date of the execution of the subcontract, the prime contractor had a
specific right of ownership in any funds accruing to the subcontractor
from the performance of the subcontract. The right to withhold these
funds upon default was superior to any other claim against the fund as
the property of the subcontractor."
This
specific right of ownership has even been held to extend to interest on
the sums expended by a surety. Glenn v. American Surety Co., 6
Cir., 160 Fed. (2d) 977 [47-1 USTC ¶9220]. Steelcraft as the principal
on the bond had a definite ownership in the amount due Hewkin for a
specific amount at all times. Steelcraft retained the ownership of the
funds to be paid to Hewkin until the contract was fully performed. This
amount was determinable by deducting from the subcontract price the
amount which Steelcraft had advanced to Hewkin from time to time as the
work progressed. Since Steelcraft is liable under the Miller Act to the
materialmen for their unpaid bills it was entitled to retain sufficient
funds to reimburse itself, based upon its prior right of ownership which
existed from the inception of the subcontract. United States Fidelity
and Guaranty Co. v. United States, supra; Glenn v. American Surety Co.,
supra. See also General Casualty Co. of America v. United States,
5 Cir., 205 Fed. (2d) 753 [53-2 USTC ¶9483]; Karno-Smith Co. v.
Maloney, 3 Cir., 112 Fed. (2d) 690 [40-2 USTC ¶9533]; In re
Caswell Const. Co., Inc., N. D. N. Y., 13 Fed. (2d) 667 [1 USTC ¶189];
American Fidelity Co. v. Delaney, D. Vt., 114 Fed. Supp. 702
[53-2 USTC ¶9620]; Great American Indemnity Co. v. United States,
W. D. La.
, 120 Fed. Supp. 445 [54-2 USTC ¶9469]; New York Casualty Co. v.
Zwerner, N. D. Ill., E. D., 58 Fed. Supp. 473 [45-1 USTC ¶9140].
The terms of
the contract obligated Hewkin to "furnish all materials and
supplies," thereby creating an implied condition of the subcontract
that the materialmen would be paid.
Houston
Fire and Casualty Insurance Co. v. E. E. Cloer, 5 Cir., 217 Fed.
(2d) 506;
United States
v.
United States
Fidelity and Guaranty Co., 2 Cir., 113 Fed. (2d) 888. The
materialmen are thus third-party beneficiaries of Steelcraft's specific
ownership in the amount due Hewkin derived by and from the date of the
subcontract. The government's claim is based upon the failure of Hewkin
to pay his taxes and he and his property alone are liable for their
payment. See Central Bank v. United States, 345
U. S.
639 [53-1 USTC ¶9408]. Steelcraft is not liable for the payment of
Hewkin's taxes to the government.
United States
v. Crosland Const. Co., 4 Cir., 217 Fed. (2d) 275 [55-1 USTC ¶9112].
See Great American Indemnity Co. v.
United States
, supra. Since Hewkin was not entitled to receive payment until be
complied with his subcontract he had no right of ownership in the amount
still due and the lien of the government never attached to this fund.
The rights of the government rose no higher than those of the taxpayer
whose right to the withheld sum never accrued. Great American
Indemnity Co. v. United States, supra; F. H. McGraw & Co. v. Sherman
Plastering Co., D. C. Conn., 60 Fed. Supp. 504, affirmed 2 Cir., F.
H. McGraw & Co. v. Milcor Steel Co., 149 Fed. (2d) 301, cert.
denied 326
U. S.
753. To hold otherwise would impose upon Steelcraft double liability,
that is, to the government and the unpaid materialmen. This would be
inequitable. See Karno-Smith Co. v. Maloney, 3 Cir., 112 Fed.
(2d) 690 [40-2 USTC ¶9533].
The bank
contends that its assignment is superior to the claim of the
materialmen. Steelcraft acknowledged the assignment but it is obvious
that Hewkin thereby intended to assign only his profit to be received
under the subcontract. See Mueller v. Northwestern University,
195
Ill.
256. Furthermore, the bank could stand in no better position against
Steelcraft than Hewkin, its assignee. Reeve v. Smith, 113
Ill.
47; Angelina County Lumber Co. v.
Michigan
Cent. R. Co., 252
Ill.
App. 32.
The bank does
have priority over the tax claim of the government. This is not disputed
by the government. The assignment to the bank was executed long before
the government's taxes were assessed. By virtue of 26
U. S.
C. A. 6323 (formerly 3672) the bank is a purchaser to the extent of the
amount it advanced to Hewkin as present consideration for the
assignment. National Refining Co. v.
United States
, 8 Cir., 160 Fed. (2d) 951 [47-1 USTC ¶9221]. Cf. Scovil v.
United States
, 348
U. S.
218 [55-1 USTC ¶9137]; R. F. Ball Construction Co. v. Jacobs, W.
D. Texas, 140 Fed. Supp. 60 [56-1 USTC ¶9514].
This court
therefore concludes that Steelcraft is entitled to an order that it be
discharged upon the payment of $15,361.51 into this court and the
materialmen are entitled to be paid their claims. The balance remaining
after the payment of these claims of the materialmen must be paid to the
bank. Since this absorbs the entire fund withheld there is nothing to be
paid to the government on withholding taxes.
Findings of
fact, conclusions of law and final order may be submitted.
[55-1 USTC
¶9407]United States of America, for the use and benefit of F. J. Gregg
and W. L. Budlong; R. Hugh Haynes, trading as Service Plumbing and
Heating Company; W. A. Browne, trading as Cavalier Electric Company; R.
Lee White, trading as Lee White Hardware Company, Plaintiff v. Seaboard
Engineering Corporation and U. S. Casualty Company, a New York
Corporation, Defendants
In
the United States District Court for the Eastern District of Virginia,
Newport News Division, Consolidated Civil No. 344, March 5, 1955
[1939 Code Sec. 3672--similar to 1954 Code Sec. 6323]
Collection of taxes: Liability of surety under Miller Act payment
bond.--The government was not entitled to recover from the taxpayer,
a surety under two payment bonds which it had executed pursuant to the
so-called Miller Act and in connection with two federal construction
contracts between its principal and the government, Federal income
withholding taxes and Federal Insurance Contributions Act taxes which
were unpaid and owing by its principal. Such taxes were not within the
coverage of the Miller Act payment bonds since the bonds merely promised
that taxpayer's principal would promptly pay all persons furnishing
labor or materials for use in the performance of the construction
contracts. The decision by CA-4 in U. S. v. Crosland Construction
Co., Inc. et al., 217 Fed. (2d) 275, 55-1 USTC ¶9112, was followed.
[Note: The District Court's prior memorandum opinion in this case
(54-2 USTC ¶9605) reached a contrary decision, but since the same issue
was on appeal to CA-4 in the Crosland case, the parties
stipulated that entry of judgment should await the decision of CA-4 in Crosland
and an order continuing the case was so entered. Accordingly, since the
District Court entered judgment for the taxpayer in accordance with the Crosland
case, its prior memorandum opinion is of no effect.]
John M.
Hollis, Assistant
United States
Attorney,
Norfolk
,
Va.
, for
United States
. Richard Newman,
Melson
Building
,
Newport News
,
Va.
, for plaintiff. Maurice B. Shapero, Bank of
Commerce
Building
,
Norfolk
,
Va.
, and
E.
Sclater
Montague
,
First
National
Bank
Building
,
Newport News
,
Va.
, for United States Casualty Corp. and Seaboard Engineering Corp.
Judgment
Order
WILKIN,
District Judge:
This cause was
referred on
February 10, 1953
, to Special Master
Rob
ert M. Saunders who, after taking testimony filed his report of
April 1, 1954
.
It was found,
among other things, by the Special Master that the United States
Casualty Company (hereinafter sometimes called Casualty Company) was
liable on two payment bonds that it had executed as surety in connection
with two federal construction contracts between the Seaboard Engineering
Corporation and the
United States
. These payment bonds were furnished in accordance with the Act of
August 24, 1935
, c. 642, 49 Stat. 793, the so-called Miller Act, and the condition or
promise of each bond was that Seaboard Engineering Corporation would
promptly pay all persons furnishing labor or materials for use in the
performance of these construction contracts.
In the
proceedings before the Special Master the
United States
asserted claims against the Casualty Company on its two payment bonds
for federal income withholding taxes and the employees' portion of
Federal Insurance Contributions Act taxes assessed against and owed by
Seaboard Engineering Corporation for the second quarter of 1952. These
taxes arose out of the performance of the two federal construction
contracts covered by the payment bonds.
The Special
Master refused to allow the claims of the
United States
on the ground that these claims were not within the coverage of the
payment bonds excepted by the Casualty Company. The
United States
filed an exception to this portion of the report of the Special Master.
Oral argument was heard on this exception on
July 21, 1954
, and briefs were thereafter submitted.
Thereafter, on
September 3, 1954, the court rendered its Memo Opinion [54-2 USTC ¶9605]
in which it expressed the view that the claims by the United States
asserted in this proceeding were within the coverage of a Miller Act
payment bond and in said memorandum of said date announced that in its
opinion the United States was entitled to recover from the Casualty
Company.
Inasmuch as
similar issues to those asserted in this case were then in process of
adjudication before the United States Circuit Court of Appeals, Fourth
Circuit, in the matter of United States of America, Appellant v.
Crosland Construction Company, Inc., Pacific Employers Insurance
Company, and American Indemnity Company, Appellees, Case No. 6891
[55-1 USTC ¶9112], the following was stipulated by counsel for both the
United States of America and counsel for Seaboard Engineering
Corporation and U. S. Casualty Company, a New York corporation, and said
stipulation was filed by Order of this Court among the papers in this
cause in the following words and figures, to-wit:
"STIPULATION
"It
is hereby agreed and stipulated by the undersigned attorneys for the
United States
and the United States Casualty Company that entry of judgment in the
above-entitled cause shall not be made until after the decision of the
Court of Appeals in United States v. Crosland Construction Company
now pending on appeal. It is further stipulated that in event any
judgment is entered for the
United States
it shall bear interest from
September 3, 1954
."
Simultaneously
with the filing of the foregoing Stipulation, the Court entered an Order
in the following words, to-wit:
"ORDER
"This
day came the
United States of America
and U. S. Casualty Company, a New York Corporation, by counsel, and
submitted at the bar of the court a STIPULATION IN WRITING, which is
herewith ordered filed, and pursuant to said stipulation it is ORDERED
that this proceeding be continued generally until the further Order of
this Court."
Thereafter, on
the 1st day of December, 1954, the United States Circuit Court of
Appeals, Fourth Circuit, rendered its decision in United States of
America, Appellant v. Crosland Construction Company, Inc., Pacific
Employers Insurance Company, and American Indemnity Company, Appellees,
217 Fed. (2d) 275 [55-1 USTC ¶9112], holding: "Though measured by
the amount of wages, the money due the
United States
was owing as taxes and not as wages. Such a claim is not covered by the
bond in this case."
In accordance
with the announced decisions of the Tenth Circuit, the Ninth Circuit,
the Fifth Circuit and the Fourth Circuit, the Court reverses its memo
opinion rendered on September 3, 1954 in this proceeding and concludes
that the claims by the United States of America for federal income
withholding taxes and the employees' portion of Federal Insurance
Contributions Act taxes are not within the coverage of the Miller Act
payment bond and, therefore, the United States is not entitled to
recover in this proceeding.
Accordingly,
it is further ORDERED that the report of the Special Master be approved
and confirmed.
WHEREFORE, it
is hereby ORDERED, ADJUDGED and DECREED that judgment be entered in
favor of the defendant, U. S. Casualty Company, a
New York
corporation.
[54-1 USTC
¶9404]
United States of America
, Plaintiff v. Crosland Construction Company, Inc., Pacific Employers
Insurance Company and American Indemnity Company, Defendants
In
the United States District Court for the Eastern District of South
Carolina, Columbia Division, C. A. 3580, 120 FSupp 792, April 30, 1954
Collection of taxes: Liens: Priority of surety's interest.--Sureties
of taxpayer paid the sub-contractors whom taxpayer had not fully
compensated. The court held that surety's liens thus arising on amounts
due the taxpayer on the indemnified contract relate back to the date of
the contract between the contractor and the hospital, as the surety has
all the rights of his principal. Such lien was prior in time over the
government's tax lien which was perfected after the contract had been
performed.
Collection of taxes: Liens: Priority to assigned funds.--Sureties,
holding an assignment from the taxpayer for amounts due to the taxpayer
on a contract which sureties indemnified, have priority over the
government's tax lien by reason of the assignment, which was delivered
according to the provisions of the application for the contract bond.
Collection of taxes: Federal Priority Statute.--Taxpayer's
sureties, who had paid off taxpayer's obligations to sub-contractors,
are not subject to the Federal Priority Statute, R. S. 3466, as taxpayer
must be in bankruptcy proceedings for that statute to apply. Here the
taxpayer was insolvent but not in bankruptcy.
Collection of taxes: Liens: Liability of sureties.--Sureties were
held not to have insured the collection of taxes owing by taxpayer, when
they indemnified "wages" to be collected from taxpayer. Sums
withheld from wages of employees of taxpayer do not constitute
"wages" within the meaning of the surety contract.
N. Welch
Morrisette, Jr. for plaintiff. Cooper,
Gary
, Whaley and McCutchen,
Columbia
, S. C., for defendants.
Opinion
and Order
WYCHE,
District Judge:
This action
was instituted on February 24, 1953, by the United States of America for
unpaid taxes due it by the defendant Crosland Construction Company, Inc.
for income withholding taxes for the third and fourth quarter-year
periods (periods ending September 30th and December 31st) of 1950, for
all four quarter-year periods of 1951, for federal insurance
contributions taxes for the third quarter-year period (period ending
September 30th) of 1950, and for federal unemployment taxes for the
years 1949, and 1950. The total amount of taxes claimed to be owing the
Government by the taxpayer, including interest and penalties, is
Thirty-Seven Thousand, Three Hundred Ninety and 41/100 ($37,390.41)
Dollars. By its amended answer, the taxpayer denies any tax liability in
excess of Thirty-Two Thousand, Three Hundred, Eighty-Two and 95/100
($32.382.95) Dollars, including interest and penalties. The defendants
Pacific Employers Insurance Company and American Indemnity Company are
sureties on the taxpayer's performance bond issued pursuant to a
construction contract between taxpayer and the
Newberry
County
Memorial
Hospital
,
Newberry
,
South Carolina
. The construction contract was entered into
June 10, 1949
, in the amount of Two Hundred, Twenty-Four Thousand, Seven Hundred One
and no/100 ($224,701.00) Dollars. The taxpayer and the sureties entered
into a performance bond bearing date of
June 29, 1949
. The taxpayer's application for contract bond bears date of
July 6, 1949
. Of the total taxes due the Government, only Two Thousand, Four Hundred
Eighty-Four and 31/100 ($2,484.31) Dollars, arise from performance of
the hospital contract; the remainder is from other construction
contracts performed by the taxpayer during the same or at about the same
time as the hospital contract.
It does not
appear that the sureties were involved in any job other than the
Newberry
Hospital
. The taxpayer answered the complaint and subsequently filed an amended
answer which admits its liability for taxes in the amount of Thirty-Two
Thousand, Three Hundred Eighty-Two and 95/100 ($32,382.95) Dollars, but
denies liability for any amount in excess of that sum. Taxpayer further
denies any liability on the part of the sureties for any taxpayer's
unpaid taxes, on their performance bond or otherwise.
The sureties
served notice of a motion for an order dismissing the complaint as to
them on the ground that it failed to state a claim upon which relief
could be granted. Subsequently, the Government moved for leave to amend
its complaint, which motion was granted in an order of the court dated
December 2, 1953
, with leave to the defendants to file amended answers, motions, or to
otherwise plead to the complaint as amended. Thereafter the sureties
amended their previous motion to dismiss by filing an amendment thereto.
The case is
now before me upon the amended motion of the sureties to dismiss.
Arguments were based on the pleadings and affidavits submitted by the
parties. The affidavits having been made a part of the record and having
been considered by the court, I stated that the motion to dismiss on
behalf of the sureties would be treated as a motion for summary judgment
under Rule 12(b); no objection was made thereto by any party and the
motion will be so treated.
The Collector
of Internal Revenue received the assessment lists for withholding taxes
as follows:
Assessment Notice
Period Ended List Rec'd and Demand
9-30-50
12-14-50
12-27-50
12-31-50
4-16-51
4-20-51
3-31-51
5-17-51
6-6-51
6-30-51
9-19-51
9-25-51
9-30-51
1-3-52
1-3-52
12-31-51
3-13-52
3-14-52
The Collector
of Internal Revenue received the assessment list for federal insurance
contributions taxes on
December 14, 1950
, notice and demand for payment being made on
December 27, 1950
.
The Collector
of Internal Revenue received the assessment lists for federal
unemployment taxes for 1949, on
March 19, 1951
, and for 1950, on
April 7 1952
.
The Government
filed notices of tax liens for the unpaid taxes on
July 20, 1951
(for $29,782.72) and
January 9, 1952
, (for $8,501.65) in the offices of the Clerk of Court,
Richland
County
,
Columbia
,
South Carolina
, and the Clerk of Court, United States District Court, Eastern District
of South Carolina,
Charleston
,
South Carolina
.
On January 5,
1952, and long after construction on the hospital contract had been
completed, the taxpayer executed a written assignment to the sureties of
retained percentages or sums due taxpayer on the hospital contract, in
consideration of the sureties' payment of certain outstanding claims of
materialmen and sub-contractors against the taxpayer incurred in the
performance of the hospital contract. These claims were paid by the
sureties, which they were obligated to do under their bond, and they
suffered losses thereby in excess of Three Thousand ($3,000.00) Dollars,
over and above the amount of the retainage. All work had been completed
on the
Newberry
Hospital
before
January 5, 1952
; the sureties did not supervise any work or complete the same.
On
January 10, 1952
, the Government served a levy on the
Newberry
County
Memorial
Hospital
for payment of Forty Thousand, One Hundred Ninety-Eight and 63/100
($40,198.63) Dollars, in taxes claimed due by taxpayer. The total amount
then remaining unpaid under the construction contract was Twenty-Four
Thousand, One Hundred, Eighty-Seven and 35/100 ($24,187.35) Dollars.
This amount was paid to the sureties by the hospital on
November 6, 1952
, by reason of the assignment of
January 5, 1952
.
The Government
claims it has a lien under Title 26 USCA Sections 3670, 3671, 3672 and
related sections, on the Twenty-Four Thousand, One Hundred, Eighty-Seven
and 35/100 ($24,187.35) Dollars, assigned to the sureties by taxpayer
and paid to them by the hospital, superior to the written assignment or
any lien or claim of the sureties to this sum. The Government also
asserts that even without a prior and superior lien under the statutes,
it is entitled to priority in payment over the sureties by reason of the
so-called "priority" statute (Section 3466 R. S., 31 USCA
Section 191). In addition, the Government claims the sureties are liable
on their performance bond in the amount of Two Thousand, Four Hundred,
Eighty-Four and 31/100 ($2,484.31) Dollars, for the taxes owed by
taxpayer from performance of the hospital contract.
The Government
has a lien on all property of the taxpayer by statute. 26 USCA 3670. The
lien arose at the time the assessment lists were received by the
Collector. 26 USCA 3671. The first assessment lists received by the
Collector were those received on
December 14, 1950
.
By paying the
materialmen and sub-contractors on the hospital contract, upon the
taxpayer's inability to pay, the sureties did what they were required to
do under their performance bond. The assignment of
January 5, 1952
, was executed and thereafter the sureties paid the materialmen and
sub-contractors. But even without the assignment of
January 5, 1952
, the sureties were required to satisfy the claims of these unpaid
materialmen and sub-contractors under the terms of the performance bond.
Upon the
sureties' performance under their bond obligation, they acquired an
equitable lien against any sum remaining in the hands of the one for
whose protection the bond was given. This lien relates back to the date
of the contract and is superior to any lien arising thereafter. Prairie
State Bank v. United States, 164 U. S. 227, 17 S. Ct. 142, 41 L. Ed.
412; Henningsen v. U. S. Fidelity & Guaranty Co., 208 U. S.
404, 28 S. Ct. 389, 52 L. Ed. 547; Town of River Junction v. Maryland
Casualty Co., (C. A. 5) 110 Fed. (2d) 278, Cert. den. 60 S. Ct.
1077; Standard Acc. Ins.
Co.
v. Federal Nat. Bank, (C. A. 10) 112 Fed. (2d) 692, affirmed on
rehearing, 115 Fed. (2d) 34; Exchange State Bank v. Federal Surety
Co., (C. A. 8) 28 Fed. (2d) 485, 488; Claiborne Parish Sch. Bd.
v. Fidelity & Deposit Co. of Maryland, (C. A. 5) 40 Fed. (2d)
577, 579; Maryland Casualty Co. v. Dulaney Lumber Co., (C. A. 5)
23 Fed. (2d) 378, 380; Fidelity & Deposit Co. v. Union State
Bank, (D. C. Minn.) 21 Fed. (2d) 102, 104; In re Van Winkle,
(D. C. Ky.) 49 Fed. Supp. 711; United States F. & Guaranty Co. v.
John R. Alley & Co., (D. C. Okla.) 34 Fed. Supp. 604; Southern
Surety Co. v. J. R. Holden Land & Lumber Co., (C. A. 8) 14 Fed.
(2d) 411, 413; American Fidelity Co. v. Delaney, (D. C. Vt.) 114
Fed. Supp. 702. It is superior to the Government's lien for unpaid
taxes. American Surety Co. v. City of
Louisville
M. H. Comn. (D. C.
Ky.
) 63 Fed. Supp. 486, affirmed 160 Fed. (2d) 977 [47-1 USTC ¶9220]; Glenn
v. American Surety Co., (C. A. 6) 160 Fed. (2d) 977 [47-1 USTC ¶9220];
United States Fidelity & Guaranty Co. v. United States, (C.
A. 10) 201 Fed. (2d) 118 [53-1 USTC ¶9249]; New York Casualty Co. v.
Zwerner, (D. C. Ill.) 58 Fed. Supp. 473 [45-1 USTC ¶9140]; American
Fidelity Co. v. Delaney, (D. C. Vt.) 114 Fed. Supp. 702 [53-2 USTC
¶9620]. The performance bond was executed on
June 29, 1949
; therefore, the sureties' lien is superior to any lien arising
thereafter, including the Government's lien for taxes which dates from
December 14, 1950
.
In addition to
an equitable lien, the sureties have a written assignment of any funds
remaining in the possession of the hospital under the provisions of the
application for contract bond. Such a provision is valid and
enforceable. Lacy v. Maryland Casualty Co., (CA 4) 32 Fed. (2d)
48. Accordingly, the rights of the sureties to the funds remaining in
the hands of the hospital were not determined solely by the assignment
of January 5, 1952, but by bond and application therefor (in view of the
sureties' performance under the bond) and by the sureties' equitable
lien.
The
Government's rights to the funds in the hands of the hospital are no
greater than the rights of the taxpayer. F. H. McGraw & Co. v.
Sherman Plastering Co., (D. C. Conn.) 60 Fed. Supp. 504, affirmed,
149 Fed. (2d) 301, cert. den. 326
U. S.
753, 66 S. Ct. 92, 90 L. Ed. 452; United States Fidelity &
Guaranty Co. v.
United States
, (CA 10) 201 Fed. (2d) 118 [53-1 USTC ¶9249].
Upon
performance under its bond, a surety is subrogated to the rights of the
obligee to any funds remaining in possession of the latter which were
retained under the contract with the principal. Farmer's Bank v.
Hayes, (CA 6) 58 Fed. (2d) 34; Lacy v. Maryland Casualty Co.,
supra. See, Amer. Surety Co. v. Bethlehem Bank, 314
U. S.
314, 62
S. Ct.
226, 68 L. Ed. 214; In re Baltimore Pearl Hominy Co., (CA 4) 5
Fed. (2d) 553 [1 USTC ¶130].
The
Government's claim of priority over the sureties to the funds retained
by the hospital is based on Section 191, 31 USCA, which gives the
United States
priority in payment of funds of an insolvent under certain conditions.
It is claimed that the taxpayer was without sufficient assets to meet
its obligations and was therefore insolvent at the time of the
assignment of
January 5, 1952
. It is admitted by the taxpayer that it was without assets sufficient
to meet its obligations sometime prior to this assignment. In that sense
the taxpayer is and was insolvent. However, the taxpayer continued in
business after this assignment and, in fact, still is in business. No
claim is made that the taxpayer has been adjudged a bankrupt or that
receivership or bankruptcy proceedings have been brought against it or
that it has made a general assignment for the benefit of creditors.
The
"priority" statute applies only to cases involving some type
of insolvency court proceedings disposing of an insolvent's estate. Conard
v. The Atlantic Insurance Co., 1 Pet. 386, 7 L. Ed. 189; United
States v. Oklahoma, 261 U. S. 253, 43 S. Ct. 295, 67 L. Ed. 638; Bramwell
v. U. S. Fidelity Co., 269 U. S. 483, 46 S. Ct. 176, 70 L. Ed. 368; Glenn
v. American Surety Co., (C. A. 6) 160 Fed. (2d) 977 [47-1 USTC ¶9220];
Davis v. Pringle, (CA 4) 1 Fed. (2d) 860, affirmed 268
U. S.
315, 45 S. Ct. 549, 69 L. Ed. 974; Davis v. Miller-Link Lumber Co.,
(CA 5) 296 Fed. 649;
United States
v. The Pomare (D. C. Hawaii), 92 Fed. Supp. 185; American
Surety Co. v. City of
Louisville
M. H. Comn., (D. C. Ky.) 63 Fed. Supp. 486, affirmed, 160 Fed. (2d)
977 [47-1 USTC ¶9220]; New York Casualty Co. v. Zwerner, (D. C.
Ill.) 58 Fed. Supp. 473 [45-1 USTC ¶9140]; United States v.
Woodside, (D. C. S. C.) 34 Fed. Supp. 281. See also, United
States v. Hooe, 3 Cranch 73, 2 L. Ed. 375; Prince v. Bartlett,
8 Cranch (12 U. S.) 431, 434, 3 L. Ed. 614; Brent v. Bank of
Washington, 10 Pet. 596, 611, 9 L. Ed. 547; Beaston v. The
Farmers' Bank of
Delaware
, 12 Pet. 102, 132, 9 L. Ed. 1017; and In re Baltimore Pearl
Hominy Co., (D. C. Md.) 294 Fed. 921 [1924 CCH ¶2861], reversed on
other grounds, (CA 4) 5 Fed. (2d) 553 [1 USTC ¶130]. This is not a
proceeding involving the disposition of an insolvent's estate;
therefore, the "priority" statute has no application.
Whether the
sureties are liable on their bond for the taxpayer's taxes resulting
from performance of the hospital contract will now be determined. Taxes
owed by the taxpayer are owed by virtue of law and not because of any
contractual relationship. Central Bank v. United States, 345 U.
S. 639, 73 S. Ct. 917, -- L. Ed. -- [53-1 USTC ¶9408]; United States
Fidelity & Guaranty Co. v. United States, (CA 10) 201 Fed. (2d)
118 [53-1 USTC ¶9249]. See, American Fidelity Co. v. Delaney,
(D. C. Vt.) 114 Fed. Supp. 702; New York Casualty Co. v. Zwerner,
(D. C. Ill.) 58 Fed. Supp. 473 [45-1 USTC ¶9140]; Westover v.
William Simpson Construction Co., (CA 9) 22 L. W. 2384 (
1-28-54
) [54-1 USTC ¶49,022].
Sums withheld
by the taxpayer from the wages of its employees do not constitute
"wages" within the terms of a surety's bond for wages. United
States Fidelity & Guaranty Co. v. United States, supra; United
States v. Zschach Const. Co., (D. C. Okla.) 110 Fed. Supp. 551 [53-2
USTC ¶9529] (holding that a surety's bond is to indemnify the owner and
not the
United States
for taxes). The sums retained by the hospital and assigned by the
taxpayer to the sureties were for payment of materialmen and
sub-contractors and no part of this sum was used to pay wages of
employees of the taxpayer. But even if the sureties had paid wages owing
to the employees of the taxpayer, the sureties still would not be liable
for the taxes in this case. See, United States Fidelity &
Guaranty Co. v.
United States
, supra; American Fidelity Co. v. Delaney, supra; Westover v. William
Simpson Construction Co., supra. It follows that the sureties are
not liable on their bond for the taxpayer's unpaid taxes arising from
the hospital contract.
Accordingly,
IT IS ORDERED,
That the defendants Pacific Employers Insurance Company and American
Indemnity Company, sureties, have judgment entered in their favor, and
IT IS SO
ORDERED.
[56-2 USTC
¶10,076]Wayne C. Huddleston v. U. S. Air Conditioning Corporation et
al. The
United States of America
for the use of R. F. Zimmerman & Co. v. The Travelers Indemnity
Company et al.
U.
S. District Court, So. Dist. Tex., Corpus Christi Div., C. A. 1271,
1312, 9/22/56
[1939 Code Secs. 3670, 3671--covered in 1954 Code Secs. 6321, 6322]
Assessment: Lien for taxes: Fund withheld by general contractor from
subcontractor.--A general contractor withheld certain money due a
subcontractor on an Air Force base construction job because the
subcontractor had failed to pay materialmen. The money was deposited in
the district court in connection with an interpleader action. The
Government intervened, asserting tax liens against the deposited fund
for taxes due by the subcontractor, and claimed that it had a prior
specific and perfected lien against the fund since the lien related back
to and attached on the dates the assessment lists were received by the
District Director. The court refused to sustain the Government's
position, pointing out that the statute provided for a lien against
property belonging to the taxpayer. Here, the court found, the
subcontractor had no property rights in the withheld money because, by
agreement, the general contractor could not pay him until he had
furnished proof of payment of materialmen. Specifically, the court held
that at the time the assessment lists were received by the District
Director, the subcontractor had no property or right to property in the
hands of the general contractor, and no equity to which the tax lien
could or did attach. The general contractor's right to apply the
withheld funds toward the payment of materialmen was good even against
the Government.
Gus Kowalski,
Kingsville, Tex., Kleberg, Mobley, Lockett & Weil, Jones Building,
Corpus
Christi
,
Tex.
, for plaintiff Huddleston. L. L. Gragg, Jones Building, Corpus Christi,
Tex., for U. S. Air Conditioning Corporation. Carter, Stiernberg &
Skaggs, Post Office Box 809, Harlingen, Tex., for R. F. Zimmerman &
Co. Malcolm R. Wilkey, United States Attorney, Willard I. Boss,
Assistant United States Attorney, Houston, Tex., for Intervenor, United
States of America. Elmer H. Theis, Medical Professional Building, Corpus
Christi, Tex., for East Texas Plumbing Supply Co. Lewright, Dyer,
Sorrell & Redford, J. M. Burnett, Driscoll Building, Corpus Christi,
Tex., for Travelers Indemnity Company. Ungerman, Hill & Ungerman,
Wilson Building, Dallas, Tex., for Minneapolis-Honeywell Regulator Co.
Lloyd & Lloyd, Alice, Tex., for Roger J. Seaman.
[Interpleader
Action]
ALLRED,
District Judge:
These
consolidated actions primarily involve the rights of four claimants to
$4,735 deposited in the registry of the court by Huddleston, in an
interpleader action. The Government has intervened, asserting liens
against the fund for taxes due by Leo Gist who was a subcontractor under
Huddleston in the construction of a dental clinic building at Harlingen
Air Force Base. As a result of pretrial hearings, detailed and difficult
stipulations were worked out. The court is appreciative of the careful
and painstaking efforts of all counsel in the case in entering into
stipulations and avoiding a long and complicated trial.
Huddleston is
the successor to Huddleston-Seaman Construction Company, which was the
general contractor for construction of the building at Harlingen Air
Force Base; as such, he is subject to all the liabilities and has all
the rights of the original contractor. Therefore Huddleston's name will
be used throughout this memorandum just as though he were the original
contractor.
[Materialmen
Not Paid by Subcontractor]
Gist, the
subcontractor, completed his contract with Huddleston but did not pay
for materials furnished by four suppliers as hereafter set out.
Traveler's Indemnity was surety on Huddleston's bond given as provided
in the Miller Act, 40 U. S. C. A. 270a et seq. The unpaid claims are as
follows:
United States Air Conditioning Co. ..... $3,228.50
R. F. Zimmerman & Co. .................. 1,994.00
Minneapolis-Honeywell Regulator Co.
(balance) .............................. 190.00
East Texas Plumbing Co. ................ 341.93
Total .................................. $5,754.43
These unpaid
claims total more than the amount tendered into court (4,735.00) to say
nothing of the Government's tax claims totaling $9,916.96.
Huddleston
completed the contract, the building was accepted and final settlement
made
May 3, 1954
. During the construction, the contractor received progress payments of
90%, as provided in the contract. Huddleston, in turn, made 90% payments
to Gist from time to time. These payments totaled $20,908.65, the last
payment ($4,441.34) being made
February 28, 1954
. Prior to that time, Huddleston had learned from Gist's suppliers that
he was not paying them promptly and had determined not to make further
payments to him except upon proof that he had paid all of such
suppliers. At the time of the last payment on February 28, 1954, after
considerable discussion, it was agreed between Huddleston and Gist (1)
that out of the $4,441.34 paid that day, Gist would pay Zimmerman's
claim ($1,994.00); and (2) that no further payments would be made to
Gist but the balance would be held by Huddleston till Gist furnished
proof of payment of outstanding bills. Both of them understood that at
the time that Huddleston would be liable under the Miller Act for
supplies and labor owned by Gist and the agreement was made in order
that Huddleston might protect himself against such claims.
[Prime
Contractor Withheld Funds]
After the last
payment on
February 28, 1954
, a balance of $3,709.37 was due Gist under the contract. This amount
was withheld by Huddleston. It would have been sufficient to pay all
outstanding bills provided Gist paid the Zimmerman bill, as agreed, out
of the $4,441.34 payment of February 28th. In March or April 1954,
Huddleston learned that Gist had not paid Zimmerman. Therefore
"Huddleston awarded to Gist contracts to do other work in Corpus
Christi in an effort to give Gist opportunity to make a profit to be
applied by Huddleston to reimbursement for the excess of (a)
amounts paid and owed to Gist and his suppliers over (b) the
contract price as to the dental clinic. Gist authorized such reimbursement
at the time of the agreements to do such additional work."
As stated,
Huddleston has paid $4,735 into the registry of the court. This
represents the $3,709.37 withheld from Gist on the
Harlingen
contract and $1,025.63 withheld on the
Corpus Christi
job under the agreement.
Huddleston was
in direct and daily supervision of the Harlingen job, familiar at all
times with the labor and materials performed for and furnished to Gist
by various suppliers, including those whose claims are involved here,
and approved such labor and materials so provided in performance of
Gist's subcontract, although he did not know until later of the exact
contract or invoice prices. After the two agreements with Gist as to
withholding moneys due on either job, Huddleston paid three Miller Act
claimants (on the
Harlingen
job) as follows:
Minneapolis-Honeywell ....... $500.00
Mar. 8, 1954
Gist and Hargis Electric
Co.
......................... $207.32
Aug. 16, 1954
Gist and Southern Engine
& Pump Co. .................. $524.00
Aug. 16, 1954
Huddleston
later (November 10, 1954) issued a check to East Texas Plumbing Company
for its account $341.93. Their representatives were to meet for delivery
of the check but failed, for some reason, to do so. Huddleston also
issued checks later (November 13, 1954) to the other claimants
(Zimmerman, U. S. Air Conditioning Co., Honeywell), with Gist, or his
company, as joint payee. These checks were issued, although they totaled
more than the $4,735 due Gist on both the
Harlingen
and
Corpus Christi
jobs, "because Huddleston was familiar with the Miller Act and knew
he would be liable for unpaid labor and materials supplied to
Gist." None of these checks have been paid because of failure to
secure Gist's endorsement promptly and later demands made by the
Collector of Internal Revenue (after notice of Levy,
December 8, 1954
), that payment be stopped. This was the first notice Huddleston or the
claimants had of the tax claims against Gist.
[Government
Intervenes]
The Government
claims the fund in the registry by virtue of alleged tax liens, Internal
Revenue Code (1939) 3670, 3671, asserting that the lien relates back to
and attached on the dates the assessment lists were received by the
District Director of Internal Revenue, the first being
May 17, 1954
, for $2,466.88. 1
The Government takes the position that it has a prior specific and
perfected lien against the fund whereas the other claimants have only a
right to garnish the fund. 2
[Statute
Discussed]
Section 3670
of Title 26, in effect at the time, provided for a lien in favor of the
Government for unpaid taxes, "upon all property and rights to
property, whether real or personal, belonging to such person,"
3
(the taxpayer). Section 3671 provided that, unless another date was
specifically fixed by law, the lien should arise at the time the
assessment list was received by the collector, etc. Section 3672
provided that the lien should not be valid as against any mortgagee,
pledgee, purchaser, or judgment creditor until notice thereof had been
filed by the collector in the manner therein prescribed. Before becoming
lost in discussion of the many cases as to priority of liens, it
would be well to remember the basic fact that the lien provided by
Section 3670 is on property and rights to property BELONGING TO
THE TAXPAYER. Here, Gist's right to the balance due on both contracts
with Huddleston was burdened with the equitable and contractual right of
Huddleston to refuse to pay him until Gist furnished proof of payment of
all outstanding bills; and to Huddleston's right to pay such accounts
for his own protection against such claimants; and to the agreement in
March or April, 1954, authorizing Huddleston to reimburse himself for
any excess of the amounts paid or owed Gist and his suppliers
over the contract price as to the dental clinic. Any demand on Gist's
part for payment of either balance would have been denied by any court
because he had nothing coming until all claims were paid. Any garnishing
creditor of Gist's, or even The Government on its tax claims, could
stand in no better position than Gist as against Huddleston. 4
The Miller Act does not purport to give suppliers of materials, etc., a
lien on funds due the subcontractor; rather it is a right of action
on the bond required by the act, provided proper notice is given.
But the requirement as to notice is to be, and has been, liberally
construed, to the point that an oral notice by the supplier, later
acknowledged in writing by the prime contractor, has been held
sufficient. 5
[Question
of Notice]
Here there can
be no doubt that Zimmerman, Honeywell and East Texas Plumbing gave
sufficient written notice to Huddleston, within 90 days after the last
of the supplies, etc. were furnished; so that not even Huddleston may
now urge, and he does not urge, lack of written notice. The situation is
a bit different as to U. S. Air Conditioning Corporation. There is no
showing that it gave notice, or that Huddleston acknowledged such claim
in writing, within 90 days. It is clear, however, that Huddleston knew
that the air conditioning equipment had been furnished, when it was
furnished, the amount of the claim and that Gist had not paid
it,--all within the 90 day period. It is equally clear that within the
90 day period Huddleston recognized such claim and held back money for
the purpose of paying it, along with others, at the time of the
agreement of
February 28, 1954
. Huddleston says in his affidavit that Gist agreed to pay Zimmerman's
account ($1,994.00) out of the $4,441.34 final payment of February 28th.
Gist did not keep his agreement. If he had paid the Zimmerman account,
there would have remained, so far as we are concerned here, only the
claims of U. S. Air Conditioning Corporation, East Texas, and the
balance due Honeywell, all three totaling $3,760.43. 6
This is so close to the $3,709.37 withheld by Huddleston that it shows
he knew almost exactly what was due these three unpaid suppliers. So it
appears that the reason for the supplemental agreement in March or
April, 1954, whereby Huddleston was also to withhold Gist's profits on
the
Corpus Christi
houses, was that Huddleston had been notified in writing,
April 12, 1954
, that Zimmerman had not been paid. 7
The 90 days
notice requirement is for the protection of the prime contractor and his
surety in order that he may do exactly what Huddleston did here--hold
back sufficient moneys to indemnify him or his surety. Since he knew of
U. S. Air Conditioning's claim, held back enough to take care of it and
later committed himself in writing to pay it, he hardly could be heard
to plead in a Miller Act case that he did not get the written notice
within 90 days. It is clear that Huddleston waived such requirement
during the 90 day period and agreed to pay in writing after the 90
days, by, among other things, the issuance of checks for the amounts
claimed. Huddleston wanted to be protected against such claims, perhaps
against a lawsuit even though he might have the right to plead that
there was not sufficient notice within 90 days; therefore he withheld
from Gist sufficient moneys to pay all of them except Zimmerman. He took
his chance as to Zimmerman by relying upon Gist to pay this claim out of
the February 28th payment. The remaining claimants should not suffer
when Huddleston held out sufficient moneys to pay them, and could have
held back sufficient [moneys] to pay the Zimmerman claim but saw fit to
rely on Gist to pay that account. As pointed out, Huddleston retrieved
and bettered his position by $1,105.63 by holding back that amount on
the profits on the
Corpus Christi
job. (He lacked $968.37, however, of getting enough to take care of the
Zimmerman claim in full.)
[Tax
Lien Did Not Attach]
I find it
unnecessary to discuss all the propositions and authorities asserted by
the parties. Suffice to say that, as to the Government's claim for
liens, I hold that, at the time the assessment lists were received by
the District Director, 8
Gist had no property or rights to property in the hands of Huddleston
and no equity to which the lien could or did attach. Huddleston had a
specific right of ownership to any funds due Gist, superior to
any tax lien of the Government. 9
He had a right, under the agreements with Gist, made long before the
Government's tax lien attached, to reimburse himself for any amounts due
Gist and his suppliers. This really is not a case as to priority
of liens between the claimants and the Government. Rather it is between
the right of Huddleston on the one hand to see that the money withheld
by him is applied to the payment of claims for which he was or might be
liable and the Government on the other. Huddleston's right to so apply
the funds was and is good against Gist. It was and is good against the
Government.
This also
disposes of the Government's contention that a fee cannot be allowed to
Huddleston's attorneys who were compelled to institute the action
because of demands of the Government. The suppliers' claims total more
than the funds against which the Government asserts its tax liens.
Zimmerman
timely filed his action under the Miller Act and is entitled to recover
against Travelers as surety to the extent that it does not secure
payment from Huddleston as principal. U. S. Air Conditioning,
East Texas
and Honeywell are entitled to recovery against Huddleston who may apply
the funds in the registry to the payment, pro rata, of all the claims. A
fee of $1,000 will be allowed Huddleston's attorneys out of such fund.
The remainder will be prorated between
Zimmerman
,
U. S.
Air Conditioning,
East Texas
and Honeywell in proportion to their claims. In addition, Zimmerman will
be given judgment against Huddleston's surety, Travelers, for the
difference between the total of his share of the funds on deposit, and
his share of the attorney's fees, and the $1,994.00.
The foregoing
is adopted as findings of fact and conclusions of law.
The Clerk will
notify counsel to submit an order accordingly.
1
The dates the other assessment lists were received were as follows:
June 22, 1954
, ($6,024.70);
September 9, 1954
, ($1,425.32).
2
As in Kings County Iron Works, 2 Cir., 224 Fed. (2d) 232 [55-2
USTC ¶9536] and United States v. White Bear Brewing Co., Inc., et
al., 350 U. S. 1010 [56-1 USTC ¶9440], reversing 7 Cir., 227 Fed.
(2d) 359 [55-2 USTC ¶9776].
3
Emphasis mine throughout unless otherwise indicated.
4
Cf. Great American Indemnity Co. v.
United States
, (D. C.,
La.
), 120 Fed. Supp. 445 [54-2 USTC ¶9469], United States v. Bank of
Shelby, 5 Cir., 68 Fed. (2d) 538 [4 USTC ¶1226].
5
Houston Fire & Casualty Insurance Company v.
United States
, 5 Cir., 217 Fed. (2d) 727, in which, however, the written
acknowledgment was within 90 days of the last delivery.
6
Of course, at the time of the agreement there also was due the amounts
paid Gist and Hargis, Gist and Southern, and the $500 paid on
Honeywell's account; but the amount due Gist on the Harlingen contract
was sufficient to take care of these and U. S. Air Conditioning, East
Texas and the Honeywell balance.
7
See Exhibit H. Pretrial Order.
8
May 17, June 22,
September 9, 1954
.
9
United States Fidelity & Guaranty Co. v.
United States
, 10 Cir., 201 Fed. (2d) 118 [53-1 USTC ¶9249].
[62-1 USTC
¶9229]A. J. Bankhead doing business as Airtrol Engineering Company,
Plaintiff v. Maryland Casualty Company, Irving Ward-Steinman, R. F.
Zimmerman & Company, Inc., and United States of America, Defendants
U.
S. District Court, East. Dist. La., Baton Rouge Div., Civil Action No.
2131, 197 FSupp 879, 9/26/61
[1954 Code Sec. 6321]
Priority of liens: Federal tax lien: Surety's subrogration claim.--The
Federal tax lien on retained percentages was held to be prior to a
surety's claim of subrogation for amounts paid to materialmen and
laborers on behalf of a defaulting subcontractor. The latter claims were
not perfected and lacked specificity as to any particular fund.
David W.
Rob
inson and Watson, Blanche, Wilson, Posner & Thibaut, 137 St.
Ferdinard St., P. O. Box 36, Baton Rouge 2, La., for plaintiff. Elven E.
Ponder and Major & Ponder, 5053 Government St., Baton Rouge, La.,
Paul M. Hebert, Dean of Law School, Louisiana State University, Baton
Rouge, La., Victor A. Sachse, III, of Breazeale, Sachse, Wilson &
Hebert, 701-719 Fidelity National Bank Bldg., Baton Rouge, La., M.
Hepburn Many, United States Attorney, New Orleans, La., Prim B. Smith,
Jr., Assistant United States Attorney, and Leonard Fuhrer of Gravel,
Sheffield & Fuhrer, 611 Murray St., Alexandria, La., for defendants.
WRIGHT,
District Judge:
This suit in
interpleader involves the sum of $11,208.39 paid into the registry of
the court by Airtrol Engineering Company, representing retained
percentages on a subcontract between Airtrol and the Yerby Tin Shop.
Upon default by Yerby, his surety, Maryland Casualty Company, was called
upon to complete the subcontract and now claims the retained funds. The
United States
has assessed withholding taxes against Yerby and it likewise claims the
fund. While the representative of Yerby's estate and a materialman are
interpleaded, the dispute is essentially between
Maryland
and the
United States
.
On
October 29, 1956
, Airtrol signed a contract with the Louisiana State Authority to
provide air conditioning facilities for
Louisiana
State
University
at
Baton Rouge
. Airtrol subcontracted the sheet metal work for the air conditioning to
Yerby on
December 12, 1956
.
Maryland
executed a performance bond for Yerby's contract on
November 1, 1956
. Pursuant to this bond Yerby assigned all payments due or to become due
under the contract to
Maryland
in case of default. Payment terms for the Airtrol-L. S. U. contract and
the Airtrol-Yerby contract both provided for thirty-day estimates of
work completed and retention of percentages until completion and
acceptance of the work.
With the work
95 per cent complete, Yerby encountered financial difficulties. On
January 3, 1958
, Airtrol formally put Yerby in default and called upon
Maryland
to complete the work. On
January 6, 1958
, Yerby also called upon
Maryland
to perform. On
January 8, 1958
, the
United States
assessed withholding taxes against Yerby in the amount of $13,988.01. A
later assessment on
March 3, 1958
, will be disregarded since the January 8 assessment would exhaust the
fund.
After Yerby's
default
Maryland
expended $21,911.49 in completing the work and satisfying prior claims
arising before Yerby's default. The job was accepted by the Louisiana
State Authority on
February 6, 1958
. On the same day R. T. Zimmerman filed a mechanic's lien pursuant to
La. R. S. 9:4801 and La. R. S. 38:2241. 1
A similar lien was filed by John T. Megison, a foreman, on
March 2, 1958
. Both the Zimmerman and the Megison claims arose before default.
Maryland
satisfied these claims and asserts the lien rights arising thereunder by
subrogation.
On default the
retainage on the Yerby contract amounted to $11,208.29. Being faced with
several claimants to this fund, Airtrol filed this interpleader.
Although
Maryland
's claim rests on three grounds, its principal reliance is on the
proposition that the retainage in suit never became the property of
Yerby and consequently there was nothing to which the federal tax lien
could attach. The
United States
claims that Yerby had a right to the retained percentages which was
perfected on completion of the job, and, under applicable federal law,
its claim is prior to all other liens or claims on the fund.
The contest
between the federal tax collector and private claimants for various
funds, while of relatively recent origin, has a complexity beyond its
years. 2
When the fund involved is retained percentages held by an owner in the
presence of a defaulting contractor and an incomplete building, and
contest is even more recent but of comparable complexity, involving, as
it does, a host of decisions interpreting priorities, 3
relation back, 4
the "no debt" theory, 5
and, more recently, the application of state property law and federal
priority law. 6
From the older cases, and now from recent Supreme Court decisions,
certain general principles emerge.
Federal tax
liens are not property rights; they are claims to property which require
perfecting as do other claims. 7
Being statutory liens, 8
they take preference over open accounts and inchoate and unperfected
liens. 9
Likewise, assignments, without more, although prior in time to federal
tax assessments, are subordinate to the tax lien because of the greater
dignity of the tax lien under federal law. 10
Private
claimants may assume a variety of positions. They may be simple
creditors, or holders of mechanic's liens, or assignees, or sureties, or
subrogees to private liens, or subrogees to private rights. For a
private lienor to take preference over a federal tax lien, its lien must
be perfected by prior recordation, 11
or other "perfecting" device cognizable by federal law. Its
priority may be based on a theory of relation back to the date of
creation of the original debt. 12
For a private assignee to take preference over a federal tax lien, he
apparently must reduce his assignment to judgment, although this is not
altogether certain. 13
For a surety to assert subrogative rights to property of parties other
than the taxpayer, the surety must show that the property does not
belong to the taxpayer against whom the federal tax lien is asserted. 14
In balancing
these various claims, it must first be determined whether the taxpayer
owns the property against which the federal tax lien is asserted
according to state law. 15
If it is determined that the fund in question is the property of the
taxpayer, then the various claims to the fund must be ranked according
to federal law. 16
In the present
case, the fund involved is retained percentages withheld by the general
contractor, Airtrol, from the subcontractor, Yerby, and claimed by the
federal tax collector and the subcontractor's surety. The surety's
principal claim, and the one upon which it must stand, is that the
retained percentages are the property of Airtrol since the owner, or as
in this case the general contractor, has the right, under Louisiana law,
to apply retained percentages to the completion of the work. Thus, only
the balance remaining after completion, if any, belongs to the
subcontractor and is subject to the federal tax lien. The surety, if it
completes the work, is subrogated to the owner's rights, and thus the
portion of the retained percentages used in completion of the work
belongs to the surety.
The respective
rights among owners, contractors, contractors' creditors, and sureties
to retained percentages when a job is incomplete have been spelled out
by the
Louisiana
courts and legislature in rather specific terms. The statute creating
the
Louisiana
counterpart to federal interpleader, the concursus proceeding, states in
part:
"In
the event that the owner has claims in concursus with the other
claimants who have a privilege on his property under the provisions of
this Sub-part, the cost of completing the building or other work by
reason of the default of the original contractor, when established to
the satisfaction of the court and when paid for by the owner, shall be
reimbursed to him by preference out of any balance which might have been
due under the contract if completed by the contractor; but the owner
shall have no claim for the excess in the cost of completion if such
cost exceeds the amount of the said balance, or for any other of his
claims against the surety on the bond of the contractor until all other
claimants have been paid in full."
La.
R. S. 9:4804.
An
early case in
Louisiana
jurisprudence gave the owner in a concursus proceeding the right to
offset the amounts needed to complete the job against retained
percentages required to be paid into court. 17
The setoff was ordered since "[w]hatever was necessarily and
reasonably expended for that purpose [completion] must be deducted from
the stipulated instalment, and the balance only belongs to Wills
[contractor], or his creditors." 18
The Supreme Court of Louisiana explained that the purpose of retained
percentages was "to create a temporary fund to insure all the
better the payment of claims against the work, and to enable better the
owner, or the surety, in the event of necessity, to complete the
undertaking." 19
In a similar concursus proceeding, the plaintiff failed to pay retained
percentages into court as required by statute. In excusing this the
Louisiana Supreme Court said:
"In
the present case, plaintiff has not made a tender and deposit of the
'balance due under the contract' for the reason that the building has
never been completed and it will require more than the amount in
plaintiff's possession to complete it. If this be true, and we must
accept the allegations of the petition as true for the purposes of the
exception, plaintiff is entitled to exhaust the funds in its possession
to complete the contract, and there is therefore no 'balance due' the
contractor under the contract, to be tendered and deposited into
court." 20
If
only to make the position more definite, the Court later explained the Natchitoches
Sweet Potato Co. case in the following succinct language:
"All
that we said in that case [Natchitoches Sweet Potato Co. v.
Perfection Curing Co.] was (in effect) that there was nothing due
the contractor by the owner under the contract when the contractor had
defaulted, and it would require more than the unpaid balance of the
contract price to complete the building. In other words, there was no
balance due under the contract because the contractor had not earned it
by completing the contract." 21
The conclusion
that
Louisiana
law gives the owner, and the surety, a property right in the retained
percentages when the job is incomplete at the date of default is
supported by the rule that the equitable lien theory does not obtain in
Louisiana
. 22
Neither surety nor owner had a statutory lien on the retainage and the
right does not arise out of specific terms in the contract. Since
Louisiana
does not give owner and surety a "claim" on the retainages but
does give them a right prior to all "claims," the indication,
along with the specific words of the statute and cases, is strong that
this is a property right and not a claim on property.
Thus it is
apparent that the law of Louisiana is quite similar to the law generally
as stated in Prairie State Bank v. United States, 164 U. S. 227, 23
and the Fifth Circuit's decision in General Casualty Co. v. Second
Nat. Bank of
Houston
, 5 Cir., 178 F. 2d 679. 24
While
Louisiana
law in the present case would probably be at variance with
North Carolina
law as found in U. S. v. Durham Lumber Co., supra,
Durham
supports the conclusion reached here that the
United States
may claim only that portion of the funds which belonged to the taxpayer.
However,
simply expending money after the subcontractor's default does not
automatically give the surety the right to reimbursement from the
retained funds. The law is clear that the retainage is to insure
completion of the building and not to make a carte blanche satisfaction
of every claim arising during performance of the contract by the now
defaulting subcontractor. 25
That amount of the retained percentage which remains after completion of
the sheet metal work belongs to the subcontractor. 26
While the owner may not collusively pay that money to the subcontractor
in derogation of the rights of subcontractor's creditors, 27
the property right nevertheless vests in the subcontractor. Any other
result would work a nullification of the hierarchy of priorities
developed by federal statutory and decisional law. If "completion
of the contract" amounted to satisfaction of every claim on open
account against the subcontractor, these claims would take
"priority" over a federal tax lien since these claims would be
paid by the surety out of the retained percentages, even though the
federal tax lien was perfected, choate, and prior in time. The principle
of subrogation can work no such magic.
After
completing the work, the balance of retained percentages, if any, 28
being the property of Yerby, is subject to the claims of his general
creditors, private lienors, and the federal tax lien, according to their
preference under federal law. The only private claims presently in issue
are: (1) surety's claim as equitable assignee of payments due and to
become due the subcontractor; and (2) surety's claim as subrogee to the
claims, supported by liens, of the materialmen and laborers which have
been satisfied by the surety.
The equitable
assignments are, in all material respects, identical to the assignments
involved in U. S. v. Ball Construction Co., supra. In that case
the Supreme Court reversed the lower court which had granted preference
to an assignment of retained percentages to a surety over a federal tax
lien, holding that the assignments were inchoate and unperfected.
Whatever may be the procedure for perfecting assignments, no action
other than formal assignments occurred here and the surety's claim based
on the assignments must fail here as it did in Ball.
The liens to
which the surety claims subrogation are in reality statutory claims
granted under
Louisiana
law to materialmen and laborers against retained percentages withheld by
an owner which is a state agency. 29
Clearly, the nature of these statutory claims as liens or their priority
are irrelevant here. The statute, by its terms, does not apply to the
contractor for a governmental authority who hold retained percentages
against a defaulting subcontractor. Thus, as to the retained percentages
held by Airtrol, the claims of materialmen and laborers have the status
of general creditors unsupported by liens. These claims lack specificity
as to any particular fund and are in no wise perfected. Thus the federal
tax lien is prior under the Code provisions 30
and by operation of law. 31
Hence the balance of the retained percentages must be paid to the
United States
.
Judgment
accordingly.
1
La. R. S. 9:4801 provides for liens by materialmen and laborers on
private buildings for unpaid claims on completion of the work. La. R. S.
38:2242 provides for sworn statements of amounts due on contracts to
build public buildings which may be filed by materialmen and laborers
and which require the governmental authority to hold retained
percentages from the contractor until materialmen and laborers have been
satisfied.
2
See the thorough history of this phase of lien priority law in Wolverine
Insurance Company v. Phillips, N. D. Iowa [58-2 USTC ¶9755], 165 F.
Supp. 335.
3
United States v. Bess [58-2 USTC ¶9595], 357
U. S.
51: U. S. v. White Bear Brewing Co. [56-1 USTC ¶9440], 350
U. S.
1010.
4
United States v. Acri [55-1 USTC ¶9138], 348 U. S. 211; U. S.
v. Security Trust & Savings Bank [50-2 USTC ¶9492], 340 U. S.
47; see also Great American Indemnity Co. v. United States, W. D.
La. [54-2 USTC ¶9469], 120 F. Supp. 445, 451.
5
Aquilino v. United States [60-2 USTC ¶9538], 363
U. S.
509; U. S. v. Durham Lumber Co. [60-2 USTC ¶9539], 363
U. S.
522; Fidelity & Deposit Co. v. New York City Housing Auth., 2
Cir. [57-1 USTC ¶9410], 241 F. 2d 142.
6
Aquilino v.
United States
, supra; U. S. v. Durham Lumber Co., supra.
7
Aquilino v.
United States
, supra.
8
26 U. S. C. §6321.
9
U. S. v. Security Trust & Savings Bank, supra.
10
U. S. v. Ball Construction Co. [58-1 USTC ¶9327], 355
U. S.
587.
11
United States
v.
New Britain
[54-1 USTC ¶9191], 347
U. S.
81; see 26
U. S.
C. §6323.
12
United States
v. Acri, supra.
13
U. S. v. Ball Construction Co., supra.
14
U. S. v. Durham Lumber Co., supra.
15
"The threshhold question in this case, as in all cases where the
Federal Government asserts its tax lien, is whether and to what extent
the taxpayer had 'property' or 'rights to property' to which the tax
lien could attach. In answering that question, both federal and state
courts must look to state law * * *." Aquilino v. United States,
supra, 512-513.
16
"However, once the tax lien has attached to the taxpayer's
state-created interests, we enter the province of federal law, which we
have consistently held determines the priority of competing liens
asserted against the taxpayer's 'property' or 'rights to
property.'" Aquilino v. United States, supra, 513-514. The
combined effect of Ball Construction,
Durham
Lumber, Aquilino, and Commercial Standard Insurance Co. v.
Campbell, 5 Cir. [58-1 USTC ¶9477], 254 F. 2d 432, is to make the
question of whether the right involved is a claim on property or
property itself of controlling importance.
17
Hale v. Wills, 3
La.
Ann. 504.
18
Hale v. Wills, supra, 506.
19
Hanson v. Liberty Const. Co., 172
La.
298, 134 So. 98, 99.
20
Natchitoches
Sweet Potato Co. v. Perfection Curing Co., 153
La.
916, 96 So. 808, 811.
21
Fidelity
Homestead
Ass'n v. Kennedy & Anderson, 158
La.
1059, 105 So. 64, 69.
22
In re Liquidation of Canal Bank & Trust Co., 181
La.
856, 160 So. 609; In re Hagin,
E. D. La.
, 21 F. 2d 434, affirmed sub nom. Phoenix Bldg. & Homestead Ass'n
v. E. A. Carrere's Sons, 5 Cir., 33 F. 2d 563, certiorari denied 281
U. S.
726.
23
"If the
United States
had been compelled to complete the work, its right to forfeit the ten
per cent [retained percentages] and apply the accumulations in reduction
of the damage sustained remained. The right of Hitchcock to subrogation,
therefore, would clearly entitle him when, as surety, he fulfilled the
obligation of Sundberg & Company, to the government, to be
substituted to the rights which the
United States
might have asserted against the fund. It would hardly be claimed that if
the sureties had failed to avail themselves of the privilege of
completing the work, they would not be entitled to a credit of the ten
per cent reserved in reduction of the excess of the cost to the
government in completing the work beyond the sum actually paid to the
contractor, irrespective of the source from which the contractor had
obtained the material and labor which went into the building." Prairie
State Bank v.
United States
, supra, 232-233.
24
"In these retained percentages, the contractor could give no one a
right superior to that of the owner and the surety. This principle was
established in Prairie State Bank of Chicago v. United States,
164
U. S.
227, 17 S. Ct. 142, 41 L. Ed. 412." General Casualty Co. v.
Second Nat. Bank of
Houston
, supra, 680.
25
Hale v. Wills, supra; La. R. S. 9:4804. Compare General
Casualty Co. v. Second Nat. Bank of
Houston
, supra, 680, wherein the Fifth Circuit distinguished between
progress payments (money actually earned but not paid) and retained
percentages (money withheld to insure completion of the job). The
assignee of the progress payments prior to default had a right to those
funds since they actually belonged to the contractor. The surety had a
right to demand that the retained percentages be used to complete the
building, as in fact they were, but the surety could claim no right to
the funds advanced to satisfy claims arising before default. While only
retained percentages were involved in the present case, the same
principle obtains that the surety can claim property rights in only so
much of the withheld funds as are needed to complete the building.
26
"Whatever was necessarily and reasonably expended for that purpose
must be deducted from the stipulated instalment, and the balance only
belongs to Wills, or his creditors." Hale v. Wills, supra,
506.
27
La.
C. C., art. 2772.
28
It is not entirely clear from the record which expenditures by the
surety after default were for settlement of claims arising before
Yerby's default and which were for labor and materials needed subsequent
to default to complete the sheet metal work. Only the items of
expenditure concerning materialmen are uncertain. The record illustrates
the pay periods for which the expenditures were made. Surety may submit
evidence of its disbursements needed for completion of the sheet metal
work. It is assumed this may be done by affidavit and document.
29
See Note 1.
30
26 U. S. C. §6321.
31
United States
v.
New Britain
, supra.
[55-1 USTC
¶9179]Phoenix Indemnity Company, a corporation, Appellant v. Hugh H.
Earle, Collector of Internal Revenue, and Ross H. Coppock, Trustee in
Bankruptcy of the Estate of Alan A. Siewert, Bankrupt, Appellee
(CA-9),
In the United States Court of Appeals for the Ninth Circuit, No. 13,755,
218 F2d 645, January 14, 1955
Appeal from the United States District Court for the District of Oregon.
[1939 Code Sec. 3672(a)--similar to 1954 Code Sec. 6323(a)]
Lien for taxes: Priority over claims of surety.--A contractor
contracted to do certain construction work for a government agency.
Appellant furnished a performance bond and a payment bond, in
consideration of which the contractor made a conditional assignment to
appellant of the percentages retained and all other sums due under the
contract. Before the completion of the work the Government filed tax
liens against the contractor. Upon the contractor's being adjudicated a
bankrupt, the Collector filed in the bankruptcy proceeding a proof of
claim containing the items included in the tax liens. The government
agency delivered to the trustee in bankruptcy the balance due to the
contractor on his contract. Appellant then filed with the Referee a
claim for the amount it had paid to the laborers and materialmen. The
Referee held that the sum received from the government agency should be
paid to the Director of Internal Revenue, which holding was approved by
the lower court. The lower court in turn was affirmed by the Ninth
Circuit on the ground that the Government was the holder of a valid,
perfected lien and as such a claimant had a position in bankruptcy
superior to priority claimants whose claims were unsupported by
perfected liens.
George A.
Rhoten, Rhoten, Rhoten & Speerstra,
Salem
,
Ore.
, for appellant. H. Brian Holland, Assistant Attorney General, Ellis N.
Slack, A. F. Prescott, John J. Kelly, Jr., Special Assistants to
Attorney General, Elmer Kelsey, Attorney, Department of Justice,
Washington, D. C., C. E. Luckey, United States Attorney, Maurice V.
Engelgau, Assistant United States Attorney (Bryan Goodenough, Salem,
Ore.), Portland, Ore., for appellee.
Before HEALY
and BONE, Circuit Judges and DRIVER, District Judge.
BONE, Circuit
Judge:
Alan Siewert,
a self-employed contractor, was adjudicated a bankrupt by the lower
court on
July 7, 1951
, and on the same day the proceeding was referred to a referee in
bankruptcy. On
August 4, 1951
, the Collector of Internal Revenue for the District of Oregon filed a
claim of the
United States
asserting a tax against the bankrupt and his assets in the hands of the
trustee with the Referee in Bankruptcy, this claim being for $12,770.28.
Later, two supplemental claims for taxes due were filed with the
Referee, one on
January 17, 1952
and the other on
June 21, 1952
. These two subsequent claims totaled $684.20.
Phoenix
filed petitions with the Referee on
April 18, 1952
, and on
August 4, 1952
, asserting claims against the assets in the hands of the Referee. The
allowance of all of these claims was opposed by the
United States
.
Upon hearing
and under date of November 22, 1952, the Referee entered his findings,
opinion and order holding that the sum of $11,838.61 received from the
Bonneville Power Administration, herein Bonneville, came into the hands
of the trustee impressed with certain tax liens (later noted) of the
United States, and that this sum (less costs and expenses of
admin
istration as determined by the court) should be paid to the Director of
Internal Revenue.
The order of
the Referee was later reviewed by the lower court on petition therefor
by appellant
Phoenix
, and the Referee's order was, without opinion, affirmed by the court
for the reason set forth in the Referee's findings, opinion and order.
This appeal followed. As we later note, the basic question here is
whether, under the facts 1
and the law, the Government's tax liens asserted against the funds in
the hands of the trustee in bankruptcy are superior to the claim of
appellant Phoenix.
The
Facts
Since the
basic facts are of controlling significance, the chronology of events
becomes important. The order of the Referee was based on the records
before him which established to his satisfaction facts set forth in his
findings, opinion and order which we summarize below. We find no reason
in the record to disagree with the Referee's appraisal of the facts.
Siewert
entered into a contract with Bonneville, the Government agency here
involved, to construct an entrance road and parking area at a Bonneville
substation in
Oregon
. At the same time
Phoenix
executed and delivered a performance bond and a payment bond in favor of
the
United States
as required of contractors by federal law in situations of the character
before us. In Siewert's application to Phoenix for these bonds, he
agreed to indemnify this surety against all loss sustained by reason of
the execution of the bonds, and assigned to Phoenix, as collateral, to
secure the obligations contained in the application and any other
indebtedness or liability of his to the surety, 2
such assignment to become effective as of the date of the contract
bonds, but only in the event of (1) breach of the contract or of the
bonds; or (2) any breach of the agreements contained in his application;
or (3) of a default in discharging other indebtedness or liabilities
when due; or (4) of any assignment for the benefit of creditors or of
the appointment of a receiver or trustee for Siewert, any and all
percentages retained (by Bonneville) on account of said contract, and
any and all sums that may be due under said contract at the time of
abandonment (of the contract work), forfeiture or breach, or that
thereafter may become due.
In the spring
of 1951, Siewert experienced some financial difficulties and for a time
funds paid by Bonneville on the Siewert contract were deposited with a
bank in a special account from which disbursements were made (by Siewert
and Phoenix) only for labor and material employed in performance of the
Bonnevile contract. The Referee found that Siewert did not default in
performing his contract; that his work was completed on
June 19, 1951
and it was forthwith inspected and accepted by Bonneville as
satisfactory.
Subsequently,
Phoenix
, under its payment bond paid claims totalling $15,210.60 for labor and
material furnished to Siewert in the performance of his contract.
[Tax
Liens]
Prior to
Siewert's bankruptcy and prior to any payments made by
Phoenix
in compliance with the requirements of its payment bond, three separate
notices of tax liens were filed by the
United States
against Siewert in Marion County, Oregon, (his place of residence and of
doing business). These lien notices were filed on
June 29, 1951
,
June 15, 1951
, and
May 24, 1951
, and the three lien claims totalled $12,486.00. On
July 29, 1951
, the Collector of Internal Revenue filed in the bankruptcy proceeding a
proof of claim containing the items included in the above (three) liens;
the total of the Collector's claim, with penalties and interest to
August 1, 1951
, amounted to $12,770.28.
Later, and on
January 17, 1952, and Collector filed a supplemental proof of claim
covering withholding and employment taxes for the June, 1951 quarter in
the sum of $323.15, and the brief of the Government in the Referee's
court indicated that a notice of lien for this amount had been filed in
said Marion County, Oregon on January 3, 1952.
The total
amount paid to Siewert's creditors by
Phoenix
under the payment bond amounted to $15,210.60.
On or about
January 18, 1952 Bonneville delivered to the trustee a check for
$11,838.61 this amount being the balance due to Siewert on his contract,
including the amount of retained percentages of progress payments made
prior to completion date of the contract.
The
Claims of the Parties
The claims of
the parties, asserted here and before the Referee and lower court, are
brief and appear to concern only questions of law arising out of the
agreed facts.
Appellee
contends that the above noted tax liens of the Government are superior
to the claim of appellant.
Appellant
poses the problem here in two questions: First, does
Phoenix
have subrogation rights under the circumstances surrounding its claim;
and second, did the lower court err in sustaining the above noted
contention of the Government.
In the posture
of the case, as above outlined, the question here for decision boils
down to appellant's challenge to the validity of the Referee's
conclusion and holding that the sum of $11,836.61 received by the
trustee from Bonneville should be paid over to the Director of Internal
Revenue by reason of the Government's prior lien for the aforesaid taxes
due it. Or, in other words, is this lien for unpaid taxes superior to
and entitled to priority over the claim of
Phoenix
?
Appellee
contends that the decisions of the Supreme Court in Goggin v.
California Labor Division, 336 U. S. 118 [49-1 USTC ¶9142]; United
States v. Munsey Trust Co., 332 U. S. 234; and our decision in In
Re Knox-Powell-Stockton Co., 100 Fed. (2d) 979 [39-1 USTC ¶9277],
require an affirmative answer to the question just above noted.
Appellant
makes the following assignment of errors:
"First:
That the referee and the District Court erred in determining that the
doctrine of subrogation does not apply in favor of Phoenix Indemnity
Company under the circumstances surrounding its claim; and
"Second:
The referee and the District Court erred in holding that the tax claim
of the
United States
is superior to the right of Phoenix Indemnity Company."
[Subrogation]
In its brief
the appellant based its right of subrogation upon its payments to labor
and materialmen. In oral argument appellant expressly abandoned any
claim of subrogation based upon materialmen's claims 3
and appears to have no further claim of subrogation other than a passing
remark in oral argument, that although it abandoned its right to be
subrogated to materialmen it did not give up any right to be subrogated
to the rights of the Government. No prior nor further reference was made
to such a right of subrogation to the Government's position, nor was any
explanation or authority offered for such a claim during oral argument
or in the brief.
Such an
assertion would seem to have been laid to rest in United States v.
Munsey Trust Co., supra, from which the Referee quoted extensively
in his "Discussion of Law" in "Referee's Findings,
Opinion and Order" which were adopted in their entirety by the
district court. After Justice Jackson established in the Munsey
case that the
United States
was a secured creditor he said at page 241:
"But
the infirmity in respondent's case goes deeper. If the
United States
were obligated to pay laborers and materialmen unpaid by a contractor,
the surety who discharged that obligation could claim subrogation. But
nothing is more clear than that laborers and materialmen do not have
enforceable rights against the
United States
for their compensation. [citations] They cannot acquire a lien on public
buildings, [citations] and as a substitute for that more customary
protection, the various statutes were passed which require that a surety
guarantee their payment. Of these, the last and the one now in force is
the Miller Act under which the bonds here were drawn."
As to
appellant's claim of assignment by way of the bond application and its
subrogation to the claims of labor and materialmen the Referee said in
his "Discussion of Law":
"The
assignment was made as collateral to secure the indemnity agreements of
Siewert [bankrupt]. No attempt was made to comply with requirements of
Title 31 U. S. C. A. Section 203 relating to assignments of claims
against the
United States
. It was, therefore, void as to the
United States
* * *"
"It
is conceded that
Phoenix
is subrogated to the rights of the creditors whose claims it paid. This
right is fortified by the assignment of these claims by the creditors to
the surety. But these creditors had no lien or other enforceable right
against Bonneville or the funds owing to Siewert. Hence, their claims
against the estate of the bankrupt are general and unsecured. In this
case no funds will be available for general creditors after the payment
of expenses of
admin
istration, tax liens and other priority tax claims."
In oral
argument appellant based its claim upon an asserted "right to an
equitable lien." There is no reference to an "equitable
lien" in the record before us from the district court (which
includes the claims and memorandums presented to the Referee); there is
no assignment of error by appellant dealing with an "equitable
lien," and an "equitable lien" is not mentioned in the
briefs.
It may well be
that no case remains for our consideration. Rule 18(2)(d) of the Rules
of this Court says in part: "in all cases a specification of errors
relied upon which shall be numbered and shall set out separately and
particularly each error intended to be urged * * * In all cases, when
findings are specified as error, the specification shall state as
particularly as may be wherein the findings of fact and conclusions of
law are alleged to be erroneous."
[Bankruptcy]
This is an
appeal from an affirmation of the lower court of the findings and
conclusions made by the Referee in Bankruptcy. But, appellant cites no
cases and no authority dealing with bankruptcy other than merely
providing us with the citation of one 1917 case, Derby v. United
States Fidelity & Guarantee Co., 87 Or. 34, 169
Pac.
500 which was concerned with a dispute between a bank and an insurance
company. Appellant provided this Court with only one sentence which was
in any way concerned with the statutory provisions of the Bankruptcy
Act:
"The
bankruptcy act provides that taxes due the
United States
are entitled to the priority there expressed. U. S. C. A. Title 11,
section 104."
This
sentence appears to support appellee and not appellant.
Appellant's
position in this bankruptcy proceeding would appear to be fixed and
limited by Section 57(i) of the Act (11 U. S. C. A. 93(i)) which permits
a surety to be subrogated to the rights of creditors to the extent that
he pays the creditors. This section and its effect are the subject of a
full discussion in Collier on Bankruptcy, Vol. 3 (14th ed.) commencing
at page 284 and continuing to page 296. Beginning on page 287 it is
stated:
"The
surety normally has against the principal a claim, express or implied,
absolute or contingent, to be indemnified or reimbursed. Without §57i
there could be no doubt but that such a claim is provable by the surety
in the same manner any other claim provable under §63a may be
presented, namely as the surety's own claim against the bankrupt
principal debtor. Section 57i flatly denies this right. It
confines the secondary debtor to a proof of the creditor's claim,
in the creditor's name. 'A creditor may indeed prove against both
principal and surety, but that is because he has two separate claims,
really he has security upon a single claim. But there can never be more
than one claim against the principal.' It is this one claim,
namely the creditor's claim, that the surety may prove prior to or after
subrogation, and not his own claim upon an agreement, express or
implied, of indemnity."
Under the
Bankruptcy Act it appears that a surety is limited to a right of
subrogation to the position of the creditors of the debtor to the extent
that the surety pays the creditors. The best position of any of the
creditors paid by Phoenix Indemnity Company to which it might be
subrogated (although we understand this claim to be abandoned) was a
right to priority by §64 of the Act. The government is the holder of
valid, perfected tax liens. Such a lien claimant has a position in
bankruptcy superior to priority claimants whose claims are unsupported
by perfected liens.
Section 57(i)
appears to clearly support the conclusions of the Referee which were
sustained by the affirming order of the lower court.
Judgment is
affirmed.
1
In argument here, we were advised that there is no dispute as to the
facts. The Referee's findings, opinion and order clearly and succinctly
state the controlling facts on which his order was based and we resort
to it for our summary of the facts.
2
This assignment was sweeping in character. It covered and included,
inter alia, all rights of the assignor in all subcontracts and in the
main contract, materials purchased for or chargeable to the contract,
causes of action, claims and demands accrued or accruing in favor of the
assignor arising out of the contract, and the assignor's rights and
interest in all of the machinery, tools, equipment, plant and materials
about the site of the work.
3
From the rest of the discussion we gathered that appellant also intended
to abandon its claim of subrogation to laborers' claims. But in any
event, and as we later note, the rule seems to be that perfected
"liens" take preference over a "priority" claim
unsupported by a lien.
[75-2 USTC
¶9631]The Housing Authority of the City of Mexico, Missouri, Plaintiff
v. General Insurance Company of America and The United States of
America, Defendants
U.
S. District Court, East. Dist.
Mo.
, East. Div., No. 73 C 419(3), 392 FSupp 65,
5/7/74
[Code Sec. 6323]
Lien for taxes: Priority: Surety's interest.--General, surety of
a bankrupt contractor, was entitled to the interpleaded funds. The court
concluded that General has superior rights over the government's tax
liens. General had acquired an equitable lien against the unpaid funds
which related back to the date of the contract while the tax liens
concerned periods subsequent to that date.
Edward D.
Hodge, Edwards, Seigfreid, Runge & Hodge, Inc., 123 E.
Jackson
,
Mexico
,
Mo.
, for plaintiff. Donald J. Stohr, United States Attorney, St. Louis,
Mo., Francis L. Kenney, Jr., Kenney, Leritz & Reinert, 843 Boatmen's
Bank Bldg., 314 N. Broadway, St. Louis, Mo., for defendants.
Memorandum
and Order
WANGELIN,
District Judge:
This matter is
before the Court upon the cross motions of the defendants for summary
judgment pursuant to Rule 56, Federal Rules of Civil Procedure.
This is an
interpleader action which was removed from the Circuit Court of Audrian
County, Missouri. The interpleaded fund in the amount of $8,222.95 is
the balance resulting from a Contract between the plaintiff Housing
Authority of the City of Mexico, Missouri, (herein Authority) and the
Contractor, Plez Lewis & Son, Inc. (herein Plez). On August 6, 1962,
the plaintiff entered into a contract agreement with Plez for the
construction of seventy-four dwelling units, management and community
buildings, and site development in connection with housing project
MO-10-1, Phase II, sites I and II located in
Mexico
,
Missouri
. Said construction project was bonded by the defendant General
Insurance Co. (herein General) by its Performance and Payment Bond No.
477257 in the penal sum of $851,342.00. Said bond was executed on August
6, 1962, and created the relationship of General as surety and Plez as
principal. 1
Prior to the completion of the aforesaid project, Plez defaulted and was
declared a bankrupt. General, pursuant to its obligation as surety, made
payments in 1965, 1966 and 1967 to various claimants who had performed
labor or supplied material or services under the housing contract in the
amount of $8,643.20. The plaintiff prior to the default of Plez had
retained the sum of $8,222.95 of the contract balance which was to have
been paid upon satisfactory completion of the construction under the
contract agreement. Such sum is the interplead amount. On May 5th, 1965,
a notice of levy was served upon the plaintiff by a delegate of the
Secretary of the Treasury demanding payment of all sums of money or
other obligation owing to Plez. Said levy was made pursuant to tax
assessments charged against the taxpayer Plez, the first such assessment
being made on January 29, 1965, for withholding and FICA taxes and
interest in the amount of $15,351.14 as taxes and $456.85 as interest.
The plaintiff has paid into the registry of this Court the sum of
$8,222.95 and claims no interest in the amount but seeks a determination
as to the party lawfully entitled to it.
General
contends that with the payments to the various claimants pursuant to its
obligation as surety it became subrogated to the rights to the monies
due the defaulting contractor in the hands of the Authority. General
further contends that it has an equitable lien on said monies which
relates back to the date of the suretyship contract (August 6, 1962) and
such claim is superior to a claim of the
United States
for unpaid taxes for periods subsequent to the aforesaid contract. In
contravention, the Government argues that the tax lien takes priority
and is attached to all property and rights to property of the taxpayer,
Plez, including the amounts retained by Authority.
The issue as
the Court views it is whether the rights of General gained through
subrogation based on a contract of suretyship dated August 6, 1962, is
superior to the tax lien of the United States which arose prior to the
payments by the surety? This Court holds that the rights of General have
priority over the claims of the
United States
. For support of this decision the language of Glenn v. American
Surety Co. [47-1 USTC ¶9220], 160 F. 2d 977 (6th Cir., 1947) as
cited in Home Indemnity Co. v. United States, 313 F. Supp. 212
(W. D. Mo., 1970) at 215-6 is appropriate:
. . . a surety
who makes good under his contract of suretyship upon default of the
principal contractor, acquires an equitable lien against the unpaid
balance in the hands of the person in whose favor the bond runs, and
that such equitable lien upon payment by the surety relates back to the
date of the contract and is superior to a claim of the United States for
unpaid taxes for periods subsequent to the date of the contract of
suretyship although prior to the date of payment by the surety. 160 F.
2d at 982.
In
accord see United States Fidelity & Guaranty Co. v. United States
[53-1 USTC ¶9249], 201 F. 2d 118 (10th Cir., 1952): Farmer's Bank v.
Hayes, 58 F. 2d 34 (6th Cir., 1932) 2;
and New York Casualty Co. v. Zwerner [45-1 USTC ¶9140], 58 F.
Supp. 473 (N. D. Ill., 1944).
Accordingly,
IT IS HEREBY
ORDERED that the motion of the defendant General Insurance Company of
America
for summary judgment be and is GRANTED and that it shall take the fund
minus attorney's fees and costs;
IT IS FURTHER
ORDERED that the motion of the defendant
United States
for summary judgment be and is DENIED; and
IT IS FURTHER
ORDERED that the plaintiff be and is awarded reasonable attorney's fees
and costs.
1
The record indicates that on
February 17, 1959
, Plez executed an indemnity agreement in favor of the insurance company
and assigned all rights of Plez in the contract between Plez and the
Authority. However, such agreement is not essential to the determination
of this action.
2
Though the above cases deal with payment under the Miller Act, 40
U. S.
C. §270(a), et sec., for purposes here no distinction between
subrogation under said Act and herein is relevant.
[44-1 USTC
¶9133]Maryland Casualty Company, a Corporation v. The
United States
In
the Court of Claims of the United States, No. 45659, 100 CtCls 513, 53
FSupp 436, Decided January 3, 1944
Set-off for unpaid taxes on government contract: Surety's right of
subrogation on "payment" bond.--Surety on contractor's
bond, given to guarantee payments to materialmen and laborers on a
United States construction contract, seeks to recover balance of
contract price due to such contractor after he had defaulted in such
payments, after the government had applied such balance to past due
income and other taxes owing by the contractor. The surety bases its
right to recover from the
United States
for amounts paid out under the bond on its claim of subrogation to the
contract price owing to the contractor. The Court of Claims denies the
government's priority for taxes under Sec. 3466 of the Revised Statutes
as inapplicable except where debtor's insolvency is evidenced by
bankruptcy, receivership or assignment of creditors. The Court allowed
recovery to the contractor on the theory that it was not intended by the
contracting parties that the contract price would be "paid,"
not in money but by a bookkeeping process of crediting these sums
against taxes to the prejudice of the surety.
John J. Wilson
for the plaintiff. Whiteford, Hart & Carmody, and H. Ellsworth
Miller were on the briefs. J. H. Sheppard, with whom was Assistant
Attorney General Samuel O. Clark, Jr., for the defendants.
Rob
ert N. Anderson and Fred K. Dyar were on the brief.
Conclusion
of Law
Upon the * * *
special findings of fact, which are made a part of the judgment herein,
the court concludes, as a matter of law, that the plaintiff is entitled
to recover $1,987.22.
It is
therefore ordered and adjudged that the plaintiff recover of and from
the
United States
the sum of one thousand nine hundred eighty-seven dollars and twenty-two
cents ($1,987.22).
Opinion
MADDEN, Judge,
delivered the opinion of the court:
[The
Facts]
The plaintiff
seeks to recover from the
United States
$1,987.22 which the plaintiff paid to materialmen and laborers whom the
Columbia Foundation Company, Inc., failed to pay.
Columbia
had, about
February 3, 1940
, made a contract with the
United States
for the installation of a condensing water supply connection at the
National Gallery of Art. It was required by law to furnish two separate
bonds, one guaranteeing its performance of the contract, and the other
guaranteeing its payment of materialmen and laborers from whom it might
obtain supplies or services in the performance of the contract. 1
The plaintiff furnished the payment bond.
Columbia
became financially unable to pay its bills and, when it completed the
performance of the contract it left unpaid the materialmen and laborers
who were later paid by the plaintiff. On January 7, 1941, which was
after completion of performance but before the plaintiff, as surety, had
paid Columbia's unpaid bills, the Comptroller General of the United
States determined that there was a balance of $4,253.63 of the contract
price, which the Government had not paid Columbia, but that Columbia was
indebted to the United States in a larger amount than that, for income
taxes and federal insurance contribution and unemployment taxes. The
Comptroller General applied the balance against the taxes, and gave
Columbia
a receipt for the payment of that amount on its tax bill. When he did
this, the Comptroller General did not know that
Columbia
had failed to pay its bills, or was unable to do so.
On
January 22, 1941
, the plaintiff, upon becoming aware of what the Comptroller General had
done, protested against the set-off and demanded payment instead of the
set-off.
Columbia
at the same time made a similar protest and demand. The plaintiff then
paid
Columbia
's unpaid debts to materialmen and laborers in the amount of $1,984.75,
and social security taxes on the wages paid by it, in the amount of
$2.47, making the total amount here sued for $1,987.22. It made no
attempt to obtain reimbursement from
Columbia
because it learned that
Columbia
had no assets. It sought to have the Comptroller General rescind the
set-off, and pay it $1,987.22 out of the $4,253.63 which that official
had determined was owing
Columbia
on its contract, but was used up as a credit on
Columbia
's unpaid taxes. That official, however, adhered to his former decision
and denied the request.
Our question
is whether the Government has the right to settle the unpaid balance
which it owes a contractor for the performance of a certain contract, by
setting off that balance against a debt which the contractor owes the
Government upon some unrelated account, when there is a surety who has
been obliged under its bond to pay debts of the contractor for materials
and labor used by the contractor in the performance of its contract. In
this case the contractor's debt to the Government was for taxes, but the
Government does not claim that it had properly perfected a tax lien, or
that the tax debt was different, in any respect material here, from any
other debt which the contractor might have owed the Government, as, for
example, for supplies sold to him by the Government.
[Priority
Denied]
One basis for
the Government's asserted defense is that, because of Section 3466 of
the Revised Statutes, 31 U. S. C. Sec. 191, the United States, as a
creditor, had priority over other creditors of Columbia, and therefore
its paying itself by set-off gave it no more than it would have been
entitled to in any event. That section is as follows:
Whenever
any person indebted to the United States is insolvent, or whenever the
estate of any deceased debtor, in the hands of the executors or
admin
istrators, is insufficient to pay all the debts due from the deceased,
the debts due to the United States shall be first satisfied; and the
priority established shall extend as well to cases in which a debtor,
not having sufficient property to pay all his debts, makes a voluntary
assignment thereof, or in which the estate and effects of an absconding,
concealed, or absent debtor are attached by process of law, as to cases
in which an act of bankruptcy is committed.
The
plaintiff urges that this statute is not applicable except where, in the
case of a living debtor, his insolvency is a formal one evidenced by a
bankruptcy, receivership, or assignment for the benefit of creditors.
We agree with
the plaintiff as to the construction of R. S. 3466. A provision in
similar language has been in the statutes since 1797 and has always been
construed as plaintiff would have us construe it. See
United States
v. State of
Oklahoma
, 261
U. S.
253. We conclude, therefore, that the Government, as such, had no
statutory preference which would give its claim priority over the
plaintiff's claim.
[Claim
of Subrogation]
We now reach
the difficult legal question in the case. The plaintiff claims that as a
surety which has paid the debt of its principal, it is entitled to be
subrogated to the right which its principal had, under the contract,
including the right to collect so much of the unpaid balance due its
principal from the other contracting party as is necessary to make it
whole for payments made by it under its bond. The Government, in
response, says that there was nothing for the plaintiff to be subrogated
to, because
Columbia
, its principal, had no rights against the
United States
, since it owed taxes in a larger amount. The Government cites Globe
Indemnity Co. v. United States, 84 C. Cls. 587. In that case the
surety sued for the unpaid balance due the contractor from the
Government, the surety having there, as here, paid labor and material
bills of the contractor. But the contractor's claim against the
Government had been forfeited, under the statute, for attempted fraud in
the prosecution of it. The court held that the surety could not recover,
and said. "The party for whose benefit the doctrine of subrogation
is exercised can acquire no greater rights than those of the party for
whom he is substituted."
We think the Globe
case was rightly decided. There the principal's claim became literally
nonexistent as a result of the forfeiture under the statute, so of
course neither the surety nor anyone else could enforce it. But most
cases of subrogation, including the one now before us, involve only a
question of priority, i. e. whether the surety or some other creditor of
the principal has a better right to an admitted asset of the principal.
In Prairie State Bank v. United States, 164 U. S. 227, for
example, the question was whether the surety who had expended money to
complete the contract upon his principal's default, or the bank which
had loaned money to the principal to finance the contract, had the
better right to the balance due the principal from the United States,
when the contract was completed. In that case, if the bank had had an
assignment of the unpaid balance, good as against the principal, the
assignor, it and not the principal would have been entitled to collect
the money from the
United States
. But that would have proved nothing as to whether or not still another
person, the surety, had a still better right than the assignee to get
the money. So the surety's right by subrogation may give him, as it did
in the Prairie State Bank case, supra, a right to money
which, if there had been no surety, the principal would not have been
entitled to because he had assigned his right, or had subjected it to a
set-off or other valid defense not involving forfeiture of the claim.
A surety is
entitled, by subrogation, to priority in valuables pledged by the
principal debtor to the other contracting party as additional security
for the performance of the contract. Arant on Suretyship, pp. 354, 355.
In the case of the "performance" bond required by the
Government of contractors, the money retained by the Government until
performance is completed is retained for the purpose of securing
performance. By proper analogy the contractor's right to that money,
upon completion, should belong to the surety, so far as it is necessary
to make him whole, and his claim to it should have priority over the
claims of other creditors of the contractor, including claims of the
Government which are unrelated to the contract.
United States
Fidelity and Guaranty Co. v.
United States
92 C. Cls. 144.
The bond
involved in the instant case was not a "performance" bond, but
a "payment" bond. It is not clear that moneys were withheld
from the contractor in order to give the Government additional security
that materialmen and laborers would be paid. So far as appears, the
balance of the contract price would have been paid to
Columbia
, if it had not been credited on
Columbia
's taxes, without any investigation as to whether
Columbia
had paid its materialmen and laborers. If so, that would indicate that
the Government, which would have no more than a moral obligation to see
these creditors paid, relies entirely on the payment bond with regard to
such debts of the contractor. The analogy of subrogation to additional
security may, therefore, not be properly applicable to the type of bond
here involved.
[Contract
Construed]
The answer to
our question should, we think, be looked for in the contract itself and
its necessary implications. What did the parties mean? What risks did
they intend the surety to undertake? The risks undertaken by a surety,
and for which it receives its compensation, if it is, as the plaintiff
is, a commercial surety, include the risk that the contractor, the
principal, may receive the payments from the other contracting party,
here the Government, and may spend the money in speculation or in
riotous living and fail to pay his materialmen and laborers. The surety
will then have to pay them. The surety also takes the risk that, by
reason of the contractor's bad management, or of a rise in the cost of
labor and materials, the payments made to the contractor will not be
sufficient to pay the materialmen and laborers. But we do not think that
it intends, or is expected by the Government or the other contracting
party to take the risk that any part, or perhaps the whole, of the
contract price which by the contract the Government promises to pay upon
performance, will be "paid," not in money but by a bookkeeping
process of crediting these sums against taxes or other debts of the
contractor not related to the contract, to the prejudice of the surety.
Suppose a
contractor defaults, at some stage, early or late, in performance. The
surety elects to omplete performance in order to reduce its liability.
It secures another contractor and enters into a contract with him for
completion of the work. The work is completed. Then the Government says
that the original contractor owed it more on other accounts than the
unpaid contract price, hence the surety will be paid nothing, though it
did some or most of the work covered by the original contract. If, in
the same situation, the surety had not elected to complete the work, and
the Government had finished the job itself, the surety would have been
obliged to pay only the difference between the actual cost of completion
and the part of the contract price which had not been paid the original
contractor before his default.
In the first
situation suggested above, the surety would have paid the original
contractor's taxes or other debts to the Government. In the second it
would not. We think that in no case is it intended that the surety
transaction should work out in such a way that the surety has paid the
contractor's taxes or unrelated debts to the Government.
The effect of
the contract and the bonds is that the contractor promises the
Government that it will build the structure, and will pay the
laborers and materialmen. The Government takes two separate bonds to
secure the fulfillment of these promises, since its interest in the
first is more physical and direct than in the second. But when the
surety pays the laborers and materialmen, it is performing the contract
as much as when it completes the building. We see no more reason why the
parties should intend that, either under the guise of building a
building, or of paying laborers and materialmen, both of which the
surety has promised will be done, it should in reality, and because of
the ease of bookkeeping, be paying the contractor's taxes or other
debts, which it has not promised will be done.
[Conclusion]
We construe
the bond and the transaction as a whole as implying a promise on the
part of the Government to the surety that it will not so settle the
accounts of the contractor as to leave the surety in the position of
paying the contractor's taxes. When the Comptroller General was made
aware that that was the effect of his accounting, he should have
rescinded the set-off. The fact that he had made the set-off without
knowledge of its effect upon the surety's interest had no final effect
upon the plaintiff's right. The credit given to
Columbia
on its taxes could have been cancelled, without any prejudicial change
in the Government's position. This should have been done when the
plaintiff's right became known.
The plaintiff
may recover $1,987.22.
It is so
ordered.
WHITAKER,
Judge; and
LITTLETON
, Judge, concur.
WHALEY, Chief
Justice, concurs in the result.
JONES, Judge,
took no part in the decision of this case.
1
Act of
August 24, 1935
, C. 642; 49 Stat. 793, 40 U. S. C. §270.
[61-1 USTC
¶9376]United States of America, for the use of The Home Indemnity
Company, a corporation, Assignee, Plaintiff v. American Employers'
Insurance Company, a corporation, and Oil Capital Construction Company,
a corporation, Defendants, and United States of America, Interpleaded
Defendant, and York Electric Construction Company, a corporation,
Additional Indispensable Party Defendant
U.
S. District Court, Dist. N. Dak., Northeast. Div., Civil No. 3618, 192
FSupp 873,
4/8/61
[1954 Code Sec. 6323]
Priority of liens: Unpaid payroll taxes: Surety: Defaulting
subcontractor.--A subcontractor notified its surety and the prime
contractor that it would not be able to perform the subcontract even
before commencing work under it. To minimize its losses, the surety
permitted the subcontractor to perform the contract, with the
subcontract price being assigned directly to it. The subcontractor's net
payroll expenses were paid directly by the surety, but no provision was
made for payment of withholding taxes. Because of adverse claims to an
amount still owing under the subcontract, the prime contractor paid the
remaining $12,000 into court. It was claimed by the surety for
completing the contract and by the Government for some $11,000 in
payroll taxes owing by the subcontractor. The surety was held to be
entitled to the fund, since its subrogation rights dated back to the
time its performance bond was executed. However, the Government was
entitled to judgment on its cross-claim against the surety for $2,300 in
withholding taxes which were incurred in completing the subcontract in
issue.
Harold D.
Shaft of Shaft, Benson & Shaft, Grand Forks, N. Dak., and John
Murphy of Tucker, Murphy, Wilson & Siddens, 831
Scarritt Building
,
Kansas
City,
Mo.
, for The Home Indemnity Company.
Rob
ert Vaaler of Day, Stokes, Vaaler & Gillig, Grand Forks, N. Dak.,
for American Employers' Insurance Company and Oil Capital Construction
Company.
Rob
ert L. Handros and John M. Burzio, Tax Division, Department of Justice,
Washington
25, D. C., for the
United States
.
Memorandum
and Order
DAVIES,
District Judge:
Oil Capital
Construction Company (hereinafter Oil Capital) was prime contractor
under a contract with the United States for certain construction work on
the Grand Forks, North Dakota, Air Force Base. American Employers'
Insurance Company (hereinafter American Employers') issued performance
and payment bonds thereon under provisions of the Miller Act, 40 U. S.
C. A., Sections 270(a), 270(b).
On
February 11, 1957
, Oil Capital made a subcontract with York Electric Construction Company
(hereinafter
York
) whereby
York
agreed to furnish certain materials and labor for construction of
utilities required under the prime contract. A performance bond was
executed and delivered on February 25, 1957, by The Home Indemnity
Company (hereinafter Home Indemnity) conditioned upon the faithful
performance of the subcontract by York. The performance bond among other
things provided:
"Whenever
Contractor (York) shall be, and declared by Owner (Oil Capital) to be in
default under the CONTRACT, the Owner having performed Owner's
obligations thereunder, the Surety may promptly remedy the default, or
shall promptly
"(1)
Complete the CONTRACT in accordance with its terms and conditions, or
"(2)
Obtain a bid or bids for submission to Owner for completing the CONTRACT
in accordance with its terms and conditions, and upon determination by
Owner and Surety of the lowest responsible bidder, arrange for a
contract between such bidder and Owner and make available as work
progresses (even though there should be a default or a succession of
defaults under the contract or contracts of completion arranged under
this paragraph) sufficient funds to pay the cost of completion less the
balance of the contract price, but not exceeding, including other costs
and damages for which the Surety may be liable hereunder, the amount set
forth in the first paragraph hereof. The term 'balance of the contract
price', as used in this paragraph, shall mean the total amount payable
by Owner to Contractor under the CONTRACT and any amendments thereto,
less the amount properly paid by Owner to Contractor."
Prior to
commencing work under the subcontract,
York
notified both Home Indemnity and Oil Capital that due to financial
difficulties it would not be able to perform the subcontract. Oil
Capital immediately called upon Home Indemnity as surety to make good
the default of its principal, York. Under terms of the performance bond
Home Indemnity was confronted with a choice either of completing or
reletting the subcontract. Oil Capital expressed a desire that
York
be allowed to undertake performance if at all possible.
York
was in default on several other contracts upon which Home Indemnity was
acting as surety, and therefore, Home Indemnity anticipated substantial
suretyship losses. Desirous of keeping its anticipated losses to a
minimum, Home Indemnity allowed
York
to proceed under certain conditions.
[Surety
Allowed Subcontractor to Perform]
York executed
an assignment of the subcontract price to Home Indemnity; a joint
control account was set up in which deposit was to be made of the
subcontract funds; and Oil Capital was authorized to pay certain of
York's suppliers directly. Other material suppliers were to be paid from
the joint control account after Home Indemnity's approval. Material
costs in excess of the deposits in the control account were to be paid
from funds advanced by Home Indemnity. Payroll expenses were supplied to
York
by Home Indemnity upon submission of payroll vouchers. Net payroll costs
only were advanced, no provision being made for the payment of
withholding taxes.
After making
this agreement on
April 12, 1957
,
York
was allowed to proceed with the work commencing the week of
April 25, 1957
, and so far as
York
was concerned, finishing the week of
September 25, 1957
. Certain odds and ends called the "punch list" remained, and
Home Indemnity employed Jayhawk Electric Construction Company (Jayhawk)
to complete the subcontract. This was done by
November 28, 1957
, but as a dispute arose over the amount due Jayhawk, they were not paid
by Home Indemnity until
April 7, 1958
.
A total of
$22,852.47 was deposited in the joint control account from payments made
by Oil Capital on the subcontract. Of this amount $19,791.38 was paid
out for material expenses, and the balance of $3,061.09 was withdrawn by
Home Indemnity for its own use. In addition to amounts paid out of the
joint control account, Home Indemnity made necessary labor and material
payments and thereby suffered a suretyship loss of $21,794.81.
The United
States Government made assessments for payroll withholding taxes against
York
on
May 31, 1957
,
November 15, 1957
, and
March 7, 1958
, respectively, filing notices of tax liens on January 3 and on
June 4, 1958
. Notice of levy and demand were served on Oil Capital for the unpaid
taxes.
[Balance
Due Paid into Court]
Upon
completion of the subcontract there remained due and owing an unpaid
portion of the subcontract price which Oil Capital refused to deliver.
Home Indemnity, Use Plaintiff here, as
York
's assignee, pursuant to Sections 270(a) and 270(b) of the Miller Act, supra,
brought this action against Oil Capital and its surety, American
Employers'. The Defendants answered jointly, admitting liability but
pleading the Federal tax liens as an affirmative defense. A motion to
interplead the United States was granted, whereupon the Government
answered, asserting the tax liens and crossclaiming against the Use
Plaintiff, Home Indemnity, for the sum of $2,345.25 plus interest for
payroll taxes not paid by York on the Grand Forks Air Force Base
project. The tax liens asserted include
York
's tax liabilities incurred on the
Grand Forks
job, but the Government contends that Home Indemnity is liable on its
bond for this sum independently of the tax liens.
The Government
moved to add
York
as an Indispensable Party Defendant which motion was granted.
York
did not appear or answer, and judgment for $11,175.71, the full amount
of the taxes plus interest, will be entered against
York
in favor of the
United States of America
.
On trial it
was stipulated that the total tax liability of
York
was $11,175.71 plus interest, and the sum left due and owing under the
subcontract was $12,000.00. Oil Capital and its surety, American
Employers', admitting liability, have paid into this court the
$12,000.00 now in dispute.
The Government
bases its claim to the fund here in issue upon 26
U. S.
C. A., Section 6321, which reads so far as is here relevant:
"If
any person liable to pay any tax neglects or refuses to pay the same
after demand, the amount * * * shall be a lien in favor of the
United States
upon all property and rights to property, whether real or personal,
belonging to such person."
The section
following provides that a lien for taxes "shall arise at the time
assessment is made."
Section 6321
creates no property rights but merely attaches consequences, Federally
defined, to rights created under state law, United States v. Bess
[58-2 USTC ¶9595], 357 U. S. 51, 78 S. Ct. 1054, 2 L. Ed. 2d 1135; and
the right to recover from the fund must be based upon the strength of a
claimant's title and not on the weakness of the title of another
claimant, United States v. Chapman [60-1 USTC ¶9667], 281 F. 2d
862.
The Government
contends that
York
completed the subcontract, merely obtaining financial aid from its
surety, Home Indemnity. To better understand the Government's argument,
the following is quoted from the Government's brief, P. 8, 9:
"Counsel
for Home Indemnity, in their brief, cite numerous cases to show that, if
a taxpayer-contractor defaults on performance of his contract, according
to applicable state law there is no sum due him under the contract, to
which deferal tax liens can attach. All of this is, in general, good and
settled law, with which the Government has no dispute. However, this law
has nothing whatever to do with the case at bar. Rights to the fund in
issue in the instant case do not arise under a contract governed by
state law. They arise under a bond issued pursuant to the Miller Act,
and rights under such a bond are governed by federal law, i. e.,
Sections 1 and 2 of the Act. Leibman v. United States for Use and
Benefit of Cal. Elec. Supply Co., 153 F. 2d 350 (C. A. 9th); Continental
Casualty Co. v. Schaefer, 173 F. 2d 5 (C. A. 9th), certiorari
denied, 337
U. S.
940, rehearing denied, 338
U. S.
841."
The Government
then argues that only
York
as supplier of labor or materials could recover from American Employers'
under the Miller Act.
[Subcontractor
Acted as Surety's Agent]
With this
contention this Court does not agree, but finds that, in effect,
York
was a mere agent of Home Indemnity and was the vehicle utilized by the
surety in completing the subcontract as required by the performance
bond. Central Surety and Insurance Corp. v. Martin Infante Co.,
272 F. 2d 231.
It is true
that original jurisdiction in this action was predicated on the Miller
Act which gives the Use Plaintiff the right to proceed directly against
the prime contractor's surety. The Use Plaintiff's theory in the
original complaint was that the subcontract had been performed by
York
and, as
York
's assignee, the action could be instituted directly against both Oil
Capital as principal, and American Employers' as surety, on the payment
bond.
The complexion
of the case changed, however, after the original Defendants answered
jointly, admitted liability, interpleaded the Government and paid into
the Court's registry account the disputed sum of $12,000.00. An amended
complaint was filed by Home Indemnity wherein its rights to the fund
were based upon two theories, the first as assignee of York Electric,
and the second on its rights as completing surety (subrogation). It is
on the second theory that Home Indemnity must prevail if at all. United
States v. Bess, supra; United States v. Acri [55-1 USTC ¶9138], 348
U. S. 211, 75 S. Ct. 239, 99 L. Ed. 264; United States v. City of New
Britain [54-1 USTC ¶9191], 347 U. S. 81, 74 S. Ct. 367, 98 L. Ed.
520; United States v. White Bear Brewing Company [56-1 USTC ¶9440],
350 U. S. 1010, 76 S. Ct. 646, 100 L. Ed. 871; United States v. Ball
Construction Company [58-1 USTC ¶9327], 355 U. S. 587, 78 S. Ct.
442, 2 L. Ed. 2d 510; cases wherein it was held that under Federal law
for a lien to be valid it must be choate, and in the case of a surety's
lien growing out of assignment it was inchoate, and therefore, not on
the same footing as the Federal tax liens.
The first
issue to be determined here is set out in Aquilino v. United States
[60-2 USTC ¶9538], 363
U. S.
509, 512; 80
S. Ct.
1277; 4 L. Ed. 2d 1365:
"The
threshold question in this case, as in all cases where the Federal
Government asserts its tax lien, is whether and to what extent the
taxpayer had 'property' or 'rights to property' to which the tax lien
could attach. In answering that question, both federal and state courts
must look to state law, for its has long been the rule that 'in the
application of a federal revenue act, state law controls in determining
the nature of the legal interest which the taxpayer had in the property
. . . sought to be reached by the state.' Morgan v. Commissioner
[40-1 USTC ¶9210], 309
U. S.
78, 82. * * * However, once the tax lien has attached to the taxpayer's
state-created interests, we enter the province of federal law, which we
have consistently held determines the priority of competing liens
asserted against the taxpayer's 'property' or 'rights to
property.'"
The Home
Indemnity rights arising by subrogation relate back to the date of the
execution of the performance bond. Prairie State Nat. Bank of Chicago
v. United States, 164 U. S. 227, 17 S. Ct. 142, 41 L. Ed. 412; Henningsen
v. United States Fidelity and Guaranty Company, 208 U. S. 404, 28 S.
Ct. 389, 52 L. Ed. 547; United States Fidelity and Guaranty Company
v. Sweeney, 80 F. 2d 235; Gilbertson v. Northern Trust Company,
53 N. D. 503, 207 N. W. 42; and it is entitled to the benefit of every
security for the performance of the principal obligation held by the
creditor at the time of entering into the contract of suretyship.
North Dakota
Century Code, Section
22-03-12
.
[Subcontractor
Had No Property Rights]
Under
North Dakota
law, York Electric had no "property" or "rights to
property" in the subcontract price to which Federal tax liens could
attach.
North Dakota
follows the general rule that a material failure of performance by one
party to a contract, not justified by the conduct of the other,
discharges the latter's duty to give the agreed exchange. North Dakota
Century Code, Section
9-01-16
; Kupfer v. McConville, 35 N. D. 622, 161 N. W. 283. Since the
Government's rights can rise no higher than those of York Electric,
there was nothing to which the liens could attach. Central Surety and
Insurance Corp. v. Martin Infante Co., Supra; Atlantic Refining Co. v.
Continental Casualty Co. [60-1 USTC ¶9413], 183 F. Supp. 478. It
appears to this Court that United States v. R. F. Ball Construction
Company, Supra, would control here, as the Government contends, only
if Home Indemnity was basing its action as
York
's assignee. As this Court understands it, the rationale of Ball
suggests that an assignment made by a subcontractor to his
performance-bond surety of all sums to become due for performance of the
subcontract, as security for any indebtedness or liability thereafter
incurred by the subcontractor to the surety, did not constitute the
surety a mortgagee of those sums within the meaning of the Internal
Revenue Code of 1939, Section 3672(a), as amended.
It does
appear, however, that since Aquilino, supra, and United States
v. Durham Lumber Company [60-2 USTC ¶9539], 363
U. S.
522, 80
S. Ct.
1285, 4 L. Ed. 2d 1371, the so-called "choateness" rule of Ball
has been restricted and the priorities will be established by state law.
This is high-lighted by the dissenting opinion of Mr. Justice Harlan in Aquilino,
supra, P. 521, wherein he says:
"*
* * If the federal standard of choateness is thought to be an
undesirable restriction on the States' freedom to regulate property
relationships, the cases establishing that standard should be expressly
overruled and not emasculated by dubious distinctions."
It is evident
then that Home Indemnity's subrogation rights take priority over the tax
liens of the
United States
. In Massachusetts Bonding and Ins. Co. v. State of New York
[58-2 USTC ¶9704], 259 F. 2d 33, 37, 38, the Court said:
"The
questions here are whether the bankrupt defaulted so as to bring into
operation the rights of the surety, and if so, whether these rights to
payments from the owner take priority over tax claims of the State of
New York
and the
United States
. Both the State and the
United States
vehemently argue that the default contemplated in the contract between
the bankrupt and the surety never occurred, and hence the assignment
never matured; nor did the surety acquire a lien by way of subrogation.
To some extent the arrangement created by the bankrupt and the surety
whereby construction costs were paid out of the joint account into which
they deposited progress payments supports this argument, for nominally
the bankrupt continued its operations subject only to financial
supervision by the surety. In this way construction activity never
ceased and bills were paid without material delay. But to analyze these
facts so as to deprive the surety of its claim based on subrogation when
it actually provided over $136,000 of its own money to pay laborers and
materialmen is too technical to warrant serious consideration. * *
*"
It is felt
that the foregoing quotation aptly describes the situation in the case
at bar.
[Surety
Itself Liable for Payroll Taxes]
The Government
is entitled to judgment on its cross-claim against Home Indemnity for
withholding taxes not paid but incurred in performance of the
subcontract.
Where a surety
issues a performance bond conditioned upon the faithful performance of a
contract in which there is no requirement that all taxes be paid, the
Government cannot recover on the bond for unpaid taxes incurred by a
defaulting principal. United States v. Crosland Construction Company
[55-1 USTC ¶9112], 217 F. 2d 275; Westower v. Wm. Simpson
Construction Co. [54-1 USTC ¶49,022], 209 F. 2d 908; General
Casualty Co. of America v. United States [53-2 USTC ¶9483], 205 F.
2d 753; United States Fidelity & Guaranty Co. v. United States
[53-1 USTC ¶9249], 201 F. 2d 118; First National Bank in Yonkers v.
City of New York [59-2 USTC ¶9639], 177 F. Supp. 175. An exception
occurs, however, where the surety guarantees the faithful performance of
all covenants and agreements in the contract, and these include an
agreement to pay all the taxes payable because of the work. United
States v. Phoenix Indemnity Company [56-2 USTC ¶9659], 231 F. 2d
573.
The contract
upon which Home Indemnity issued its performance bond provided that:
"The
Subcontractor (York) shall pay all taxes of whatever kind imposed by any
governmental authority in connection with his work, including but not
limited to sales taxes, unemployment compensation and social security
taxes. * * *"
But here the
performance bond specifically provides that:
"No
right of action shall accrue on this bond to or for the use of any
person or corporation other than the Owner herein or the heirs,
executors,
admin
istrators or successors of Owner."
And the
Government cannot recover as a third party beneficiary as it did in the
Phoenix
case.
United States
v. Island Constructors, Inc., 179 F. Supp. 133.
This Court
would be inclined to follow the view taken in Island Constructors,
supra, if it were not for the fact that
York
was merely the means utilized by Home Indemnity in completing the
subcontract. By this the Court means only that where the taxes are
incurred under the facts here present is the surety to be held liable.
The Court
finds that the Interpleaded Defendant, United States of America, is
entitled to judgment against The Home Indemnity Company upon the
Government's cross-claim in the sum of $2,345.25 plus interest, that
being the amount of the unpaid taxes arising out of the completion of
the subcontract on the Grand Forks Air Base.
The Court
further concludes that The Home Indemnity Company is entitled to
judgment in the sum of $12,000.00 against American Employers' Insurance
Company and Oil Capital Construction Company.
So far as the
Use Plaintiff, The Home Indemnity Company, and the Interpleaded
Defendant, the United States of America, are concerned, the ultimate
result is that of the $12,000.00 in the Clerk's custody the United
States is entitled to the unpaid taxes incurred in the prosecution of
the work called for by the subcontract, in the sum of $2,345.25,
together with interest thereon as provided by law, and The Home
Indemnity Company is entitled to the balance remaining.
No costs will
be allowed or assessed against any party to this litigation.
The attorneys
for the Use Plaintiff, The Home Indemnity Company, a corporation, will
prepare appropriate findings of fact, conclusions of law, order for
judgment and judgment, in conformance herewith and transmit them through
the Clerk of this court.
[53-1 USTC
¶9249]United States Fidelity and Guaranty Company, a corporation,
Appellant v. United States of America, Appellee
(CA-10),
In the United States Court of Appeals for the Tenth Circuit, No.
4497--November Term, 1952, 201 F2d 118, December 30, 1952
Appeal from the United States District Court for the District of New
Mexico.
Collection of income tax at source on wages: Liability of surety in
case of government contracts.--Appellant, surety on a
subcontractor's payment bond pursuant to a subcontract entered into with
a prime contractor for the construction of a public building, is not
liable for withholding taxes which the principal withheld from the wages
of its employees but did not pay to the Government, such delinquency not
being a breach of the subcontractor's contractual obligation to pay all
claims for wages and material. For the same reason the liability of the
subcontractor for the withholding taxes was not a part of the liability
of the contractor under its payment bond. Furthermore, the surety's
claim to the funds accruing from performance of the subcontract is
superior to the government's tax liens. When, after the subcontractor's
default on the contract, surety performed, it was subrogated to all the
rights that the prime contractor held against the subcontractor, and
these rights were effective from the date of the subcontract, which was
prior to the date when the Government's tax liens were perfected. One
dissent.
Justin T. Reid
and J. Harry Cross (A. K. Montgomery and Wm. R. Federici were with them
on the brief), for appellant, Louise Foster (Charles S. Lyon, Acting
Assistant Attorney General, Ellis N. Slack, A. F. Prescott, and Fred E.
Youngman, Special Assistants to the Attorney General, and Maurice
Sanchez, United States Attorney, were with her on the brief), for
appellee.
Before HUXMAN,
MURRAH and PICKETT,
United States
Circuit Judges.
HUXMAN,
Circuit Judge:
The
Construction Department of the United States Army entered into a
contract with C. H. Leavell and Company for the construction of the
Missile
Building
at White Sands Proving Grounds in
New Mexico
. Leavell entered into a subcontract with Kendrick Electric, Inc., for
performance of part of this work. The United States Fidelity and
Guaranty Company executed the payment bond for Kendrick required by the
Miller Act. 1
In the application for the bond Kendrick assigned to the surety company
as collateral to secure its obligations under the bond all right, title
and interest it had under the subcontract, including all retained
percentages, deferred payments, earned money, etc. Kendrick defaulted in
the discharge of its obligations under its subcontract. In addition to
claims for materials, supplies and equipment due from Kendrick, it was
also indebted to the
United States
for withholding taxes from its employees, withheld by it from their
wages but not paid to the Government. Demand being made upon Kendrick's
surety by Leavell, it paid all unpaid claims for materials, supplies and
equipment due from Kendrick. At that time there was due Kendrick from
Leavell on the subcontract the sum of $4,960.24. Conflicting claims were
asserted to this fund. The Government claimed prior right thereto in
satisfaction of its lien for federal income taxes and federal
unemployment taxes assessed against Kendrick. The surety company claimed
prior right thereto by virtue of the assignment of all funds in the
application by Kendrick for the bond. The trial court decided the issue
in favor of the Government. This appeal challenges the correctness of
that conclusion.
In its
conclusions of law the trial court held that Kendrick agreed to and
accepted full and exclusive liability for the payment of these
withholding taxes and that it was obligated to the
United States
for their payment and that under the surety company's bond for the
performance of Kendrick's obligations it became liable for their
payment.
It is true
that in Paragraph 12 of the subcontract Kendrick assumed and accepted
"full and exclusive liability for the payment of any and all
contributions or taxes for Unemployment Insurance and/or Old Age
Retirement Benefit, Pensions, or Annuities, * * *" imposed by the
Government and measured by the wages paid to its employees. But this did
not create the liability on Kendrick's part for the payment of these
taxes. It was merely declaratory of Kendrick's existing liability under
the federal tax laws.
26
U. S.
C. A. §1401(a) and 26
U. S.
C. A. §1622(a) deal with the imposition of withholding taxes. §1401(a)
provides that the tax imposed by §1400 shall be collected by the
employer by deducting the amount thereof from the employee's wage. §1622(a)
provides that "every employer making payment of wages shall deduct
and withhold upon such wages a tax equal to * * *." 26
U. S.
C. A. §1623 provides that "The employer shall be liable for the
payment of the tax required to be deducted and withheld under this
subchapter [§1622], and shall not be liable to any person for the
amount of any such payment." A similar provision is contained in 26
U. S.
C. A. §1401(b). By Treasury Regulation 116 §405.301 and Regulation 128
§408.304 the employer's liability for the tax attaches whether or not
he withholds it from the wages and the amount withheld from the wages of
an employee shall be allowed to him as a credit on his income tax
liability 2
and the Government shall make a credit or refund to the employee
"even though such tax has not been paid over to the Government by
the employer." 3
It is thus clear that Kendrick's liability for the payment of these
taxes arises by virtue of law and not because of any contractual
acknowledgment of the existing legal liability.
The trial
court's conclusion that Kendrick breached its construction contract with
Leavell was not predicated on the ground that it had failed to discharge
its tax liability for these withholding taxes to the Government. Rather
the court seems to have concluded that the sums withheld constituted
wages and failing to pay them over to the Government constituted a
breach of the contract requiring it to pay all wages. 4
This is also one of the contentions made by the Government on appeal. In
its brief the Government states: "The amounts covered by the liens
of the United States represent amounts deducted and withheld from wages
paid by Kendrick Electric, Inc., to its employees in the performance of
its subcontract. They represent a part of the liability assumed by the
prime contractor and its surety for the payment of labor and material
and to the extent of such withholding the
United States
succeeded to the rights of the wage earners by operation of law."
And that "Under the circumstances the United States succeeds by
operation of law to the rights of the wage earners to the amounts
deducted and withheld from wages as effectively as if it had taken a
written assignment from the wage earners covering the withheld portion
of their wages." However, from the statutes and regulations as set
out it seems clear that when an employer withholds the tax from an
employee's wage and pays him the balance the employee has been paid in
full. He has received his full wage. Part of it has gone to pay his
withholding tax and the balance he has. The employer has discharged his
contractual obligation to pay the full wage. Thereafter there remains
only his liability for the tax which he has collected. That is a tax
liability for which he alone is liable to the Government as for any
other taxes which he may owe. 5
The Government
in its brief cites a line of cases in support of its contention that
failure to pay taxes such as these imposes liability under similar
payment bonds. A detailed analysis of each case would unduly extend this
opinion. Typical of this line of cases are Standard Insurance Co. v.
United States, 302
U. S.
442, and Illinois Surety Co. v. John Davis Co., 244
U. S.
376. In the Standard Insurance Company case the Supreme Court
held that a common carrier's claim for freight charges for the
transportation of materials used in the construction of a federal
building was one for labor and materials within the meaning of the act
requiring the bond, and in the Illinois Surety Company case the
Supreme Court held that the rental for cars and the expense of loading
the plant there involved and freight thereon used in fulfillment of the
contract constituted labor and materials within the act requiring a bond
from the contractor. The facts in the other cases relied upon also
distinguish them and make them inapplicable to the question before us.
These cases as well as the others all hold that the Miller Act and the
acts preceding it should be liberally construed in determining what
constituted furnishing labor, material or supplies, but no case to which
our attention has been called goes so far as to hold that an employer's
tax liability is within the provision of the bond merely because wages
were used in paying the employee's tax liability and creating that of
the employer.
[Payment
Bond Does Not Cover Tax Obligations]
The Government
further asserts that "The liability of the subcontractor to deduct
and withhold a part of the wages of its employees, and to pay over to
the Collector the portion of wages so withheld, was as much a part of
the liability of the prime contractor under its Miller Act bond to pay
for labor and material as was its liability to pay the net 'take-home'
wages of such employees." The reasons that impel us to conclude
that Kendrick's liability for these taxes was not a liability for the
payment of wages and that failure to pay them to the Government was not
a breach of its contractual obligation to pay all wages and material
claims requires the same conclusions with respect to this contention.
The debate on the floor of Congress indicates that the performance bond
of the Miller Act was to make the contractor liable for default by
reason of his inability to complete the contract or by reason of failing
to meet the requirements and specifications as to material, and that the
payment bond was to insure the contractor's liability for claims of
subcontractors, material-men and laborers. 6
There is nothing in the legislative history of the Miller Act or the
acts which it succeeded to indicate that the performance bond was to
cover any obligations other than the requirement that the contractor
complete his contract according to its specifications.
[Priority
of Surety's Claim Over Tax Liens]
Finally it is
contended that the Government's lien for these taxes is superior to the
surety's claim to these funds. This contention has been decided against
the Government in a series of cases. As pointed out in the application
for the payment bond, Kendrick assigned to the surety company all its
right, title and interest in and to any funds it was entitled to receive
from the principal contractor, Leavell, to indemnify it against
liability to which it might become subjected by virtue of Kendrick's
breach of its construction subcontract. At the time the surety company
became liable and discharged its liability by paying all material,
supply and labor claims, the fund in question was due Kendrick from
Leavell. When a surety is called upon and makes good under its contract
of suretyship upon default of its principal, it acquires an equitable
lien against any sum remaining in the hands of the one for whose
protection the bond was written due to its principal upon discharge of
his obligation under its bond. This equitable lien relates back to the
date of the contract and is superior to a Government lien for unpaid
taxes subsequent to the date of the contract of suretyship, although
prior to the date of payment by the surety. 7
The case of
the United States v. Security Tr. & Sv. Bank, 340
U. S.
47 [50-2 USTC ¶9492], upon which the Government relies is
distinguishable upon the facts. There it was held that the equitable
doctrine of relation back will not operate to defeat the specific and
perfected tax lien of the
United States
. In that case the Federal Government had perfected its tax lien against
real estate belonging to a defendant debtor in the state court in an
action in which the plaintiff had caused an attachment lien to be filed
against the debtor's property. Under
California
law the attachment gave him only an inchoate lien which became perfected
upon the entry of judgment. The effect of the decision by the Supreme
Court is that the judgment subsequent to the perfection of the
Government's tax lien did not relate back to the date of the filing of
the attachment so as to give the judgment creditor a lien superior to
the tax lien of the Government. It is to be noted that both liens
attached to property belonging to the defendant debtor, property that
was his at all times. Such is not the case here. On the date of the
execution of the subcontract the prime contractor had a specific right
of ownership in any funds accruing to the subcontractor from the
performance of his subcontract. The right to withhold these funds upon
default was superior to any other claim against the fund as the property
of the subcontractor. When the subcontractor defaulted and its surety,
the appellant in this case, performed, it stepped into the shoes of the
prime contractor and was subrogated to all rights that it held against
the subcontractor. Those rights related back to the date of the
subcontract and were effective from the date thereof. This was in point
of time prior to the perfection of the Government's tax liens. Actually
the defaulting subcontractor had no right to this fund. It owed the
principal contractor more than was due to it from such principal
contractor. As between the Government and appellant surety who stepped
into the shoes of the principal contractor, the Government could acquire
no greater right to this fund than the subcontractor had.
The judgment
of the trial court is REVERSED and the cause is remanded to proceed in
conformity with the views expressed herein.
1
40
U. S.
C. A. 270a.
2
26
U. S.
C. A. §35.
3
Treasury Regulation 116 §405-401.
4
In its conclusion of Law No. 2 the court stated that "Under the
terms of the subcontract, Kendrick Electric, Inc., was and is obligated
to pay all wages due labor used in performance of such sub-contract and
that the withholding taxes for which the United States makes claim are
part of the wages due said labor, having been previously deducted and
withheld by the employer, and that under the surety bond, on default by
said employer Kendrick Electric Inc., the surety, plaintiff herein,
became liable for the payment of such withholding taxes."
5
United States
v.
New York
, 315
U. S.
510.
6
Congressional Record, Volume 79, Page 13, 382.
7
Glenn v. American Surety Co., 160 Fed. (2d) 977 [47-1 USTC ¶9220];
New York Casualty Co. v. Zwerner, 58 Fed. Supp. 473 [45-1 USTC ¶9140];
Farmers' Bank v. Hayes, 58 Fed. (2d) 34; Prairie State Bank v.
United States
, 164
U. S.
227.
PICKETT,
Circuit Judge, dissenting:
It seems to me
that my colleagues take too narrow a view of the coverage intended by
the terms of the performance and payment bond in this case. Under the
statute and the provisions of the bond, the surety has the primary
obligation to pay the wages of the laborers upon default of the
contractor. This obligation extends to the full amount of the wages
earned and not just a percentage or portion of them. I can see no reason
why this obligation should be diminished because the law requires that a
portion of the wages be diverted to the
United States
for the payment of income taxes and other benefits for the wage earners.
By holding the surety responsible for the amounts withheld from the
wages under the law, no more is required than what the surety agreed to
do and for which it was paid a premium. To so hold does not injure or
mislead the surety or extend its liability in any manner.
Where a wage
earner has assigned his wages or a portion of them to a third party, the
surety is responsible to the assignee if the employer defaults. U. S.
Fidelity and Guaranty Co. v. Bartlett, 231 U. S. 237; Title
Guaranty & Trust Co. v. Crane Co., 219 U. S. 24; Third
National Bank of Miami v. Detroit Fidelity & Surety Co., 5 Cir.,
65 Fed. (2d) 548, certiorari denied, 290
U. S.
667; United States v. Rundle, 9 Cir., 100 Fed. 400; National
Market Co. v. Maryland Casualty Co., 100 Wash. 370, 170 Pac. 1009; Northwestern
Nat. Bank v. Guardian Casualty & G. Co., 93 Wash. 635, 161 Pac.
473; 43 Am. Jur., Public Works and Contracts, Sec. 152; Anno. 77
A. L. R. 149. I see no essential difference in this case and the
assignment cases. The liability remains exactly the same as though the
full amount of the wage earned was due to the wage earner. Under such
conditions, the surety should bear any loss in the total amount of the
wages earned even though a portion of the wages bears the label of a
tax. This type of case is easily distinguishable from those where it was
sought to hold the surety liable for ordinary taxes of the employer.
In determining
whether the amounts withheld are part of wages earned or strictly a tax,
the provisions of the Miller Act and the bond should be given a liberal
construction to require full coverage of the bond. Fleisher
Engineering & Construction Co. v. United States, 311 U. S. 15; Massachusetts
Bonding & Ins. Co. v. United States, 5 Cir., 88 Fed. (2d) 388. I
would affirm the judgment.
[69-1 USTC
¶9148]Fireman's Fund Insurance Company, Appellant v. C. S. Leonard,
Individually and Trading as Leonard Excavating Company, W. W. Wendell
Company, Inc., a Pennsylvania Corporation and Agricultural Insurance
Company, a New York Corporation
(CA-3),
U. S. Court of Appeals, 3rd Circuit, No. 17170, 10/1/68, Aff'g an
unreported District Court opinion
[Code Sec. 6323 prior to enactment of P. L. 89-719]
Lien for taxes: Notice: Surety's interest: Subrogation.--A
surety's interest in certain materials subject to a federal lien for
unpaid withholding taxes did not ripen until after the lien was filed.
The surety had notice of the lien and could not, consequently, claim
ownership by reason of subrogation.
Rob
ert F. McCabe, Jr., 930 Grant Bldg.,
Pittsburgh
,
Pa.
, for appellant. James C. Larrimer, Dougherty, Larrimer, Lee &
Hickton, Grant Bldg.,
Pittsburgh
,
Pa.
, for appellees.
Before BIGGS,
FREEDMAN and VAN DUSEN, Circuit Judges.
Opinion
of the Court
PER CURIAM:
Fireman's Fund
Insurance Company, a
California
surety company doing business in
Pennsylvania
, appeals to this court from the denial of its motion for a new trial in
the court below. The facts are as follows.
On
December 26, 1963
, Stanton Construction Company entered into a written contract with the
Lower Yoder Municipal Authority of Cambria County, Pennsylvania, for the
construction of a sewage collection system. Pursuant to the contract
Stanton
gave bonds for the faithful performance of the contract and the payment
for materials and labor furnished. Fireman's Fund was surety on the
bonds. The United States made an assessment under Sections 3402-03 of
Chapter 24 ("Collection of Income Tax at Source on Wages") of
the Internal Revenue Code of 1954 (26 U. S. C. §§ 3402-03 (1958)),
against Stanton for the fourth quarter of 1963 and for every quarter of
1964, the last assessment date being November 4, 1964. Notice of liens
was filed in the offices of the Prothonotary and Recorder of Deeds for
Allegheny
County
on
November 9, 1964
. The
United States
then executed on
Stanton
's assets. It is clear that all interested parties including Fireman's
Fund had notice of the liens when filed.
On
November 25, 1964
Stanton
was declared in default by the Municipal Authority. At that time
Stanton
was in possession of pipe and other materials for which payment had not
been made. Fireman's Fund paid the materialmen and by reason of these
payments acceded to
Stanton
's interest in the materials under the assignment provisions of the
bonds. On
May 27, 1965
the
United States
sold the pipe and other materials at public sale to Wendell and Leonard,
the new contractors. The Internal Revenue Service thereupon issued a
certificate of sale to Wendell and Leonard. Fireman's Fund objected to
these proceedings claiming ownership of the pipe.
The suit at
bar is to recover the value of the pipe, Fireman's Fund contending that
the material in question belonged to it by reason of subrogation. The
argument is without merit. The federal tax lien was good against all
persons having notice of it. See 12A P. S. §9-401(a) and 26 U. S. C.
§§ 6321-22. Fireman's Fund is merely a general creditor. Its rights as
subrogee did not ripen until the declaration by the Municipal Authority
of the default, by which time the federal tax liens had already been
filed.
Accordingly,
the judgment will be affirmed.
[47-1 USTC
¶9220]Seldon R. Glenn, Collector, Appellant, v. American Surety Company
of
New York
and the New York Casualty Company, Appellees
(CA-6),
United States Circuit Court of Appeals, Sixth Circuit, No. 10302, 160
F2d 977, Decided April 1, 1947
Appeal from the District Court of the United States for the Western
District of Kentucky.
Procedure: Correction of appeal record.--The Collector filed
notice of appeal from a District Court decision, but did not file a
record. The
United States
filed a record, but not a notice of appeal. The Court, in the discretion
granted it by Rule 73(g) of the Federal Rules of Civil Procedure, grants
the motion of the
United States
to correct the caption of the record, instead of dismissing the appeal.
Prohibition of suits to restrain assessment or collection:
Application to third parties.--The statutory prohibition against
suits to restrain the assessment or collection of taxes (Code Sec. 3653)
applies to such suits by taxpayers, not to a third party seeking to
enjoin the Collector from taking his property to pay the taxes of
another.
Lien for taxes: Validity against sureties of taxpayer: Prior liens.--Lien
for taxes is invalid against a taxpayer's surety's claim for interest
upon the amount expended by it in making good under its contract of
suretyship upon default of its principal (taxpayer). (The right of the
sureties to recover their expenditures in principal amount is not here
challenged.) One dissent. Affirming the decision of the District Court
in American Surety Company of New York et al. v. City of Louisville
Municipal Housing Commission et al., 63 Fed. Supp. 486.
Irving I.
Axelrad, Washington, D. C., Sewall Key, Louis Monarch and Norman S.
Altman, Washington, D. C., David C. Walls and A. Roy Copeland,
Louisville, Ky., with him on brief, for appellant.
Rob
ert L. Blackwell, Louisville, Ky., William Marshall Bullitt and R. Lee
Blackwell, Louisville, Ky., with him on brief, and Bullitt &
Middleton, of counsel, for appellees.
Before SIMONS,
ALLEN and MARTIN, Circuit Judges.
[The
Issue]
SIMONS,
Circuit Judge.
The only
substantive question that appears to be left of the controversy in the
present posture of the appeal, is whether sureties for the faithful
performance by a contractor after satisfying the debts of their
principal, are entitled to interest upon the amounts expended,
recoverable out of retained percentages as against the claim of the
government for taxes asserted against the same funds. The right of the
sureties to recover their expenditures in principal amount, though
unsuccessfully contested below, is not here challenged. Before reaching
that question, however, it becomes necessary to solve a procedural
problem raised by the appellees' motion to dismiss the appeal, and a
motion of the appellant to correct the caption of the record.
[The
Facts]
The
controversy arose out of the following circumstances. On
October 3, 1941
, one W. J. Paul entered into a contract with the Louisville Municipal
Housing Commission to perform certain public housing construction work.
Paul, as principal, and the appellees as sureties, delivered to the
Housing Commission a faithful performance bond in the penal sum of
$540,214, guaranteeing the faithful performance of the construction work
and the payment of all obligations incurred in connection with it. Paul
completed the contract but defaulted in the payment of labor and
material claims in amounts totaling $52,571.57. Pursuant to the terms of
the contract the Housing Commission withheld from Paul $59,647.72. On
August 12, 1943
, Glenn, Collector of Internal Revenue for
Kentucky
, served a notice of levy and a warrant for distraint upon the Housing
Commission for delinquent internal revenue taxes owed by Paul, in the
amount of $13,029.28. The Kentucky Unemployment Compensation Commission
also filed a lien against the fund, but since it has not appealed its
claim of lien disappears from the case. Upon being notified that the
Housing Commission proposed to pay the federal tax out of the retained
percentages, the sureties brought suit to restrain the Commission from
paying any money to the Collector until their claims were satisfied, and
for a declaration of right that their claims were prior liens against
the retained fund. A temporary restraining order was followed by a
temporary injunction and the sureties paid the claims against Paul in
amounts totaling $52,571.57. The Collector was made a party defendant to
the suit, the United States intervened and, upon motion for summary
judgment, the sureties were adjudged to have an equitable lien upon the
fund which had, in the meanwhile, been deposited in the registry of the
court, in an amount covering their payment of the debts of Paul with
interest from the date of payment, and the clerk of the court was
directed to make payment to them out of the fund on deposit in the
registry. The facts are not in dispute and are sufficiently recited in
the memorandum of the district judge. American Surety Co. et al. v.
Louisville
Municipal Housing Commission et al., 63 Fed. Supp. 486.
On
March 8, 1946
, and within the jurisdictional period, the Collector filed a notice of
appeal. After several extensions a record was filed and the appeal
docketed in the name of the
United States
on
July 17, 1946
. Subsequently, a motion was filed to correct the notice of appeal by
substituting the
United States
, intervenor, for the Collector, and on July 29 an order was entered
correcting the notice of appeal pursuant to the motion. Thereafter, by
stipulation, the order of July 29 was vacated, and on October 16 an
order was entered denying the motion of July 17, but without prejudice
to a consideration of the rights of the
United States
as they may appear at the hearing of the case upon its merits. In
January, 1947, the sureties moved to docket and dismiss the appeal of
Glenn because he had failed to file a record and to docket his appeal on
or before the return date, as enlarged, and to dismiss the appeal of the
United States
because it had failed to file a notice of appeal within the required
time. The
United States
thereupon moved that the caption of the record and docket entry be
corrected by a nunc pro tunc decree substituting the Collector
for the
United States
as the appellant.
[Correction
of Caption of Record and Docket Entry]
We have, then,
this situation. The Collector filed the notice of appeal but did not
file a record. The
United States
filed a record but had failed to notice an appeal within the statutory
period. The
United States
now seeks to correct the docket by substituting Glenn as the appellant,
which the sureties oppose. The sureties seek a dismissal of the appeal
because of the variance between the party filing the notice and the
party perfecting the record. Rule 73(g) of the Federal Rules of Civil
Procedure, requires a docketing of the appeal within 40 days from the
date of notice, and Rule 73(a) provides that the failure of the
appellant to take any further steps following his notice of appeal will
not affect its validity, but is ground for such remedies as may seem
appropriate to the appellate court, including dismissal of the appeal.
That remedy the sureties would now have us apply. Our jurisdiction
attaches at the time of filing the notice of appeal, and whether a
dilatory appellant should be allowed to proceed is within our
discretion. Ispass v. Pyramid Motor Freight Corp., 152 Fed. (2d)
619 (C. C. A. 2). This discretion could be exercised if we grant the
motion of the United States to correct the caption of the record, which
would make it Glenn's record filed out of time, and this we think ought
to be done for it is apparent that the caption of the record was a
clerical error made by the United States Attorney who represented both
the Collector and the United States as intervenor. The courts, in
general, have liberally construed the rule. Mosier v. Federal Reserve
Bank, 132 Fed. (2d) 710 (C. C. A. 2); Ainsworth v. Gill Glass
& Fixture Co., 104 Fed. (2d) 183 (C. C. A. 3); National
Surety Co. v. Williams, 110 Fed. (2d) 873 (C. C. A. 8).
A more
fundamental and less technical ground for permitting the extension and
correction, however, appears. The Collector, in asserting the rights of
the
United States
to the reserved fund for the payment of Paul's taxes, was acting not in
his individual capacity but as the agent of the
United States
. Second Nat'l Bank of
Saginaw
v. Woodworth, 54 Fed. (2d) 672 (D. C., S. D. Mich.) [1932 CCH ¶9049],
affirmed 66 Fed. (2d) 170 (C. C. A. 6) [1933 CCH ¶9429]. While he was
the formal party defendant, the real party in interest was the
United States
, which, by its intervention in the suit, likewise became a formal party
thereto. The interests of the Collector and the
United States
were, however, identical. The tax, if collected, would be remitted to
the Treasury of the
United States
. The appeal could have been prosecuted either by Glenn or the
government. While it has been held, Sage v. U. S., 250 U. S. 33
[1927 CCH ¶7184], that a suit against the Collector for the recovery of
an illegally held tax is not a suit against the United States, in
respect to the application of the doctrine of res judicata, yet it has
also been held that a judgment for or against the United States is
binding upon the Collector who is the agent or trustee for the
government. Second Nat'l Bank of
Saginaw
v. Woodworth, supra. However, it has been with great clarity pointed
out that a suit against a Collector is today "an anomalous relic of
bygone modes of thought" when he is engaged merely in the
fulfillment of a ministerial duty. Moore Ice Cream Co. v. Rose,
289
U. S.
373, 382 [3 USTC ¶1100]. There Mr. Justice Cardozo observed,
"There may have been utility in such procedural devices in days
when the Government was not suable as freely as now (citing cases). They
have little utility today, at all events where the complaint against the
officer shows upon its face that in the process of collecting he was
acting in the line of duty, . . . In such circumstances his presence as
a defendant is merely a remedial expedient for bringing the Government
into court." Whether the present appeal could be by us entertained
in the name of the United States, in view of this identity of interest
between the government and the Collector, we need not now decide, but
viewing the present situation realistically, we are not persuaded that
the appeal should fail because the United States Attorney, through
neglect, excusable or otherwise, failed to caption the record in the
name of the Collector who had filed the notice of appeal. We held in Toledo
Edison Co. v. McMaken, 103 Fed. (2d) 72 [39-1 USTC ¶9447], cert.
den. 308 U. S. 569, that while a Collector could expressly or by
indirection waive the statute of limitations in a suit against him, he
could not impart to such waiver the obligation which the statute, Title
28 U. S. C. A., §842, imposes upon the government under certain
circumstances to pay a judgment rendered against him individually.
Similarly, we think, a neglect by the Collector to caption a record on
appeal to conform to the notice of appeal, may not deprive the
government of its hearing on appeal where the government is not only the
real party in interest but is likewise a formal party, and now, by its
motion, seeks to have the record conform to the notice. Wherefore, we
conclude that the motion to dismiss the appeal must be denied and the
motion to correct the caption of the record granted.
The contention
of the sureties that if the Collector's name is substituted for that of
the United States upon the record and docket entry, he cannot bring this
appeal because of the provisions of Title 28 U. S. C. A., §732, which
requires that all suits for recovery of taxes must be brought in the
name of the United States, is, of course, without merit. The present
suit was not brought by the Collector. He was made a party defendant at
the suit of the sureties, and it would be novel doctrine, indeed, to
hold a Collector, subjected to an adverse judgment, to be deprived, by
reason of this statute, of the right to appeal. It was said in Moore
Ice Cream Co. v. Rose, supra, "One who is brought before the
court as a formal party only will not be heard to object that there has
been a denial of due process in enlarging the liability to be borne by
someone else." Similarly, it may be said that those who bring
before the court one who is only a formal party will not be heard to
challenge the right of such party to defend the suit or to review an
adverse judgment.
[Suit
to Restrain Assessment or Collection of Tax]
Coming to the
substantive issue of law, the appellant is in the anomalous position of
declining to assail the judgment for the amount paid by the sureties,
yet contesting the award of interest thereon on the ground that it
violates §3653 of the Internal Revenue Code which, with certain
exceptions, forbids a suit to restrain the assessment or collection of a
tax in any court. The short answer to the contention, if it is still in
the case, is that given by the district judge in his preliminary
memorandum of December 31, 1943, "The statute, however, applies to
actions by taxpayers; it does not apply to a third party seeking to
enjoin the Collector from taking his property to pay taxes of another. Tomlinson
v. Smith, (C. C. A. 7th), 128 Fed. (2d) 808 [42-2 USTC ¶9540]; Rothensies
v. Ullman, (C. C. A. 3rd) 110 Fed. (2d) 590 [40-1 USTC ¶9308]; Long
v. Rasmussen, Collector, 281 Fed. 236. See Hubbard Investment
Company v. Brast, Collector (C. C. A. 4th) 59 Fed. (2d) 709, 710
[1932 CCH ¶9366]." Neither the validity nor the timeliness of the
tax nor the correctness of the amount sought, is here assailed, and the
plaintiffs in the suit are under no obligation to pay the tax.
[Validity
of Tax Lien]
There is left
the contention that a surety is generally not entitled to interest upon
its claim, and that the tax lien is superior to the interest charge
because the latter is an unsecured claim against Paul which arose after
the effective date of the tax lien. As to the first, the prevailing rule
is that a surety has a right to be made whole when it fulfills its
obligations under a contract of suretyship, and this includes interest
upon the money expended by it in fulfilling its obligations until
repaid. American Law Institute, Restatement of Security, §104; Memphis
& Little Rock R. R. Co. v. Dow, 120 U. S. 287; American
Surety Co. v. Carbon Timber Co., 263 Fed. 295 (C. C. A. 8). The rule
that interest is not allowable on claims against a bankrupt or insolvent
estate, as illustrated in Thomas v. Western Car Co., 149 U. S.
95, is not applicable here and rests upon a different principle. Where
there is not enough money to pay all lienholders of the same rank
entitled to share in the estate of a bankrupt or an insolvent, the
disallowance of interest on all claims is but in pursuance of the rule
of equitable treatment to all claimants. Nor is the rule which denied to
a surety a profit on a building contract which it completes in default
of its principal, available to the appellant. While interest may, in
certain aspects, be considered as a profit to the lender or investor, it
is not profit within the doctrine of authorities exemplified by Fidelity
& Guaranty Co. v. Worthington & Co., 6 Fed. (2d) 502 (C. C.
A. 5), cert. den. 269
U. S.
583; Lacy v. Maryland Casualty Co., 32 Fed. (2d) 48 (C. C. A. 4).
Nor is it within the purview of those cases which deny to the surety the
right to retain funds which accrue to it by reason of a favorable
compounding of the debts of its principal as illustrated in Laber v.
Gall, 110 Fed. (2d) 697 (C. A., D. C.); Martin v. Ellerbe's
Adm'r, 70
Ala.
326; Coggeshall v. Ruggles, 62
Ill.
401. The principle applied in rendering the presently assailed judgment,
is the right of the sureties to be made whole, and profit is not
involved.
There remains
the appellant's final contention that the claim for interest is
unsecured in that it arose after the levy of the tax lien. We agree with
the district judge that a surety who makes good under his contract of
suretyship upon default of the principal contractor, acquires an
equitable lien against the unpaid balance in the hands of the person in
whose favor the bond runs, and that such equitable lien upon payment by
the surety relates back to the date of the contract and is superior to a
claim of the United States for unpaid taxes for periods subsequent to
the date of the contract of suretyship, although prior to the date of
payment by the surety. In re Zaepfel and Russell, 49 Fed. Sup.
709, aff. Farmers State Bank v. Janes, 135 Fed. (2d) 215 (C. C.
A. 6); Farmers' Bank v. Hayes, 58 Fed. (2d) 34 (C. C. A. 6); Prairie
State Bank v.
U. S.
, 164
U. S.
227. The cases relied upon by the appellant are not contra. New York
v. Maclay, 288 U. S. 90, involved 31 U. S. C. A. §191, which
provides that when a person indebted to the United States is insolvent
and the estate insufficient to pay all debts of the deceased, those due
the United States shall be first satisfied. No disposition of an
insolvent's estate is here involved, and the statute has no present
application.
U. S.
v. City of
Greenville
, 118 Fed. (2d) 963 (C. C. A. 4) [41-1 USTC ¶9381]. Michigan v.
U. S., 317
U. S.
338 [43-1 USTC ¶9225], is further afield. It rejected the contention
that a
Michigan
statute declaring state taxes to be a first lien upon real property on
specified dates, could create a priority against an earlier lien for
federal taxes under the Supremacy Clause of the United States
Constitution, Art. 1, §8, "Hence it is not debatable that a tax
lien imposed by a law of Congress, as we have held the present lien is
imposed, cannot, without the consent of Congress, be displaced by later
liens imposed by authority of any state law or judicial decision."
Conceiving the liens of the sureties to have been created by the
contract and effective as of its date, the doctrine in the
Michigan
case has no present application.
[Conclusion]
The motion to
dismiss the appeal is denied, the motion to correct the docket and
caption of the record by substituting Seldon R. Glenn, Collector, for
United States of America
, is granted, and the judgment below is
AFFIRMED.
[Dissenting
Opinion]
MARTIN,
Dissenting.
I would
reverse the judgment and remand this cause to the district court, with
direction that the sum of $7,076.15 be paid from the funds in the
registry of the court to the United States Collector of Internal Revenue
in partial payment of the tax lien of the
United States
for $13,029.28.
It may be
conceded that, in ordinary circumstances, a surety who makes good under
his contract of suretyship upon default of the principal contractor
acquires an equitable lien against the unpaid balance in the hands of
the obligee of the bond and that such equitable lien, upon payment by
the surety, relates back to the date of the contract. But, to my
thinking, it does not follow from this that such equitable lien is
superior to the perfected lien of the United States for unpaid taxes of
the defaulting contractor, for periods subsequent to the date of the
contract of suretyship but prior to the date of payment by the surety,
to the extent that interest must be allowed the surety on the principal
sum paid by it when such allowance would completely exclude the
Government tax lien, which attached to the funds involved before the
surety expended money in performance of its obligation under the bond.
Nor do I think
the authorities cited, but not discussed, in the opinion of the court
support the conclusion reached. In re Zaepfel and Russell, 49
Fed. Supp. 709, aff. Farmers State Bank v. Jones, 135 Fed. (2d)
215 (C. C. A. 6); Farmer's Bank v. Hayes, 58 Fed. (2d) 34 (C. C.
A. 6); Prairie State Bank v.
United States
, 164
U. S.
227. None of these cases dealt either with interest or with tax liens.
The controversies in them were between surety companies and banks, and
were decided upon principles of subrogation, by which priority was
accorded to the claims of the sureties over the claims of banks
advancing money to the contractors.
In this case,
the obligee of the faithful performance bond who had in possession
retained percentages was served by the Collector with a notice of levy
and warrant for distraint on
August 12, 1943
, followed by service of final notice and demand on
August 16, 1943
. The Collector appropriately recorded his notice of tax lien on
August 13, 1943
. The obligee notified the sureties that, on
August 20, 1943
, the $13,029.28 internal revenue taxes claimed out of the $59,647.72
retained percentages in its hands would be paid to the Collector, in
compliance with his demand, unless the obligee was restrained from doing
so. On
August 19, 1943
, payment to the Internal Revenue Collector was stayed, and
ultimately enjoined, by the filing of this action by the sureties.
After the
sureties paid off the material and labor claims, there were sufficient
retained funds ($59,647,72) in the hands of the obligee to pay in full
the amount expended by the sureties ($52,571.57) and leave a balance of
$7,076.15 to be paid pro tanto on the tax lien of the United
States, if this action had not been brought. To allow the surety
companies to absorb this sum in interest, to the exclusion of the
United States
in the partial collection of its taxes, seems to me inequitable in the
circumstances. Such allowance is certainly not supported by direct
authority.
Moreover, my
reasoning by analogy differs from that of the majority opinion. The
question before us is new; but the facts here are not too far afield to
enable us to receive guidance from the applicable rules in bankruptcy,
receivership and reorganization proceedings. It should be remembered
that while no insolvency proceedings were pending against the
contractor, he was nonetheless insolvent at the time this action was
brought. See Vanston Bondholders Protective Committee v. Green,
--
U. S.
--, decided
December 9, 1946
, for discussion of the balancing of equities with respect to the
allowance of interest in bankruptcy, receivership and reorganization
matters. See New York v. Maclay, 288
U. S.
290, for discussion of the priority of
United States
tax claims over claims of a state for franchise taxes given precedence
by state law over other intervening claims. Upon the principles
derivable from these authorities and from Michigan v. United States,
317 U. S. 338, and upon logical reasoning, I think the equitable lien of
the sureties is equitably satisfied by reimbursement to them of the
principal sum expended in fulfilment of their obligation, without added
allowance of interest on such amount.
A surety is
limited to recovery of his actual loss, and no profit may be made by him
at the expense of other creditors of his principal. While interest is
not generally the equivalent of profit, it may become so when balanced
against the equities of other creditors of the principal. Especially is
this true when, as in the instant case, the
United States
is a tax-lien creditor protesting against the allowance of six percent
interest on a related-back lien accruing from the insolvency of a
defaulting principal, whose faithful contractual performance the surety
had guaranteed. There are relatively few six percent investments in the
portfolios of insurance companies.